Nockamixon Township Landfill Operation

58 Pa. D. & C.2d 37
CourtPennsylvania Environmental Hearing Board
DecidedMarch 21, 1972
Docketdocket no. 71-94
StatusPublished

This text of 58 Pa. D. & C.2d 37 (Nockamixon Township Landfill Operation) is published on Counsel Stack Legal Research, covering Pennsylvania Environmental Hearing Board primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nockamixon Township Landfill Operation, 58 Pa. D. & C.2d 37 (Pa. Super. Ct. 1972).

Opinion

MALIN, Chairman,

This is an appeal by Nockamixon Township from the grant to the County of Bucks of Solid Waste Permit No. 100678 under the Pennsylvania Solid Waste Management Act of July 31, 1968 (No. 241), 35 PS §6001, for the operation of Hidden Valley Landfill in Nockamixon Township. Originally, appellant also appealed from the grant of Industrial Waste Permit No. 0971204 under the Clean Streams Law, but this part of the appeal was withdrawn at the hearing held in this matter.

The township argues that the permit should not be issued for operation of the landfill until such time as a leachate collection and treatment system is installed and operating. It also argues that the collection system approved in permit no. 100678 is inadequate because part of the system is a contingency plan, to be constructed only if the original part of the system fails to collect all of the leachate emanating from the landfill.

FINDINGS OF FACT

1. Bucks County is the owner and operator of [39]*39Hidden Valley Landfill, located in Nockamixon Township.

2. In December, 1970, the township initiated an action in equity in the Court of Common Pleas of Bucks County, Pa., December term, 1970, no. 1252, to enjoin the operation of Hidden Valley Landfill by the county.

3. At that time, the county did not have a permit for operation of the landfill, nor had an application for a permit been filed.

4. On February 27, 1971, the Court of Common Pleas of Bucks County entered judgment against the county based upon admissions contained in the pleadings in that action and the landfill was closed.

5. On May 28, 1971, the county applied for a Solid Waste Disposal Permit and on June 4, 1971, was granted permit no. 100678. That permit has not been revoked and continues in effect.

6. The permit covered operation of solid waste disposal sites designated as A and B on the plan submitted as part of the application. Site A contained the site which was then being operated as a landfill, and site B was a new area to be filled after the completion of operations at site A.

7. The permit required the county to apply for and obtain an Industrial Waste Permit for the construction and operation of a treatment facility by July 2, 1971.

8. The county filed an application for a Water Quality Management Permit on July 7, 1971, and an amendment thereto dated August 3, 1971. Permit No. 0971204 was issued on August 17, 1971.

9. Reports filed by members of the Pennsylvania Department of Environmental Resources, based upon visits to the site, indicated that the site was not an appropriate one for a landfill unless a collection and treatment system was provided.

[40]*4010. Application no. 100678 provided for a collection system based upon trenches which will surround the landfill area and collect liquids which flow horizontally.

11. Stephen F. Curran, Jr., geologist in the Division of Water Quality, Bureau of Sanitary Engineering, Department of Environmental Resources, suspected that vertical fracturing in the rock structure underlying the landfill area might permit liquid effluent to flow vertically downward, thus escaping collection in the surface trenches, and then moving with ground water into the surrounding streams.

12. Valley Forge Laboratories, Inc., consulting engineering firm engaged by the county, conducted additional tests and submitted data to Mr. Curran which indicated that there was no substantial fracturing of the rock and vertical flow would not occur.

13. Although the data indicated that there would be no vertical flow and Mr. Curran’s fears of such flow were based upon visual observation rather than technical data, the department required the county to amend its application by adding provisions for a contingency collection system, to be constructed and operated in the event the original system did not capture all of the leachate eminating from the landfill.

14. Construction of the contingency system would require additional land acquisitions and, in addition to the cost of the acquired land, the expenditure of $20,000 to $100,000 on work and equipment.

15. The existing landfill is producing leachate, a highly concentrated pollutant, which is flowing into the waters of the Commonwealth and there are no facilities presently existing which can collect and treat that effluent.

16. Operation of the landfill at the present site and at any additional sites will continue to produce [41]*41leachate, for which no collection and treatment facilities presently exist.

17. Application no. 100678 and the data submitted with it support the department’s conclusion that the collection and treatment system as designed will, when constructed, be adequate to handle the effluent generated by the landfill.

18. Provision for additional collection and treatment facilities as a contingency, rather than as part of the original system, is a reasonable conclusion by the department in light of the available data and the high cost involved in providing for the contingency.

DISCUSSION

We cannot agree with the township’s argument that the contingency collection system must be made part of the original system. No data submitted in connection with this matter supports a conclusion of vertical fracturing within the site that would lead to discharges which will escape the original collection system. While observations of discharge at or near stream level give cause for concern, all the results of test data submitted to the department indicate that there is no vertical fracturing within the site. The permit provides for an observation period of approximately two months after construction of the original system, followed by construction of an additional collection system within another two months in the event that a pollutional effluent escapes the original system. A contingency plan to guard against such discharge, which might never occur, is not an unreasonable conclusion by the department, since considerable amount of trouble and expense would be involved.

A more serious question arises with respect to the grant of the Solid Waste Management Permit prior to construction of the original collection system. The [42]*42parties agree that a pollutional discharge is emanating from the landfill and that there are no facilities presently available to collect and treat this effluent. Construction of the collection and treatment facilities, if the original schedule were adhered to, would not be completed and in operation until May 1, 1972, or June 1, 1972. It is likely that the litigation surrounding this project will extend those dates by many months. Therefore, the question is whether it was proper for the department to grant a permit with respect to a landfill which was producing a pollutional discharge for which treatment facilities were not available at the time the permit issued.

Section 7 of the Pennsylvania Solid Waste Management Act makes it unlawful to operate a solid waste disposal area without a permit from the department.

Section 9(4) of the act makes it unlawful to store, collect, transport, process or dispose of solid wastes contrary to the rules, regulations, standards or orders of the department or in such a manner as to create a public nuisance.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
58 Pa. D. & C.2d 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nockamixon-township-landfill-operation-paenvhrbd-1972.