Noble House, Inc. v. W & W Plumbing & Heating, Inc.

881 So. 2d 377, 2004 Miss. App. LEXIS 880, 2004 WL 1925958
CourtCourt of Appeals of Mississippi
DecidedAugust 31, 2004
DocketNo. 2002-CA-02060-COA
StatusPublished
Cited by2 cases

This text of 881 So. 2d 377 (Noble House, Inc. v. W & W Plumbing & Heating, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noble House, Inc. v. W & W Plumbing & Heating, Inc., 881 So. 2d 377, 2004 Miss. App. LEXIS 880, 2004 WL 1925958 (Mich. Ct. App. 2004).

Opinions

CHANDLER, J.,

for the Court.

¶ 1. This appeal arises from an October 28, 2002 order of the Adams County Circuit Court denying a motion by Noble House, Inc. and Francis J. Ransom, d/b/a Ransom Construction Company, Inc., to alter or amend a judgment entered on October 4, 2002. At issue is a so-called “agreed judgment of dismissal” devised by Noble House and Ransom, which, without notice, unilaterally precluded the subcontractor, W & W Plumbing & Heating, Inc., from sharing in funds interpled with the court pursuant to Rule 22 of the Mississippi Rules of Civil Procedure. Noble House and Ransom challenge the circuit judge’s hand-written provision in the October 28 order for W & W Plumbing, which had been named as an interpleader defendant when litigation began in 1997. Finding that the circuit judge did not abuse his discretion in refusing to grant the motion to alter or amend the judgment, we affirm the decision of the court below.

FACTS

¶ 2. On April 27, 1994, Francis J. Ransom, d/b/a Ransom Construction Company, entered into a contract with Noble House, Inc. and the Adams County Board of Supervisors for the construction of a multifamily, low-income housing project in Natchez, Mississippi, under the aegis of the Home Investment Partnership Program of the United States Department of Housing and Urban Development. Under the terms of the contract, construction of the apartments was scheduled for completion within 240 days of the contract date. However, because of various collateral legal proceedings not related to the case sub judice, work was stopped between November 1994 and August 1995. Consequently, the apartments were not ready for occupancy until November 1996.

¶ 3. As a result of the work stoppage, the original subcontractor Ransom had hired to install the plumbing, heating and air conditioning systems refused to perform. Ransom substituted W & W Plumbing & Heating as the alternative subcontractor, which bid $55,964.32 to correct work previously done and to complete the project. Invoices submitted by W & W Plumbing to Ransom indicate that the contractor paid the first draft of $30,589.05 on September 3, 1996. Two subsequent drafts of $14,287.51, due on October 1, 1996, and $10,817.76, due on December 1, 1996, were not paid.

¶ 4. During the course of construction, Noble House made periodic installment payments to Ransom. On October 16, 1996, with the apartments nearly ready for occupancy, Noble House notified Ransom in writing that its contract was terminated because of Ransom’s alleged failure to complete the limited work remaining in a timely and workman-like manner. Noble House thus withheld its final payment of $72,356 to the contractor. Ransom, in turn, did not pay W & W Plumbing the final $25,105.27 it was owed for completing the plumbing, heating and air conditioning work.1

¶ 5. On February 1, 1997, Noble House filed a complaint in the Adams County Circuit Court against Ransom and W & W Plumbing. Noble House charged that Ransom had breached its contract by failing to complete the project in a timely and workman-like manner. Noble House averred that it had not made the final payment of $72,356 to Ransom because of economic losses caused by the construction delays. Noble House further stated in its complaint that Ransom owed the plumbing [380]*380contractor $25,105.27. Therefore, Noble House sought to interplead a total of $72,856 and named W & W Plumbing as an interpleader defendant for purposes of the escrowed funds.

¶ 6. W & W Plumbing filed its response to the complaint on February 26, 1997. Ransom filed a response and counter-claim against Noble House on March 13, 1997, seeking recovery for additional project expenses incurred by the stop work order. Ransom further alleged that the original contract was rescinded by the stop work order and never revived, either orally or in writing.

¶ 7. W & W Plumbing filed a motion for partial summary judgment on March 27, 1997. W & W Plumbing asserted that it was undisputed that it had properly completed the work as agreed and was entitled to payment in the amount of $81,877.29, which included accrued interest. Since the pleadings filed by Noble House and Ransom agreed that W & W Plumbing was entitled to $25,105.27 due and payable from December 1, 1996, the subcontractor asked the court to declare that there was no issue of material fact and to pay the amount due from the interpled funds. Noble House responded that proof of the amount due had not been placed in evidence. Accordingly, the circuit judge found that granting relief would be premature and denied the motion on April 30, 1997.

¶ 8. Ransom amended its counterclaim against Noble House on July 8,1998, seeking payment of the money owed to W & W Plumbing, the $72,356 allegedly still owed for completing the construction, and further, compensation for business lost because of bonding problems arising from the litigation. Noble House likewise amended its complaint against Ransom, joining Cumberland Surety & Performance Co., Inc., which had provided Ransom’s performance bond.

¶ 9. On June 1, 2000, W & W Plumbing filed an amended response to the initial complaint. Contrary to all parties’ earlier position that the plumbing company was a subcontractor, W & W Plumbing asserted that because time had been of the essence in completing the project, it had acted as an independent contractor for both Ransom and Noble House. W & W Plumbing alleged that it had reported directly to Noble House, which had supervised the work and guaranteed payment. Because of the disputes and delays encountered during the course of construction, W & W Plumbing further claimed that it had refused to enter into a contract and all work had been done on an hourly basis. Noble House denied the allegations made in the amended response, subsequently filing a motion for partial summary judgment in August 17, 2000, seeking dismissal of any claims W & W Plumbing might have against it or the interpled funds.

¶ 10. Ransom then filed its motion for summary judgment on October 4, 2000. Ransom, for the first time, asserted that the work performed by W & W Plumbing had been done pursuant to an open account arrangement. Ransom therefore argued that any claim W & W Plumbing might have against it was time-barred by the three-year statute of limitations on open accounts prescribed by Mississippi Code Annotated Section 15-1-29 (Rev. 2003).

¶ 11. Noble House’s motion for summary judgment was denied on October 23, 2000. The circuit judge found that no independent claim by W & W Plumbing existed against Noble House which would be a proper subject for summary judgment. The judge expressly refused to rule on the validity or invalidity of any claims against the interpled funds, stating that the issue should be bifurcated and held in abeyance until the claims between Ransom and Noble House were resolved. In his [381]*381November 2, 2000 order, the circuit judge reiterated that W & W Plumbing had basis for a claim against Noble House, and had not asserted any counterclaims against the owner or cross-claims against Ransom and remained only an interpleader defendant, with claims solely to the interpled funds.

¶ 12. In its amended response, W & W Plumbing noted that Noble House had failed to deposit the full $72,356 it sought to interplead in the original complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sean McDowell v. Zion Baptist Church
203 So. 3d 676 (Court of Appeals of Mississippi, 2016)
Berryman v. Lannom
94 So. 3d 1238 (Court of Appeals of Mississippi, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
881 So. 2d 377, 2004 Miss. App. LEXIS 880, 2004 WL 1925958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noble-house-inc-v-w-w-plumbing-heating-inc-missctapp-2004.