Nir Zeer v. Ziv Azulay

50 A.D.3d 781
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 8, 2008
StatusPublished
Cited by6 cases

This text of 50 A.D.3d 781 (Nir Zeer v. Ziv Azulay) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nir Zeer v. Ziv Azulay, 50 A.D.3d 781 (N.Y. Ct. App. 2008).

Opinion

[782]*782Motion by the plaintiffs and separate motion by the defendants Ziv Azulay and Wagner Ziv Plumbing and Heating Corporation, inter alia, for leave to reargue a decision and order of this Court dated July 24, 2007, which determined an appeal from an order of the Supreme Court, Kings County, dated February 3, 2006, and an appeal and cross appeal from an amended judgment of the same court dated February 6, 2006.

Upon the papers filed in support of the motions and the paper filed in relation thereto, it is,

Ordered that those branches of the motions which seek leave to reargue the decision and order of this Court dated July 24, 2007 are granted, and the motions are otherwise denied; and it is further,

Ordered that, upon reargument, the decision and order of this Court dated July 24, 2007, in the above-entitled action (see Zeer v Azulay, 42 AD3d 532 [2007]) is recalled and vacated, and the following decision and order is substituted therefor:

In an action, inter alia, to recover damages for breach of contract, the defendants Ziv Azulay and Wagner Ziv Plumbing & Heating Corporation appeal (1), as limited by their brief, from so much of an order of the Supreme Court, Kings County (Lewis, J.), dated February 3, 2006, as granted the plaintiffs’ motion to amend a judgment of the same court entered September 16, 2005, in favor of the plaintiffs and against them in the sum of $138,220, to the extent of providing for an additional award of liquidated damages in favor of the plaintiffs and against them in the sum of $175,684.77, and denied their cross motion to vacate a stipulation of the parties dated December 2, 2004, and to vacate the judgment entered September 16, 2005, and (2) from an amended judgment of the same court dated February 6, 2006, which, upon the order, is in favor of the plaintiffs and against them in the original sum of $138,220 and the additional sum of $175,684.77, and the plaintiffs cross-appeal, on the ground of inadequacy, from so much of the same amended judgment as provided for the additional award of $175,684.77.

Ordered that the appeal from the order is dismissed, without costs or disbursements, and it is further,

[783]*783Ordered that the amended judgment is reversed, on the law, without costs or disbursements, the plaintiffs’ motion to amend the judgment is denied, the cross motion to vacate the stipulation dated December 2, 2004, and judgment entered September 16, 2005, is denied, without prejudice to the commencement of a plenary action seeking that relief, the judgment entered September 16, 2005, is reinstated, and the order is modified accordingly.

The plaintiffs Nir Zeer (hereinafter Zeer) and ZNN Development, Inc. (hereinafter ZNN), commenced this action to recover damages, inter alia, for breach of contract, against, among others, the defendants Ziv Azulay and Wagner Ziv Plumbing & Heating Corporation (hereinafter Wagner Ziv and collectively with Azulay, the defendants). In pertinent part, the plaintiffs alleged that pursuant to a September 2003 contract between ZNN and Wagner Ziv, the latter agreed to construct a three-family home on real property owned by ZNN at a site in Brooklyn. All work was to be completed within 160 days of the contract’s execution (Feb. 29, 2004), including the obtaining of a certificate of occupancy for the newly-constructed premises. The contract provided that if Wagner Ziv failed to timely complete the work, it was liable to ZNN for liquidated damages in the sum of $250 per day from February 29, 2004, until such work was completed.

The parties entered into a stipulation of settlement on December 2, 2004 (hereinafter the stipulation) which provided, in pertinent part, as follows: (1) Wagner Ziv would obtain a final certificate of occupancy for the property by December 27, 2004, or it would be subject to the $250 per day liquidated damages provision set forth in the September 2003 contract, and (2) if any parties filed liens or encumbrances on property owned by one or more of the parties, the party filing such lien would be liable for liquidated damages equal to double the amount of the lien or encumbrance. In July 2005 after Wagner Ziv failed to obtain a final certificate of occupancy for the premises, the plaintiffs moved, inter alia, for a judgment in their favor and against Wagner Ziv in the amount of $250 per day from February 29, 2004 pursuant to article V of the stipulation.

One month later, on August 10, 2005 ZNN sold the premises to a third party for the sum of $580,000. That same day, the defendants moved for a preliminary injunction, inter alia, to restrain the plaintiffs from encumbering, selling, or transferring any of ZNN’s assets upon the sale of the premises. The court granted a temporary restraining order (hereinafter the TRO) pending the return date of the motion. According to the defendants, the TRO and stay were necessary to insure that [784]*784they received the proper return on their considerable monetary investment in the premises.

Thereafter, in a judgment entered September 16, 2005, the court imposed upon Wagner Ziv liquidated damages in the sum of $250 per day from February 29, 2004 through September 2, 2005, a period of 551 days, totaling $137,750, plus $470 in costs and disbursements. September 2, 2005 had been the date a final certificate of occupancy had been obtained for the premises.

The plaintiffs thereafter moved to amend the judgment, seeking an additional award in their favor and against the defendants in the amount of $702,739.08, contending that they inadvertently failed to include such damages in the original judgment. According to the plaintiffs, by obtaining the TRO on August 10, 2005 the defendants prevented them from accessing ZNN’s corporate bank account, which then contained the sum of $351,369.54, thereby violating article VII of the stipulation and rendering the defendants liable for double the lien amount.

The defendants cross-moved to vacate the stipulation dated December 2, 2004 and to vacate the judgment entered September 16, 2005. In an order dated February 3, 2006 the court, inter alia, granted the plaintiffs’ motion to amend the judgment to the extent of awarding them an additional $175,684.77 in liquidated damages against the defendants, which the court explained is “equal to one half the amount of monies improperly restrained by said defendants.” The court denied all relief sought by the defendants.

The court thereafter issued an amended judgment that awarded the plaintiffs the sum of $138,220 (representing $250 per day for 551 days plus $470 in costs and disbursements) and $175,684.77 for the defendants’ violation of articles V and VII of the stipulation, respectively. The defendants appeal, inter alia, from the entire amended judgment and the plaintiffs cross-appeal to the extent that the amended judgment awarded them only an additional $175,684.77, instead of $702,739.08.

The Supreme Court properly denied that branch of the defendants’ cross motion which was to vacate the September 16, 2005, judgment which enforced the $250 per day liquidated damages provision of the stipulation, as the plaintiffs showed that at the time that the contract containing this liquidated damages provision originally had been entered into, the actual damages that the plaintiffs would sustain due to the defendants’ failure to obtain a certificate of occupancy were not ascertainable (see J. R. Stevenson Corp. v County of Westchester, 113 AD2d 918 [1985]).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of 27-10 37th Ave., LLC v. Nashasara, LLC
2024 NY Slip Op 06561 (Appellate Division of the Supreme Court of New York, 2024)
Church Extension Plan v. Harvest Assembly of God
79 A.D.3d 787 (Appellate Division of the Supreme Court of New York, 2010)
Central Irrigation Supply v. Putnam Country Club Associates, LLC
57 A.D.3d 934 (Appellate Division of the Supreme Court of New York, 2008)
Moshe v. Town of Ramapo
54 A.D.3d 1030 (Appellate Division of the Supreme Court of New York, 2008)
Global Crossing Bandwith, Inc. v. OLS, INC.
566 F. Supp. 2d 196 (W.D. New York, 2008)
Glazer v. Choong-Hee Lee
51 A.D.3d 970 (Appellate Division of the Supreme Court of New York, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
50 A.D.3d 781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nir-zeer-v-ziv-azulay-nyappdiv-2008.