Nones v. Ponce School Board

25 P.R. 17
Supreme Court of Puerto Rico·Decided March 16, 1917·No. No. 1447·Published

Opinion

MR. Justice Aldrey

delivered the opinion of the court.

. As the appellant bases this appeal principally on the allegation that the lower court committed manifest error in weighing the evidence and that the judgment rendered was a consequence of such error, it is necessary to state the funda[18]*18mental issue between the parties and review the evidence introduced at the trial.

- The school board of Ponce authorized the construction of a school building in that city under “Job 63,” subject to the inspection and supervision of the Commissioner of the Interior and his subordinates, and on July 15, 1913, the chairman of the said board, the Commissioner of the Interior and José A. Bruno entered into a contract in which Bruno agreed to construct the building for $33,735. After completing the foundations, Bruno, with the assent of the other contracting parties, assigned the contract on October 25 to Adolfo Nones, a civil engineer. Two days later Nones took charge of the \york and on November 14 began to erect the walls upon the said foundations and had laid three courses of concrete about •three feet high each, having begun the laying of the first <on said day, the second on November 22, which was completed on November 26, and the third on November 28, which was completed on December 2, when he received orders from superintendent of construction Nelson to suspend the concrete' work because the concrete used in the three courses already laid was soft, and two or three days later the contractor suspended all work on the building in accordance with the orders of the said superintendent. The Commissioner of the Interior caused the walls to be examined and on January 8 ordered contractor Nones to tear them down and build new walls because the concrete was soft and utterly unsuitable for the work in which it was being used. ' Nones asked whether that work was to be done at his expense or that of the school board and was informed that it was for his account, whereupon Nones stated that he was not disposed to assume a liability which he had not incurred, and on January 28 he was notified that unless he began to remove the defective concrete within five days it would be necessary to rescind the contract. On the day following Nones filed the complaint in the present action against the Ponce school board and the [19]*19Commissioner of the Interior, but later amended tire same by eliminating tbe latter.

Tbe walls were torn clown in March and tbe work continued without tbe said contractor.

Tbe parties admit that tbe concrete employed in tbe three courses of tbe walls constructed by Nones was soft at tbe time be received tbe order to suspend work and that it could be crumbled with tbe fingers, therefore tbe principal issue in this action is whether this was tbe fault of Nones.

As fundamental grounds of bis action for tbe resolution of tbe contract and to recover certain sums as damages, Nones alleged that all tbe materials composing tbe concrete for tbe walls were previously examined and accepted by superintendent of construction Nelson and bis inspectors, who were present personally and saw all of tbe work done on tbe said construction; that in doing tbe work be complied with bis contract in every particular and adhered to tbe ordinary technical and practical rules and requirements, using first-class equipment and machinery, and mixing, laying and setting tbe concrete with tbe greatest care and for tbe time necessary to obtain, as be did, a concrete of superior quality and of much greater strength than that required for tbe building, and that the order to demolish tbe work done by him was entirely arbitrary, contrary to tbe opinions of tbe engineers of tbe Department of tbe Interior, inspired by negligence and erroneous judgment and in disregard of bis rights, showing bad faith and failure to exercise honest discernment.

/ In answer to these allegations tbe defendant averred that tbe sand and gravel employed by tbe plaintiff in making tbe concrete for tbe walls were inferior; that they were never accepted by tbe person authorized to do so because they did not conform to tbe stipulations of tbe contract or to tbe specifications for tbe work; that tbe plaintiff was warned that their use would not be allowed unless he washed and sifted them, and that tbe plaintiff did not comply with tbe contract or with tbe conditions required by tbe plans and specifications [20]*20for the work or with the ordinary technical and practical rules, but used concrete of a quality inferior to that stipulated for which made the collapse of the building certain. The defendant also filed a counterclaim alleging* that Nones did not comply with the contract but built the walls with concrete of a quality inferior to that agreed upon; that he did not tear down the walls when he was ordered to rebuild them at his own expense, therebjr making* it necessary for the Department of the Interior to do the work; that Nones had contracted to complete and deliver the building on February 28, 1914; that his failure to do so compelled the defendant to rent other buildings for school purposes, and that he had furnished a bond for $6,000 to guarantee the fulfilment of the contract. It was prayed that the court declare the contract rescinded and the bond forfeited and adjudge that the plaintiff pay the defendant $480 as damages.

The final judgment of the court a quo dismissed the complaint, holding that the plaintiff should recover nothing from the defendant, but that the counterclaim should be sustained, the contract for said construction between Nones and the school board rescinded, and, to meet the liability of the contractor to respond for the sum of $3,373.50, that the bond furnished to secure the performance of the contract and $1,525.60, the value of the foundations constructed by Bruno and assigned by him to Nones, be confiscated, and that Nones should also pay to the defendant $480 as damages, together with the costs and disbursements of the action.

Before demolishing the walls in question the parties took blocks from the three courses and marked the one from the first course laid on the foundations as No. 1, that from the second course as No. 2, and that from the third and last course as No. 3. The defendant sent its samples to the Chemical Laboratory of Pittsburg, Pennsylvania, where they were received by chemist E. H. Graver in three boxes, the box marked No. 1 containing sample No. 3; box No. 2 containing sample No. 1, and box No. 3 containing sample No. 2. [21]*21The said chemist analyzed these samples of concrete and his report gave rise to a strong- controversy at the trial, for the plaintiff introduced abundant expert evidence to show that the proportions found by Craver refer to the absolute volumes in which the materials appear in the concrete, and not to the apparent volumes which it contained when the mixture was made, and, therefore, his report cannot serve as a guide for determining the proportions in which the contractor mixed the cement, sand and gravel for the concrete which he employed in the walls; and as the lower court based its judgment principally on the report of the said chemist when it reached the conclusion that Nones had not complied with the contract in mixing the concrete, it is alleged by the appellant that the lower court committed manifest error in holding that the apparent volumes had been obtained and that the amounts obtained were those in which the materials were proportioned for mixing the concrete.

Free access — add to your briefcase to read the full text and ask questions with AI

Nones v. Ponce School Board, 25 P.R. 17 (prsupreme 1917).

25 P.R. 17 (Nones v. Ponce School Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.