Nolan v. Consolidated School District No. 3

300 S.W. 523, 222 Mo. App. 59, 1927 Mo. App. LEXIS 153
CourtMissouri Court of Appeals
DecidedDecember 5, 1927
StatusPublished
Cited by4 cases

This text of 300 S.W. 523 (Nolan v. Consolidated School District No. 3) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nolan v. Consolidated School District No. 3, 300 S.W. 523, 222 Mo. App. 59, 1927 Mo. App. LEXIS 153 (Mo. Ct. App. 1927).

Opinion

ARNOLD, J.

— This is an action to recover a balance alleged to be due under a written contract for making certain additions and rebuilding a schoolhouse for district No. 3 in.Callaway county, Mo., at New Bloomfield. Judgment was for plaintiff in the sum of $775.08, but, being dissatisfied with the amount of said judgment, plaintiff brings the case here by writ of error, contending the court erred in refusing to alloAV plaintiff certain items claimed, in the total sum of $4500, for labor and material furnished in replacing certain walls of the old building which had been partially destroyed by fire and thereafter blown down by a windstorm.

The facts are that plaintiff is .a contractor and builder residing in the city of St. Louis, .and defendant, as stated, is an organized school district in Callaway county, Mo. The suit was instituted- in Callaway county, but was taken to Cole county by change of venue and was there tried to the court without the aid of a jury. The school building in question belonged to the district and had been partially destroyed by fire, leaving only parts of the walls standing..

On May 24, 1924, plaintiff entered into a written contract for the construction of a new building partly on the site of the old. It appears from the record: that under the said contract plaintiff was to furnish the necessary materials and labor for the erection and completion of alterations and additions to be made to said building, in accordance with certain plans and specifications. At the time of the execution of the contract and prior thereto, the brick walls of the old school building remained on the site and the contract contemplated replacing the' destroyed parts of the old building, with some minor changes, the addition of some rooms and the use of the brick walls which were left of the original building.

After the said contract was entered into it appears plaintiff began work by excavating for an auditorium which was one of the new parts-to be added, and by removing rubbish from the basement of the old building and placing therein joists for the first floor. At this time *61 no work had been done in the way of repairing the walls of the old building. In the month of July, 1924, a windstorm blew down the four brick walls of, the old building, excepting small detached sections thereof. Through his subcontractor plaintiff rebuilt said walls, furnishing the labor and materials therefor, and for the removal of the debris. There was no separate written contract covering this particular work. "When the building was completed, plaintiff submitted to defendant a claim in the sum of $4500' which represented the additional cost to him in replacing the walls. This claim,, including some other items, was rejected by defendant, and is the basis of this suit. Defendant interposed a counterclaim. The trial -court allowed plaintiff certain small sums for extras and disallowed the $4500.item. Defendant was allowed certain small sums on its counterclaim.

At the close of all the evidence the court refused a declaration of law, in the nature of a demurrer offered by plaintiff to all the evidence of defendant on its counterclaim. At this juncture, the court made the following statement:.

“The Court,': Mr. Reporter, please take this notation concerning the judgment of the court in this case:

‘ ‘ The court after having he.ard the evidence offered and being fully •advised in the premises, and after having heard the argument of counsel, holds the school district, the defendant in this ease, liable for the following items:

“The two written contracts mentioned in evidence totalling $24,-614.75; the extra work as noted by the minutes for the concrete in the basement and work on walls, $450; the item of $45 for digging the sewer and the item of $75 for the septic tank, mailing a total of $25,184.75; and gives the school district credit for the following amounts: $23,517.32 paid to the contractor, and also credit for Exhibit AAr of $35 and Exhibit X of $33.38, making a total of $23,585.70 of cash paid out; and also gives them credit for the roof at $550, a lumber bill of $102.97, lumber and work in the schoblhouse $63, and work now incomplete and yet to be done of $108, making a total credit of $24,409.67; that amount deducted from the other sum, $25,184.75, leaves a balance for judgment in favor of the plaintiff of $775.08.”

The following decree and judgment were entered of record:

“Noav at this day comes the plaintiff, A. G. Nolan, in his own proper person and by his attorneys, E. L. McCall and P. S. Terry; comes also the defendant Consolidated School District No. Three of Callaway county, Missouri, by its attorneys. N. T. Cave and Baker & Baker, and both parties announce ready for trial, and by agreement of parties this cause is tried before the court, sitting- as a jury,, without the intervention of a jury, and the trial begins, and at the conclusion of the evidence and .after having heard argument of counsel, it appears to the court that the defendant is indebted to the. plaintiff *62 herein on its contract for material .and labor in the sum of seven hundred and seventy-five dollars and eight cents ($775.08). It is therefore ordered, adjudged and decreed by the court that the plaintiff A. G. Nolan, have and recover of and from the defendant Consolidated School District No. Three of Callaway county, Missouri, the sum of seven hundred seventy-five dollars and eight cents ($775.08), together with his costs laid out and expended in this behalf and that execution issue therefor.”

The only point for which plaintiff contends is that the court erred in disallowing the item of $4500, claimed by him. It is urged in this behalf that (a) when one .by contract creates a duty or charge upon himself he is thereby bound to make it good, notwithstanding any accident by inevitable necessity, because he might have provided against it by his contract; (b) and that where the written agreement is broad enough to cover the situation out of which recovery is sought, the statute is complied with. Plaintiff cites a number of cases in support of this well-established rule. Defendant does not refute it and we may accept plaintiff’s statements, as being correct. However, the point in controversy here is whether or not the main contract is, in fact, broad enough to cover the situation presented. The agreement between the parties is of standard form and printed. As a basis of his argument, plaintiff cites Article VTII of the contract which is as follows:

“The owner agrees to provide all labor and materials essential to the conduct of this work not included in this contract, in such manner as not to delay its progress, and in the event of failure so to do, thereby causing loss to the contractor, agrees that it will reimburse the contractor for such loss; and the contractor agrees that if he shall delay the progress of the work, so as to cause loss for which the owner shall become liable, then he shall become liable, then he shall reimburse the owner for such loss. Should' the owner and contractor fail to agree ,as to the amount of loss comprehended in this article, the determination of the amount shall be referred to arbitration, as provided in Article XII of this contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
300 S.W. 523, 222 Mo. App. 59, 1927 Mo. App. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nolan-v-consolidated-school-district-no-3-moctapp-1927.