Niram, Inc. v. Salvi Steel Fabricators, LLC

New Jersey Superior Court Appellate Division·Decided March 19, 2026·No. A-2600-24·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited . R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-2600-24

NIRAM, INC., Plaintiff-Respondent,

v.

SALVI STEEL FABRICATORS, LLC,

Defendant-Appellant.

Submitted March 4, 2026 – Decided March 19, 2026 Before Judges Mayer and Vanek.

On appeal from the Superior Court of New Jersey, Law Division, Morris County, Docket No. L-0425-25.

Kelly Law, PC, attorneys for appellant (Charles P.

Kelly, IV, of counsel; Bradley Latino, of counsel and on the briefs).

Raymond G. Chow, attorney for respondent.

PER CURIAM

Plaintiff Niram, Inc. (Niram) and defendant Salvi Steel Fabricators, LLC (Salvi) agreed to resolve their construction subcontract dispute through the entry of a "standard" arbitration award containing only the arbitrator's conclusion, rather than a "reasoned award" explaining the basis or method for calculating the award. Salvi appeals from an April 4, 2025 Law Division order confirming the arbitration award in favor of Niram and denying Salvi's cross-motion to modify or vacate the award. Under our highly deferential standard of review of arbitration awards, we affirm.

I.

In June 2021, Niram subcontracted with Salvi for the fabrication and installation of structural steel on the Javits Lecture Center rehabilitation project at SUNY Stony Brook (Javits Project) for a total contract price of $577,000 (the subcontract). Sections 6.3.1 and 6.3.7 of the subcontract required that any contractual disputes be resolved under New York law through binding arbitration conducted by the American Arbitration Association (AAA) in New Jersey.

Sections 3.4.1 and 7.2.1 of the subcontract set forth available damages in the event of Salvi's breach and Niram's termination of the subcontract. Niram could terminate the subcontract under section 3.4.1 if Salvi failed to promptly

A-2600-24

complete the work or provide sufficient skilled laborers and quality materials. In that event, after providing Salvi with five days' written notice, Niram could have the work performed by other subcontractors and recover the costs of completion from Salvi. Section 3.4.1 further specified:

[I]f the unpaid balance of the amount to be paid under this subcontract shall exceed the reasonable expense incurred by [Niram] in finishing the Work, such excess shall be paid by [Niram] to [Salvi], but if such expense shall exceed the unpaid balance, [Salvi] shall pay the difference to [Niram].

Niram could also terminate the subcontract under section 7.2.1 after ten days' written notice if Salvi failed to complete the work pursuant to the subcontract and did not cure its breach. In that event, Niram could have the work performed "by whatever means [it] may deem expedient" under section 7.2.1. Section 7.2.1 provided the same method for calculating damages as section 3.4.1.

On May 1, 2023, Niram terminated the subcontract and suspended further payments based on Salvi's failure to supply sufficient properly skilled laborers and quality materials to complete the Javits Project within the agreed-to construction schedule. After providing Salvi with the requisite notice and opportunity to cure its breach, Niram invoked its right under section 7.2.1 to

A-2600-24

complete the work and later recover the costs from Salvi. Niram had paid Salvi $255,594.98 at the time it terminated the subcontract.

On February 2, 2024, Niram filed a demand for arbitration with the AAA, which included a claim against Salvi under the subcontract. 1 Niram's arbitration demand asserted its damages caused by Salvi's breach of the subcontract were $82,507.03. Salvi filed an answer denying it had breached the subcontract and counterclaiming for "an outstanding $372,405.10 for its work on the Javits Project."

Rather than a "reasoned award" that would explain the arbitration award's basis and calculation, the parties agreed to a "standard award," that would contain only the arbitrator's conclusion. Over the course of a six-day arbitration proceeding, the parties submitted numerous exhibits, several witnesses testified, and arguments were presented by counsel. There is no verbatim record of the proceedings.

After the hearings, the parties submitted their respective damage summaries. Niram asserted its damages for breach of the subcontract were $110,838.23, including the cost of completing the work after Salvi's breach and

1 The demand for AAA arbitration also included a claim under a separate contract with Salvi that is not the subject of this appeal.

A-2600-24

credit to Salvi for the unpaid balance of the subcontract. Salvi claimed Niram owed it a balance of $301,546.44 on the original subcontract plus $151,216.81 in unpaid change orders.

On January 4, 2025, the arbitrator awarded Niram $435,369 for Salvi's breach of the subcontract. The award stated in pertinent part as follows:

On the Stony Brook Javits Learning Center Project:

1. [Niram] is awarded $435,369.00 (FOUR HUNDRED THIRTY-FIVE THOUSAND THREE HUNDRED SIXTY-NINE DOLLARS) for back charges and costs to complete.

2. The amount of the lien filed by New York Steel Erectors on the Stony Brook Javits Learning Center Project was not properly before the Arbitrator in this matter.

3. [Salvi] is not entitled to any amount (ZERO DOLLARS) since the payments by and credits due to [Niram] exceed the subcontract amount. . .

Neither party is awarded interest or attorney fees.

The administrative fees of the American Arbitration Association totaling $20,575.00, and the compensation and expenses of the arbitrator totaling $17,737.46 shall be borne as incurred.

The above sums are to be paid on or before thirty days from the date of this Award.

A-2600-24

This Award is in full settlement of all claims and counterclaims submitted to this Arbitration. All claims not expressly granted herein are hereby, denied.

Salvi then requested the arbitrator modify the award, arguing it conflicted with the subcontract and the award's "own logic," because the "credits due to Niram [did] not exceed the subcontract amount." The arbitrator denied Salvi's request and reaffirmed the award, finding "there [were] no appropriate grounds to modify [the] award."

Niram then filed a Law Division complaint and motion to confirm the arbitration award. Salvi filed an answer and cross-moved to vacate or, alternatively, to modify the award, arguing the arbitrator had acted outside his authority under the subcontract.

In an oral opinion and accompanying order, the judge granted Niram's motion to confirm the arbitration award and denied Salvi's cross-motion to vacate or modify the award, finding the award was within the arbitrator's authority under the subcontract and the issue of Salvi's entitlement to a credit for the unpaid subcontract balance had been arbitrated. The judge considered each statutorily permissible basis for vacating or modifying an arbitration award and concluded none applied. The judge found the arbitrator's award could not be modified without disturbing the arbitrator's findings, which were not apparent

A-2600-24

from the "standard award" itself, and noted "some of the issues. . . are really a product of the fact that the parties had elected the short form decision. Perhaps had there been the longer form version . . . it may have clarified . . . how [the arbitrator] reached those numbers."

On appeal, Salvi argues the judge erred in confirming the arbitration award without modification and finding the issue of its right to a credit for the balance of the subcontract had been arbitrated; the arbitrator exceeded the scope of his power by disregarding the subcontract's terms; the arbitrator erred by effectively granting Niram punitive damages; and that the arbitration award could be modified without affecting its merits.

II.

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Niram, Inc. v. Salvi Steel Fabricators, LLC, (N.J. Ct. App. 2026).

Niram, Inc. v. Salvi Steel Fabricators, LLC (Niram, Inc. v. Salvi Steel Fabricators, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Del Piano v. Merrill Lynch
859 A.2d 742 (New Jersey Superior Court App Division, 2004)
Tretina Printing, Inc. v. Fitzpatrick & Associates, Inc.
640 A.2d 788 (Supreme Court of New Jersey, 1994)
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)
Block v. Plosia
916 A.2d 475 (New Jersey Superior Court App Division, 2007)
HOJNOWSKI EX REL. HOJNOWSKI v. Vans Skate Park
901 A.2d 381 (Supreme Court of New Jersey, 2006)
Fawzy v. Fawzy
973 A.2d 347 (Supreme Court of New Jersey, 2009)
Barcon Associates, Inc. v. Tri-County Asphalt Corp.
430 A.2d 214 (Supreme Court of New Jersey, 1981)
Bound Brook Board of Education v. Glenn Ciripompa (076905)
153 A.3d 931 (Supreme Court of New Jersey, 2017)
Minkowitz v. Israeli
77 A.3d 1189 (New Jersey Superior Court App Division, 2013)