Nolander v. Burns

50 N.W. 1016, 48 Minn. 13, 1892 Minn. LEXIS 365
Supreme Court of Minnesota·Decided January 6, 1892·Published·Cited by 5 cases

Opinion

Collins, J.

.The agreement entered into between defendants Brown and Belden as owners of the real property, on which plaintiff claims a lien under the terms of Laws 1889, ch. 200, and defendant Burns, whereby the former sold and agreed to convey to the latter said property, required of Burns the erection and completion of three houses within a given period of time. Prompt performance of the conditions imposed upon the vendee was demanded in express terms, and time was made of the essence of the agreement. Two of the houses were seasonably completed, but the third was not, nor was it commenced. It stands undisputed that, had the plaintiff performed his labor under the old statute, (1878 G. S. ch. 90,) he would have been entitled to the relief demanded in the complaint, under the conclusion reached in Hill v. Gill, 40 Minn. 441, (42 N. W. Rep. 294,) —a case which has been followed a number of times. But shortly before the opinion in that case was filed the legislature passed a new law upon the subject, (chapter two hundred, [200,] supra,) in which there appeared a section wholly unlike any to be found in the various lien laws previously enacted in this state or elsewhere, so far as we have discovered. It is this section which has rendered the Hill-Gill Case inapplicable and of no force as an authority here, and has deprived the plaintiff of a statutory remedy which, beyond question, would be his, were it not for its incorporation into the statute of 1889. We refer to section four, (4,) which reads thus: “Sec. 4. Whenever the owner of land has sold the same upon an executory contract of sale contingent upon or providing for the erection, construction, alteration, removal to, or repair upon such land by the vendee thereof, of any house, mill, manufactory, or other building or appurtenance,-or of any fixture, wharf, fence, or other structure, if the vendee or his assigns shall forfeit or surrender such contract, then, for the purpose of establishing and enforcing a lien for all labor, skill, material, or machinery performed or furnished by other persons for or to such vendee or his assigns, under contract or subcontract for such erection, construction, alteration, removal, or repair, such vendee [vendor] [16] shall be deemed the owner of such house, mill, manufactory, or other building or appurtenance, or fixture, wharf, fence, or other structure, and such vendee his contractor, within the meaning of this act. But no such vendor shall be personally liable for any indebtedness so contracted by such vendee.” This section contains very plain and unambiguous language. It must be taken as fully and completely expressing the legislative will on the matter, and must be accepted as controlling in all causes where applicable. It covers all actions brought to foreclose mechanics’ liens, where the work has been performed or the materials furnished for a person whose only interest in the real property on which the lien is sought is that of a purchaser holding nothing more than an executory contract of sale, contingent or conditioned upon the erection or construction of a building by the vendee, as was the situation in the case at bar. Under such circumstances, if the vendee or his successor in interest shall have forfeited or shall have surrendered the contract, the vendor shall be deemed the owner of the structure, and the vendee his contractor, within the meaning of, and for the purpose of establishing and enforcing a lien under, the statute. With a provision of the act so explicit as this, it must be held that,when an attempt is made to establish a lien as against a vendor of real property who has entered into a contract of the character specified in section four, (4,) it devolves upon the lien claimant, as a condition precedent to his right to recover as against the estate or interest of a vendor, to allege in his complaint, and to prove, if the allegation be controverted, that the contract has either been forfeited or surrendered. By specially providing for a lien where there has been a forfeiture or surrender, and in such cases declaring that the vendor shall be regarded as the owner of the building, and the vendee his contractor, within the meaning of the lien statute, the lawmakers have declared, by implication, but beyond doubt, that until there has been a forfeiture or a surrender of the contract the vendor shall not be held to be the owner of the building which has been placed upon the real property, nor shall the vendee be deemed his contractor under the act. The result of this legislation with respect to executory contracts of sale has been to deprive quite a numerous class of mechanics and mate[17] rial men of the benefits of the statute providing for liens for work ■done and materials furnished, who would have been entitled thereto under the doctrine established in Hill v. Gill.

Free access — add to your briefcase to read the full text and ask questions with AI

Nolander v. Burns, 50 N.W. 1016, 48 Minn. 13, 1892 Minn. LEXIS 365 (Mich. 1892).

50 N.W. 1016 (Nolander v. Burns) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gruen v. State Tax Commission
211 P.2d 651 (Washington Supreme Court, 1949)
Erickson v. Ireland
158 N.W. 918 (Supreme Court of Minnesota, 1916)
Brown v. Jones
55 N.W. 54 (Supreme Court of Minnesota, 1893)
Hill v. Aldrich
50 N.W. 1020 (Supreme Court of Minnesota, 1892)
Althen v. Tarbox
50 N.W. 1018 (Supreme Court of Minnesota, 1892)