Nika Technologies, Inc. v. United States

987 F.3d 1025
Court of Appeals for the Federal Circuit·Decided February 4, 2021·No. 20-1924·Published·Cited by 3 cases

Opinion

United States Court of Appeals for the Federal Circuit

NIKA TECHNOLOGIES, INC.,

Plaintiff

v.

UNITED STATES, Defendant-Appellant

2020-1924

Appeal from the United States Court of Federal Claims in No. 1:20-cv-00299-CFL, Senior Judge Charles F. Lettow.

Decided: February 4, 2021

JAMES WILLIAM POIRIER, Commercial Litigation Branch, Civil Division, United States Department of Justice , Washington, DC, argued for defendant-appellant. Also represented by JEFFREY B. CLARK, ROBERT EDWARD KIRSCHMAN, JR., DOUGLAS K. MICKLE.

Before PROST, Chief Judge, LOURIE and HUGHES, Circuit Judges.

HUGHES, Circuit Judge.

Bid protests filed at the Government Accountability Office within five days of debriefing invoke an automatic stay 2 NIKA TECHNOLOGIES, INC. v. UNITED STATES

of performance of the underlying contract under 31 U.S.C. § 3553(d). NIKA Technologies, Inc. filed a bid protest at the GAO six days after receiving a written debriefing regarding its failed bid on a government contract, but the GAO denied an automatic stay as untimely. NIKA filed an action at the Court of Federal Claims, which instituted the stay. The government appeals. Because we hold that the plain language of 31 U.S.C. § 3553(d) dictates that the deadline for invoking the automatic stay is five days after the written debriefing is supplied (unless, as discussed below, the protestor submits additional questions), we reverse.

I

The Army Corps of Engineers issued a request for proposals seeking services for its Operation and Maintenance Engineering and Enhancement Program. NIKA bid but was not awarded a contract, so the Corps alerted NIKA to its right to request a debriefing. NIKA made a timely request for debriefing. On March 4, 2020, the Corps sent NIKA a written debriefing and alerted NIKA of the right to submit additional questions. NIKA did not submit any additional questions. NIKA filed a protest at the GAO on March 10—six days after the written debriefing.

Under 31 U.S.C. § 3553(d), bid protests filed at the GAO invoke an automatic stay of procurement during the pendency of the protest if the federal agency awarding the contract receives notice within five days of debriefing. But here, the GAO denied the stay as untimely because NIKA did not file its protest with the GAO until six days after receiving a written debriefing.

NIKA then filed an action at the Court of Federal Claims on the theory that, although the debriefing period began upon receipt of the written debriefing, debriefing did not end until two days later. NIKA cited 10 U.S.C. § 2305(b)(5)(B)(vii), which states that “[t]he debriefing shall include . . . an opportunity for a disappointed offeror to submit, within two business days after receiving a post-

NIKA TECHNOLOGIES, INC. v. UNITED STATES 3

award debriefing, additional questions related to the debriefing .” The Court of Federal Claims sided with NIKA and instituted the stay.

Since that time, the bid protest has concluded, which means that the stay has also ended. Thus, although the government appeals, NIKA no longer has an interest in the case and has not responded.

II

As a threshold matter, we address whether the case is moot.

The order that the government challenges expired on June 5, 2020. J.A. 1. Thus, any decision from this court would not directly affect the parties, which presents mootness concerns. See DeFunis v. Odegaard, 416 U.S. 312, 317 (1974) (citations omitted) (noting that when a case “no longer ‘touch(es) the legal relations of parties having adverse legal interests’” it is generally moot).

However, there is an exception to the mootness doctrine for cases capable of repetition but evading review. “That exception applies ‘only in exceptional situations,’ where (1) ‘the challenged action [is] in its duration too short to be fully litigated prior to cessation or expiration,’ and (2) ‘there [is] a reasonable expectation that the same complaining party [will] be subject to the same action again.’” Kingdomware Techs., Inc. v. United States, 136 S. Ct. 1969, 1976 (2016) (quoting Spencer v. Kemna, 523 U.S. 1, 17 (1998)). We address these two prongs below.

A

Because of the legal time constraints, this is an issue that is evading review. Some cases are inherently unlikely to get through the judicial-review process before they would become moot. Here, by statute, GAO bid protests must be decided within 100 days of submission. 31 U.S.C. § 3554(a)(1). By regulation, the GAO does not decide 4 NIKA TECHNOLOGIES, INC. v. UNITED STATES

disputes about the stay of procurement activities. 4 C.F.R. § 21.6. Therefore, in order to receive judicial review regarding a GAO stay of procurement activities, a party has at most 100 days for proceedings at the Court of Federal Claims (concerning whether a protest at the GAO was filed in time for the protester to invoke the stay), for the United States to get permission to appeal, for the United States to file an appeal with this court, and for this court to consider and decide the case. Completing all these activities in 100 days is unrealistic, if not impossible. Therefore, this issue is evading review. See, e.g., Kingdomware Techs., Inc., 136 S. Ct. at 1976 (2016) (holding that an issue was evading review because there were only two years to complete judicial review before the case would be rendered moot).

B

This issue is also capable of repetition. “[T]he capableof -repetition doctrine applies… generally only where the named plaintiff can make a reasonable showing that he will again be subjected to the alleged illegality.” City of Los Angeles v. Lyons, 461 U.S. 95, 109 (1983). In other words, we must decide whether there is a reasonable expectation that the party invoking review here will run into this same problem again. See Kingdomware Techs, Inc., 136 S. Ct. at 1976. The question is “whether the controversy [is] capable of repetition and not . . . whether the claimant [has] demonstrated that a recurrence of the dispute was more probable than not.” Honig v. Doe, 484 U.S. 305, 318 n.6 (1988) (emphasis added). Here, there is a “reasonable expectation that” the government “[will] be subject to the same action again” because it is likely that future bid protestors will rely on the Court of Federal Claims’ decision below and wait beyond the deadline to invoke a stay of procurement. See Kingdomware Techs., Inc., 136 S. Ct. at 1976 (alteration in original). In 2019, there were 2,198 bid protests at the GAO, many of which involved potential stays on procurement . U.S. Gov’t Accountability Off., GAO-20-220SP, GAO Bid Protest Annual Report to Congress for Fiscal

NIKA TECHNOLOGIES, INC. v. UNITED STATES 5

Year 2019 (2019). The government will be involved in all future bid protests, and there is a reasonable expectation that the deadline will be missed by future bid protestors, given the number of protests and the short timeline for protests .

We hold that this issue is capable of repetition but evading review and therefore consider the merits.

III

One statutory incentive for bid protestors to file claims at the GAO rather than the Court of Federal Claims is that a bid protester is entitled to invoke a stay on procurement for the duration of the GAO proceedings. To invoke this stay, the protester must file at the GAO quickly, before one of two deadlines: within ten days of the contract award or within five days of the debriefing date offered for a required debriefing. These deadlines are codified in 31 U.S.C. § 3553(d), the statute at issue here, which we reproduce in part below:

(3)(A) If the Federal agency awarding the contract receives notice of a protest in accordance with this section during the period described in paragraph (4)—

(i) the contracting officer may not authorize performance of the contract to begin while the protest is pending;

...

Free access — add to your briefcase to read the full text and ask questions with AI

Nika Technologies, Inc. v. United States, 987 F.3d 1025 (Fed. Cir. 2021).

987 F.3d 1025 (Nika Technologies, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related