Nick Hardy v. Nyberg

CourtCourt of Appeals of Arizona
DecidedJanuary 14, 2016
Docket1 CA-CV 14-0671
StatusUnpublished

This text of Nick Hardy v. Nyberg (Nick Hardy v. Nyberg) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nick Hardy v. Nyberg, (Ark. Ct. App. 2016).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

NICK HARDY CONSTRUCTION, INC., Plaintiff/Counter-Defendant/Appellee,

v.

NORMA J. NYBERG, Defendant/Counter-Claimant/Appellant.

No. 1 CA-CV 14-0671 FILED 1-14-2016

Appeal from the Superior Court in Mohave County No. L8015CV20077171 The Honorable Randolph A. Bartlett, Retired Judge

VACATED AND REMANDED

COUNSEL

Law Offices of Phillip G. Krueger, Lake Havasu City By Phillip G. Krueger

Jones, Skelton & Hochuli, PLC, Phoenix By Eileen Dennis GilBride Co-Counsel for Plaintiff/ Counter-Defendant/Appellee

Wachtel, Biehn & Malm, Lake Havasu City By Jay B. Bidwell Counsel for Defendant/ Counter-Claimant/Appellant NICK HARDY v. NYBERG Decision of the Court

MEMORANDUM DECISION

Judge Maurice Portley delivered the decision of the Court, in which Presiding Judge Margaret H. Downie and Judge Patricia A. Orozco joined.

P O R T L E Y, Judge:

¶1 Norma J. Nyberg appeals the partial summary judgment granted to Nick Hardy Construction, Inc. (“Hardy”) on her counterclaims. For the following reasons, we vacate the judgment against Nyberg, direct entry of partial summary judgment in favor of Nyberg on the counterclaim for breach of contract, and remand for further proceedings relating to Nyberg’s damages.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 Nyberg hired Hardy to construct a house. Under the contract, Hardy was required to complete all work “in a workman-like manner and in compliance with all current building code[]s and other applicable laws.” During construction, Nyberg saw cracks and heaving in the concrete slab, and demanded Hardy stop construction.

Registrar of Contractor Proceedings

¶3 Nyberg filed a complaint against Hardy with the Registrar of Contractors (“ROC”) listing ten complaints—some of which related to the concrete slab. The matter went to a hearing before an administrative law judge (“ALJ”) and Nyberg testified that the non-concrete slab items in her ROC complaint were within standard and no longer issues. The ALJ subsequently found that the concrete slab “fails to comply with applicable industry and workmanship standards and requires appropriate correction” and concluded that Hardy failed to perform work in a professional and workman-like manner in violation of Arizona Revised Statutes (“A.R.S.”) section 32-1154(A)(3).1 The ALJ recommended Hardy’s contractor license be suspended until the concrete slab problems were corrected.

¶4 The ROC adopted the ALJ’s recommended order. Hardy did not appeal the ROC order, made the repairs, and filed a notice of compliance with the ROC. There was, at Nyberg’s request, a compliance

1 We cite the current version of applicable statutes unless otherwise stated.

2 NICK HARDY v. NYBERG Decision of the Court

hearing, and the ALJ found that Hardy’s “corrective actions” had been “completed to within applicable workmanship and industry standards.” Because the ALJ concluded that Hardy had complied with the terms and conditions of the ROC’s order, it was recommended the matter be closed. The ROC adopted the ALJ’s recommended compliance hearing order. Nyberg appealed the ROC order to the superior court, which affirmed the ROC’s decision. Nyberg v. Nick Hardy Construction, Inc. et al, CV 2009-4175, Court Order, dated Oct. 26, 2010.

Superior Court Proceedings in this Case

¶5 During the ROC proceedings, Hardy sued Nyberg for breach of contract and unjust enrichment for amounts due under the contract. Nyberg filed a counterclaim alleging breach of contract, negligence, and false reporting of a lien. She reiterated Hardy’s negligence in pouring the foundation and concrete slabs and sought incidental and consequential damages.

¶6 The parties filed competing motions for summary judgment on Nyberg’s counterclaims. Hardy argued that the doctrines of collateral estoppel and res judicata barred Nyberg’s counterclaims because she had litigated the workmanship of the concrete slab in the ROC proceeding. Hardy also argued that Nyberg testified before the ALJ that the other items were within standard and were no longer issues.

¶7 Nyberg argued she was entitled to summary judgment because “Hardy’s breach of contract was clearly established in prior litigation.” She also argued that her ROC testimony that she “had no workmanship issue” with the non-concrete slab related items did not preclude her from raising those issues because they related to her consequential damages. At oral argument on the competing motions, Hardy added that Nyberg did not request a civil penalty during the ROC proceedings.

¶8 The superior court denied Nyberg’s motion and granted Hardy summary judgment. The court found that the legal doctrines of res judicata and collateral estoppel applied and precluded Nyberg’s counterclaims based on the ruling affirming the ROC’s decision, Nyberg’s testimony at the ROC hearing that the only remaining construction issues were related to the concrete slab, and her failure to disclose or assert a claim for money damages or seek restitution during the ROC proceeding.

3 NICK HARDY v. NYBERG Decision of the Court

¶9 The superior court then entered judgment in Hardy’s favor on Nyberg’s counterclaims, which Nyberg timely appealed.2 We have jurisdiction pursuant to A.R.S. § 12-2101(A)(1).

DISCUSSION

¶10 Nyberg argues the trial court erred in applying the equitable doctrines of res judicata and collateral estoppel to preclude her counterclaim for breach of contract and associated damages.3 She asks us to vacate the order granting summary judgment to Hardy and to enter summary judgment as to her claim that Hardy is liable on her breach of contract claim.

¶11 We review the grant of summary judgment de novo and view all facts and reasonable inferences drawn therefrom in the light most favorable to Nyberg, against whom the judgment was granted. Lowe v. Pima Cty., 217 Ariz. 642, 646, ¶ 14, 177 P.3d 1214, 1218 (App. 2008) (citations omitted). Although we generally do not review the denial of a motion for summary judgment, we may do so if the denial is based on a point of law. Hourani v. Benson Hosp., 211 Ariz. 427, 430, ¶ 4, 122 P.3d 6, 9 (App. 2005) (citations omitted). Further, we may direct entry of summary judgment in

2 We dismissed Nyberg’s first appeal because the judgment lacked Rule 54(b) language and Hardy’s claims were pending. After the superior court granted Hardy judgment on its claims, Nyberg filed a second notice of appeal. Because that judgment did not contain language indicating that “no further matters remain[ed] pending,” we suspended the appeal and remanded the matter for an order complying with Rule 54(c). After the order was entered, we reinstated the appeal. And Nyberg’s second notice of appeal was timely. ARCAP 9(c). 3 Although Nyberg’s notice of appeal includes the judgment on Hardy’s claims, her opening brief only contests the judgment in Hardy’s favor on her breach of contract counterclaim. She has, as a result, waived any argument challenging the judgment on Hardy’s claims and the judgment on her negligence and false reporting of a lien counterclaims. See ARCAP 13(a)(6)–(7) (opening brief shall include “‘statement of the issues’ presented for review” and “contentions concerning each issue presented for review”); MacMillan v. Schwartz, 226 Ariz.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bothell v. Two Point Acres, Inc.
965 P.2d 47 (Court of Appeals of Arizona, 1998)
J.W. Hancock Enterprises, Inc. v. Arizona State Registrar of Contractors
690 P.2d 119 (Court of Appeals of Arizona, 1984)
Anderson v. Country Life Insurance
886 P.2d 1381 (Court of Appeals of Arizona, 1994)
Marriage of MacMillan v. Schwartz
250 P.3d 1213 (Court of Appeals of Arizona, 2011)
Lowe v. Pima County
177 P.3d 1214 (Court of Appeals of Arizona, 2008)
Hourani v. Benson Hospital
122 P.3d 6 (Court of Appeals of Arizona, 2005)
Bentivegna v. Powers Steel & Wire Products, Inc.
81 P.3d 1040 (Court of Appeals of Arizona, 2004)
Twin Peaks Construction Inc. v. Weatherguard Metal Construction, Inc.
154 P.3d 378 (Court of Appeals of Arizona, 2007)
KCI Restaurant Management LLC v. Holm Wright Hyde & Hays PLC
341 P.3d 1156 (Court of Appeals of Arizona, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Nick Hardy v. Nyberg, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nick-hardy-v-nyberg-arizctapp-2016.