Nicholson v. Atchison, Topeka & Santa Fe Railway Co.

147 P. 1123, 95 Kan. 13, 1915 Kan. LEXIS 164
CourtSupreme Court of Kansas
DecidedApril 10, 1915
DocketNo. 19,206; No. 19,472
StatusPublished
Cited by1 cases

This text of 147 P. 1123 (Nicholson v. Atchison, Topeka & Santa Fe Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nicholson v. Atchison, Topeka & Santa Fe Railway Co., 147 P. 1123, 95 Kan. 13, 1915 Kan. LEXIS 164 (kan 1915).

Opinion

The opinion of the court was delivered by

Burch, J.:

The action was one for damages for personal injuries. The plaintiff recovered and the defendant appeals.

[14]*14The defendant, desiring to construct a line of rail-toad running in a southwesterly direction from Dodge City, a division point on its main line, chose to accomplish its purpose through the medium of a corporation which it organized, officered, and financed entirely within itself. The roadbed was constructed by one firm of contractors and the track was laid by another. The rails were relay rails taken from other parts of the Santa Fe system, and train crews and train service were furnished to the contractors, who laid the track. W. H. Durbin, an employee of the defendant on its eastern division, was appointed trainmaster and track inspector of the new line. Previous to June 11, 1912, some twenty-five miles of track had been laid. The track had been fully spiked and surfaced, had been inspected and passed by the track inspector to a point some distance beyond a bridge just west of a place called Ensign, and the track inspector had authorized a speed of ten miles per hour over this portion of the track. The plaintiff, who had been an employee of the defendant for a number of years, was assigned to a construction train on the new line, as conductor. No other engine having sufficient power being available, the defendant supplied a, switch engine, with footboards at the front and rear, for use in operating the construction train. On the morning of June 11, 1912, the plaintiff left Ensign with his train, carrying construction materials, • for the site of the construction work some miles beyond. The plaintiff, Durbin, and Joe Ault, who was boss tracklayer of the construction crew, were riding on the footboard of the engine. As they came near the bridge west of Ensign the plaintiff observed that Ault had a spike hammer in his hand and asked what he intended to do with it. Ault replied that he intended to spike down some bad track near a bridge. The plaintiff signaled the engineer to slow down, which the engineer did, when Ault said “This is not the bridge.” The speed of the engine had been reduced to about four [15]*15miles per hour, and when it passed over the approach to the bridge the track sunk, the footboard caught on the bridge, was turned under and broken off, and the plaintiff was dragged a considerable distance before the engine stopped. He was badly bruised and mangled, and died in November, 1913, soon after the trial of the ease was concluded. Revivor proceedings took such a course that two appeals were docketed in this court.

The ground of the action was negligence in the construction, inspection, and maintenance of the track at the place where the plaintiff was injured. The defense was that the plaintiff assumed the risk of injury at all times while engaged in construction work.

An effort was made to show that the plaintiff had equal opportunity with the defendant to know, and that he did know, the condition of the roadbed and track at the time and place of injury. The§e matters were determined adversely to the defendant by findings of fact returned by the jury. It was the plaintiff’s business to deliver construction material by means of his train at places designated by those having authority over that subject. He was not engaged in constructing roadbed or in laying track. Contractors were employed for that purpose, and the plaintiff’s duties consisted in moving his train over the track provided for him. The plaintiff freely admitted knowledge of conditions at the front, where his engine would frequently go off the track because rails were not spiked and surfacing was not done, but the engine never went off the track going to and from work, it did not rock particularly, the plaintiff noticed no depressions where the track had been surfaced, knew of no bad track where it had been surfaced, and did not notice any unevenness of the track at the place where the injury occurred when he passed over it returning from the front on the evening of June 10. The track had been inspected and had been passed by the official upon whose judgment he had the right to rely. It had taken on the character of [16]*16permanency and he had been authorized to run his train at more than double the rate of speed at which he was moving when the accident occurred. He did not observe any sinking of the track near the bridge at the time of the accident soon enough to avoid injury.

The result of the foregoing is that the defendant must rely upon the claim already indicated, that the plaintiff assumed the risk of injury at all points along the new line while construction work was in progress and until the line was open for general transportation purposes.- Manifestly this claim is too broad.

It was the duty of the defendant to make even construction work at the very front as safe as work of that character can reasonably be made, and the plaintiff assumed only those hazards which inhered in construction work performed with reasonable care. As track laying progressed the same general standard of care applied to stretches of completed track left behind. The plaintiff might well assume the risk of using unsurfaced track only partially spiked, or even held simply by bridle bars, at the site of track-laying operations, but after track had been laid and safer conditions were practicable it was the duty of the defendant to establish them. Indeed, the defendant recognized and undertook to discharge this duty to persons who were obliged to go back and forth between material yards and the front. The inspector stated that it was his duty to see that the proper number of ties were used, that rails were properly spiked and plated, and that the track was properly lined and surfaced. Conceding the right of a master to conduct his business according to his own methods, within the limits of reasonable prudence already outlined, the inspector was stationed in the midst of the defendant’s scheme of construction work and the plaintiff assumed those risks only which inhered in the operation of a construction train over inspected and accepted track while upon track of that kind. He assumed no risk of injury from defective con[17]*17struction of which he was ignorant and which proper inspection would have disclosed or anticipated.

It appears that the track sunk at the end of the bridge because of rain which had fallen upon it. After the accident Durbin posted a bulletin to all conductors not to take trains out on the new line after heavy rains until advised by him to do so. ' The plaintiff was then in a hospital.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
147 P. 1123, 95 Kan. 13, 1915 Kan. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nicholson-v-atchison-topeka-santa-fe-railway-co-kan-1915.