Noble v. C. Crane & Co.

169 F. 55, 16 Ohio F. Dec. 304, 1909 U.S. App. LEXIS 4550
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 15, 1909
DocketNo. 1,900
StatusPublished
Cited by11 cases

This text of 169 F. 55 (Noble v. C. Crane & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noble v. C. Crane & Co., 169 F. 55, 16 Ohio F. Dec. 304, 1909 U.S. App. LEXIS 4550 (6th Cir. 1909).

Opinion

TAYLER, District Judge.

This action was prosecuted in the court below by the plaintiff in error to recover from C. Crane & Co., a corporation, the damages sustained by him in consequence of the breaking of a scaffold on which he was working, which resulted in his falling some 40 feet to the ground, whereby his leg was broken and other injuries were received. At the close of the plaintiff’s testimony, the court, on the motion of the defendant, directed a verdict for the defendant. Error is prosecuted to the judgment which was entered oh the verdict.

The plaintiff was a carpenter of seven or eight years’ experience, and was employed frith other carpenters in the work of erecting a new sawmill in the extensive lumber yards of the defendant in the city of Cincinnati. After the frame of the mill had been completed, it became necessary, in the prosecution of .the work, to cover the roof with tar paper. This work was done by the carpenters. To enable them to put the tar paper along the edge of the roof, a temporary scaffold was built by the plaintiff and the three other carpenters associated with him in the work of erecting the building. The scaffolding, some 55 feet long, consisted of planks supported by five brackets or outriggers composed of 2x6 hemlock pieces, 8 or 10 feet long, projecting about 5 feet from the side of the building. These 2x6 outriggers were securely nailed to the upright 12x12 timbers, which constituted the framework of the mill. While the plaintiff and two other carpenters were standing on the scaffolding, nailing tar .paper to the edge of the roof, one of these 2x6 hemlock supports, because of a defect in it, broke close to the building, and the scaffold gave way, with the result already stated.

Plaintiff himself put up two of the five supports, but had nothing to do with putting in that which was defective, and knew nothing of its defective condition.

[57]*57The liability of the employer depends upon the manner in which it performed its duty to furnish to the plaintiff and his fellow workers on the scaffold suitable and safe materials with which to erect the scaffold. Other questions appear in the pleadings, but not in the proof. The plaintiff in error contends that the defendant did not perform this-duty, either as defined by the common law or by the statutes of Ohio.

The testimony developed this situation. The defective support or outrigger was one of several pieces of 2x6 hemlock which were lying on the third-story floor of the building which was being constructed. Similar scaffolds were erected on opposite sides of the building. These pieces had been left over from supplies brought up from the yard from time to time for the general purposes of constructing the building. Just how many pieces there were when the time came for building the scaffold does not appear, but in view of the testimony and the motion for a verdict it must be assumed that there were no more than were necessary to build the scaffold.

One of the witnesses, Sesher, testifies that McMullin, the foreman, told him to take the 2x6 hemlock pieces that were lying on the third-story floor and build the scaffold out of it. This instruction Sesher conveyed to the plaintiff and to the other carpenters engaged in the work. The same witness testified that if at any time he wanted additional material he would go and tell McMullin and the latter would have it there, and that he did not know of any carpenters with him who had any authority to go out into the yard and get material without orders from McMullin. Noble, the plaintiff, testified that he had no authority to go out into the yard or into the mill to select lumber for the' scaffold.

The testimony of the plaintiff and of his other witnesses shows very clearly what was the custom in this lumber yard respecting the ability and opportunity of workmen to obtain needed lumber. Plaintiff says that he knew of nothing to prevent the carpenters from asking to have more lumber brought up, and that there were laborers whose business it was to bring it up as the carpenters needed it. Practically all of the plaintiff’s witnesses testified that it was easy for the carpenters to get any lumber they wanted; all that was needed was to ask for it. One of the laborers or helpers testified that he was ready to bring up any amount of lumber, including 2x6 hemlock pieces, that was needed; that that was what he was there for, and if it was not there he was to go and get it. All they had to do, he said, was to call for it, and they got it. To the same general effect is the testimony of other witnesses. There is no contradiction except such as may be inferred from the testimony already referred to, and that is in no proper sense contradiction.

These references put the plaintiff’s case in its strongest possible form, and allow every reasonable inference in his favor to be drawn from them.

It is claimed by plaintiff’s counsel that this instruction of McMullin, coupled with what the plaintiff says as to his authority to go out and get additional lumber, limited the workmen to the use of the material referred to by the foreman, and that they were bound to use it, whether it was safe and suitable or not. More definitely interpreted, the [58]*58claim means this: That the foreman intended, and so directed, that these three or four carpenters, skilled in the work of building and using scaffolds, with knowledge of the kind of material needed for and suited to such construction, and skilled judges of the quality and strength of lumber, should build a scaffold, on which they themselves were to work, out of a limited and certain pile of lumber, and that they could not have any other lumber out of which to build it if it should appear, when about to be used, to be insufficient or unfit for such purpose.

Such an interpretation of such an instruction, which we must assume to have been given exactly as Sesher tells it, seems to us to be forced and unreasonable. There is no real or substantial conflict anywhere in the testimony. We are required, if we sustain plaintiff’s contention, to come to the strained and unnatural conclusion that, in spite of this testimony offered by the plaintiff, these intelligent carpenters, building their own scaffold, were helpless to select or to send for other material than that pointed out by the foreman. We are compelled, if we give weight to the contention of plaintiff, to declare that under the circumstances narrated by plaintiff’s testimony, involving, as we have said, no contradiction, no reasonable opportunity was furnished to these workmen to obtain suitable material out of which to construct a scaffold.

Counsel for plaintiff in error formulate their claim upon these facts as follows:

“Defendant cannot escape liability by claiming, as it does, that the direction to use this material given by it to these men was qualified. Defendant cannot maintain that these men should have understood that if the material they were thus directed to use should turn out, on examination by them, to be unfit, they should discard it and demand other material. The direction to use this material was not thus limited, and, had it been so limited, that would not relieve the defendant of liability, because such direction would have imposed upon these men the duty and responsibility of inspecting the lumber and of exercising judgment as to its fitness. That duty was one resting upon the master, and he could not delegate it.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moody v. Hanlon
179 So. 164 (Supreme Court of Florida, 1938)
De Kalb County v. Tennessee Electric Power Co.
67 S.W.2d 555 (Court of Appeals of Tennessee, 1933)
American Box & Lumber Co. v. Chandler
138 So. 29 (Supreme Court of Florida, 1931)
Barnsdall Oil Co. v. Ohler
1915 OK 397 (Supreme Court of Oklahoma, 1915)
Patterson v. Jacksonville Traction Co.
213 F. 289 (Fifth Circuit, 1914)
American Shipbuilding Co. v. Lorenski
204 F. 39 (Sixth Circuit, 1913)
Lane Bros. v. Couch
192 F. 509 (Sixth Circuit, 1912)
Toledo, St. L. & W. R. v. Howe
191 F. 776 (Sixth Circuit, 1911)
Collins v. John W. Danforth Co.
36 App. D.C. 592 (D.C. Circuit, 1911)
Big Brushy Coal & Coke Co. v. Williams
176 F. 529 (Sixth Circuit, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
169 F. 55, 16 Ohio F. Dec. 304, 1909 U.S. App. LEXIS 4550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noble-v-c-crane-co-ca6-1909.