NIPR, LLC v. Industrial Control Concepts, Inc. d/b/a ICC, Inc.

CourtCourt of Appeals of Washington
DecidedNovember 29, 2022
Docket38501-9
StatusUnpublished

This text of NIPR, LLC v. Industrial Control Concepts, Inc. d/b/a ICC, Inc. (NIPR, LLC v. Industrial Control Concepts, Inc. d/b/a ICC, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NIPR, LLC v. Industrial Control Concepts, Inc. d/b/a ICC, Inc., (Wash. Ct. App. 2022).

Opinion

FILED NOVEMBER 29, 2022 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

NIPR, LLC., a Washington limited ) liability company, ) No. 38501-9-III ) Respondent, ) ) v. ) ) UNPUBLISHED OPINION INDUSTRIAL CONTROL CONCEPTS, ) INC., d/b/a ICC, INC. a Missouri ) corporation, ICC NORTHWEST INC, an ) Oregon corporation, dba/aka ICC ) ENGINEERING LLC, a Missouri limited ) liability company, dba/aka ICC ) TURNKEY, INC., a Missouri corporation, ) dba/aka ICC HAWAII INDUSTRIAL ) STRUCTURES, INC., a Hawaii ) corporation, WYCKOFF FARMS, INC., a ) Washington corporation; AMERICAN ) CONTRACTORS INDEMNITY ) COMPANY, a domestic/foreign insurer; ) and ATLANTIC SPECIALTY ) INSURANCE COMPANY, a ) domestic/foreign insurer; ) ) Appellant. )

STAAB, J. — Wyckoff Farms, Inc., hired Industrial Control Concepts, Inc. (“ICC”)

for a large construction project. In turn, ICC hired NIPR, LLC, as a subcontractor for the

piping work on the project. Relations between Wyckoff Farms and ICC broke down No. 38501-9-III NIPR, LLC v. Wyckoff Farms, Inc.

when Wyckoff Farms discovered ICC’s failure to pay some of its contractors, including

NIPR. ICC and NIPR subsequently discontinued work on the project.

NIPR filed a construction lien against the Wyckoff Farms property and then filed

suit against Wyckoff Farms and ICC for unjust enrichment and foreclosure of its lien

claim. In its answer, Wyckoff admitted there was a contract between ICC and NIPR,

denied liability, and asserted numerous affirmative defenses. NIPR eventually moved for

summary judgment against Wyckoff Farms, alleging that it was entitled to judgment on

its lien claim. In its response, Wyckoff Farms argued that summary judgment was

premature and improper because there were several issues of material fact, and NIPR’s

motion failed to address Wyckoff’s affirmative defenses. The superior court denied

Wyckoff’s motion for a CR 56(f) continuance and granted NIPR’s summary judgment,

issuing an order foreclosing on NIPR’s lien claim.

On appeal, Wyckoff Farms claims that summary judgment was improper because

NIPR failed to produce evidence to prove the elements of a lien claim and failed to

address Wyckoff’s affirmative defenses. We hold that the trial court did not abuse its

discretion in denying a continuance for NIPR’s lien foreclosure claim, and Wyckoff

Farms failed to create a genuine issue of material fact as to elements of NIPR’s lien

claim. However, because the motion on summary judgment failed to include or address

Wyckoff’s affirmative defenses, those defenses survived summary judgment to the extent

2 No. 38501-9-III NIPR, LLC v. Wyckoff Farms, Inc.

that NIPR’s motion did not decide them. Consequently, it was error for the trial court to

issue a judgment foreclosing on NIPR’s lien claim.

BACKGROUND

Because this issue was decided in favor of NIPR on summary judgment, the

following facts are set forth in a light most favorable to Wyckoff Farms.

1. BACKGROUND

Wyckoff Farms hired ICC to help complete an extraction facility on Wyckoff

Farms’ property in Prosser, Washington (the Property) pursuant to multiple contracts (the

Project). Under one of the contracts, Wyckoff Farms agreed to pay ICC for piping work

on the facility on a time and materials basis. ICC hired NIPR, a subcontractor run by

husband and wife Alan Lichtenfels and Danielle Dukart, to supply labor, materials, and

equipment to complete the piping work.

NIPR began work on the project in October 2019. Five months later, after ICC

failed to pay NIPR’s invoices, NIPR threatened to leave the job. To keep NIPR on the

job, Wyckoff Farms made a direct payment of $113,000.00 to NIPR. Thereafter, the

relationship between Wyckoff Farms and ICC became increasingly strained. Ultimately,

ICC discontinued all work on the Project, as did NIPR.

In March 2020, NIPR claimed an outstanding balance of $235,045.02. In May,

NIPR filed a construction lien against the Property, asserting that it had ceased work on

the project on or about April 5, and claimed an unpaid principal balance of $314,792.15.

3 No. 38501-9-III NIPR, LLC v. Wyckoff Farms, Inc.

In June, NIPR recorded an amended claim of lien against the Property with the Benton

County Auditor. Shortly thereafter, Wyckoff Farms posted a release of lien bond with

the auditor.

2. JUDICIAL PROCEEDINGS

In October 2020, NIPR filed a complaint against Wyckoff Farms in Benton

County Superior Court, raising unjust enrichment and its lien claim. Wyckoff Farms

answered NIPR’s complaint, admitted the contract between NIPR and ICC, denied

liability, and raised numerous affirmative defenses, including fraud, estoppel, offset, and

waiver.

Nine months later, on July 7, 2021, Wyckoff Farms hired new counsel. On

August 13, NIPR filed a motion for summary judgment against Wyckoff Farms, arguing

that it was entitled to foreclosure of its lien. In support of its motion, NIPR provided

evidence that ICC hired NIPR as a subcontractor to supply labor, materials, and

equipment to improve the Property. NIPR also provided photographs of some of the

work that NIPR performed, invoices that had yet to be paid by ICC, and a spreadsheet

showing the total interest owed to NIPR on the outstanding balance.

NIPR’s attorney filed a declaration in support of the motion, attaching numerous

exhibits, including the claim of lien filed by NIPR, the complaint filed by NIPR, and

discovery responses NIPR received from Wyckoff Farms. A subpoena issued by

4 No. 38501-9-III NIPR, LLC v. Wyckoff Farms, Inc.

Wyckoff Farms to NIPR on February 1, 2020, was also attached.1 The declaration

indicated that all of NIPR’s invoices had been turned over to Wyckoff Farms as a part of

NIPR’s compliance with the subpoena.

Wyckoff Farms responded, arguing that NIPR failed to prove the existence of a

contract or “contract price” as between ICC and NIPR pursuant to RCW 60.04.021 and

RCW 60.04.011(2), respectively. Wyckoff Farms further argued that summary judgment

was precluded because Wyckoff Farms’ affirmative defenses were not addressed in

NIPR’s opening motion.

In support of its response to NIPR’s summary judgment, Wyckoff Farms filed

multiple declarations. The President and CEO of ICC, Alex Alexandrov, provided a

declaration, but all of his assertions were prefaced with the phrase, “it is my

understanding.” See Clerk’s Papers (CP) at 295-96. His declaration stated, in part, that it

was his understanding that NIPR had done work outside of the scope agreed to with ICC

and that NIPR was not entitled to payment for that work.

Wyckoff Farms presented the declaration of Patricia Westmoreland whom

Wyckoff Farms hired to audit ICC’s management of the Project as well as ICC’s

1 It appears from the record that Wyckoff Farms conducted little to no discovery in this action. The subpoena duces tecum described here was issued to NIPR as a part of a pending federal court action between Wyckoff Farms and ICC (Cause No. 4:20-cv- 05095-TOR) related to the same project.

5 No. 38501-9-III NIPR, LLC v. Wyckoff Farms, Inc.

subcontractors’ invoices, timecards, and backup.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. Key Pharmaceuticals, Inc.
770 P.2d 182 (Washington Supreme Court, 1989)
Hartley v. State
698 P.2d 77 (Washington Supreme Court, 1985)
Seven Gables Corp. v. MGM/UA Entertainment Co.
721 P.2d 1 (Washington Supreme Court, 1986)
Sandeman v. Sayres
314 P.2d 428 (Washington Supreme Court, 1957)
Coggle v. Snow
784 P.2d 554 (Court of Appeals of Washington, 1990)
Haselwood v. Bremerton Ice Arena, Inc.
155 P.3d 952 (Court of Appeals of Washington, 2007)
Pitzer v. Union Bank of Cal.
9 P.3d 805 (Washington Supreme Court, 2000)
Intermountain Elec., Inc. v. GAT BROS. CONST., INC.
62 P.3d 548 (Court of Appeals of Washington, 2003)
Owen v. Burlington Northern and Santa Fe RR Co.
108 P.3d 1220 (Washington Supreme Court, 2005)
Colorado Structures v. Blue Mountain Plaza
246 P.3d 835 (Court of Appeals of Washington, 2011)
Pitzer v. Union Bank of California
9 P.3d 805 (Washington Supreme Court, 2000)
Tellevik v. Real Property Known as 31641
838 P.2d 111 (Washington Supreme Court, 1992)
Keystone Land & Development Co. v. Xerox Corp.
94 P.3d 945 (Washington Supreme Court, 2004)
Owen v. Burlington Northern Santa Fe Railroad
153 Wash. 2d 780 (Washington Supreme Court, 2005)
Intermountain Electric, Inc. v. G-A-T Bros. Construction, Inc.
115 Wash. App. 384 (Court of Appeals of Washington, 2003)
Haselwood v. Bremerton Ice Arena, Inc.
137 Wash. App. 872 (Court of Appeals of Washington, 2007)
Colorado Structures, Inc. v. Blue Mountain Plaza, LLC
159 Wash. App. 654 (Court of Appeals of Washington, 2011)
Keck v. Collins
325 P.3d 306 (Court of Appeals of Washington, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
NIPR, LLC v. Industrial Control Concepts, Inc. d/b/a ICC, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nipr-llc-v-industrial-control-concepts-inc-dba-icc-inc-washctapp-2022.