RENDERED: JUNE 5, 2026; 10:00 A.M. NOT TO BE PUBLISHED
Commonwealth of Kentucky Court of Appeals NO. 2025-CA-0468-MR
NICHOLAS SLOWIK AND SPRING SLOWIK APPELLANTS
APPEAL FROM KENTON CIRCUIT COURT v. HONORABLE PATRICIA M. SUMME, JUDGE ACTION NO. 23-CI-01374
GUARDIAN SAVINGS BANK, INC. APPELLEE
OPINION AFFIRMING
** ** ** ** **
BEFORE: THOMPSON, CHIEF JUDGE; ECKERLE AND MOYNAHAN, JUDGES.
MOYNAHAN, JUDGE: Appellants Nicholas and Spring Slowik (the “Slowiks”),
appeal from a Kenton Circuit Court order granting summary judgment to Appellee
Guardian Savings Bank, Incorporated (“Guardian”). After careful review, we
AFFIRM. BACKGROUND
The Slowiks set out to build a home in Kenton County in 2021. They
chose Adam Miller Homes, LLC (“Miller Homes”), to construct a house in the
small city of Villa Hills. The total project cost was estimated to be $576,889. The
Slowiks tendered a $15,000 downpayment and contracted with Guardian to finance
the remainder of the project. Under the terms of the resulting construction loan
agreement, Miller Homes submitted draw requests to Guardian after key portions
of the project were completed. A Guardian employee then inspected the premises
to ensure the draw request was proportionate to the stage of work completed and
generated a report detailing the inspection findings for Guardian’s recordkeeping.
Upon receiving this verification, Guardian would issue a check in the amount of
the draw request. All of the checks were made out to the Slowiks who had to
affirmatively sign them over to Miller Homes, before the latter could access the
funds. The Slowiks chose to deal directly with their builder and did not employ a
project manager, general contractor, designer, or homeowner’s representative to
oversee the building process.
Between June 2021 and March 2022, Guardian issued three checks,
totaling approximately $484,000, to the Slowiks. Miller Homes informed the
Slowiks contemporaneously with the first draw request that the project would not
be completed within the original timeline. According to Mr. Slowik, the couple
-2- was then informed of delays “constantly” throughout the project. (Trial Record
(“T.R.”) p. 244). Despite the delays, the Slowiks still co-signed each of the three
draw checks, allowing Miller Homes full access to the proceeds as scheduled.
In May 2022, Miller Homes requested payment for multiple change
orders that had accrued on the project.1 The Slowiks expressed unwillingness to
pay for the change orders due to continued project delays. Consequently, Miller
Homes and the Slowiks negotiated to a lower amount that the couple personally
funded and paid in June 2022. At this point approximately $78,000 remained in
the Guardian construction loan account. Miller Homes offered to complete the
house for the remaining undisbursed loan funds. The Slowiks declined this offer,
terminated Miller Homes, and hired a different builder. Guardian disbursed the
remaining money in the account to the Slowiks who paid it to their new builder.
The Slowiks then sued Guardian for breach of contract and fraudulent
misrepresentation.
PROCEDURAL HISTORY
The Slowiks filed a complaint against Guardian in August of 2023.
Guardian moved for summary judgment in February 2025, and a hearing on that
motion was held the next month. On April 1, 2025, the Kenton Circuit Court
1 Per the terms of the construction loan agreement, the Slowiks were financially responsible for all change orders.
-3- granted summary judgment in favor of Guardian. The Slowiks timely filed a
notice of appeal less than two weeks later.
STANDARD OF REVIEW
“The proper standard of review on appeal when a trial judge has
granted a motion for summary judgment is whether the record, when examined in
its entirety, shows there is no genuine issue as to any material fact and the moving
party is entitled to a judgment as a matter of law.” Motorists Mutual Ins. Co. v.
First Specialty Ins. Corp., 706 S.W.3d 120, 124 (Ky. 2024) (internal quotation
marks and citations omitted). As the appropriateness of summary judgment is
ultimately a legal question that involves no factual determinations, a trial court’s
grant of summary judgment is reviewed de novo. Lewis v. B & R Corp., 56
S.W.3d 432, 436 (Ky. App. 2001). Further, “[t]he record must be viewed in a light
most favorable to the party opposing the motion for summary judgment and all
doubts are to be resolved in his favor.” Steelvest, Inc. v. Scansteel Serv. Ctr., Inc.,
807 S.W.2d 476, 480 (Ky. 1991).
ANALYSIS
I. Noncompliant Filing
The Slowiks’ brief states that, since this case involves interpretation
of a contract, “[T]here is no reason to include any legal authority in this Brief.”
The Kentucky Rules of Appellate Procedure (“RAP”) beg to differ. Specifically,
-4- RAP 32(A)(4) states that an Appellant’s brief must contain an argument
conforming to a statement of points and authorities, with ample reference to the
specific location in the record and citations of authority pertinent to each issue of
law. Grants or denials of summary judgment, as well as matters of contract
interpretation, are questions of law subject to de novo review at the appellate level.
Stowe v. Realco Ltd. Liab. Co., 551 S.W.3d 462, 465 (Ky. App. 2018). Therefore,
the Slowiks’ refusal to tender legal authority is particularly striking since their
entire appeal is based solely on matters of law. We note that it is not the role of the
appellate court to research and construct a party’s legal arguments. Hadley v.
Citizen Deposit Bank, 186 S.W.3d 754 (Ky. App. 2005).
Despite this obvious omission, the Slowiks did cite to specific
locations in the record and advanced arguments based upon those citations.
Therefore, we decline to grant Guardian’s request to strike the Slowiks’ brief from
consideration due to noncompliance. However, counsel for the Slowiks is
reminded that “[f]ailing to comply with the civil rules is an unnecessary risk the
appellate advocate should not chance.” Curty v. Norton Healthcare, Inc., 561
S.W.3d 374, 378 (Ky. App. 2018). With this preliminary matter addressed, we
turn to the merits of the appeal.
-5- II. Breach of Contract
Three basic elements are required to support a finding of breach of
contract: (1) existence of a contract, (2) breach of the contract, and (3) damages
flowing from that breach. Barnett v. Mercy Health Partners-Lourdes, Inc., 233
S.W.3d 723, 727 (Ky. App. 2007). Both parties herein agree that a valid contract
existed. Therefore, our analysis turns on whether that existing contract was
breached.
The Slowiks and Guardian executed three agreements to govern the
terms of their contractual relationship. The first was the overall construction loan
agreement (“Loan Agreement”), that established the basic financing framework for
the project. The second and third agreements were Guardian’s standard guidelines
for construction draws (“Guidelines”) and their construction inspection and
disbursement procedures (“Procedures”), respectively.
Free access — add to your briefcase to read the full text and ask questions with AI
RENDERED: JUNE 5, 2026; 10:00 A.M. NOT TO BE PUBLISHED
Commonwealth of Kentucky Court of Appeals NO. 2025-CA-0468-MR
NICHOLAS SLOWIK AND SPRING SLOWIK APPELLANTS
APPEAL FROM KENTON CIRCUIT COURT v. HONORABLE PATRICIA M. SUMME, JUDGE ACTION NO. 23-CI-01374
GUARDIAN SAVINGS BANK, INC. APPELLEE
OPINION AFFIRMING
** ** ** ** **
BEFORE: THOMPSON, CHIEF JUDGE; ECKERLE AND MOYNAHAN, JUDGES.
MOYNAHAN, JUDGE: Appellants Nicholas and Spring Slowik (the “Slowiks”),
appeal from a Kenton Circuit Court order granting summary judgment to Appellee
Guardian Savings Bank, Incorporated (“Guardian”). After careful review, we
AFFIRM. BACKGROUND
The Slowiks set out to build a home in Kenton County in 2021. They
chose Adam Miller Homes, LLC (“Miller Homes”), to construct a house in the
small city of Villa Hills. The total project cost was estimated to be $576,889. The
Slowiks tendered a $15,000 downpayment and contracted with Guardian to finance
the remainder of the project. Under the terms of the resulting construction loan
agreement, Miller Homes submitted draw requests to Guardian after key portions
of the project were completed. A Guardian employee then inspected the premises
to ensure the draw request was proportionate to the stage of work completed and
generated a report detailing the inspection findings for Guardian’s recordkeeping.
Upon receiving this verification, Guardian would issue a check in the amount of
the draw request. All of the checks were made out to the Slowiks who had to
affirmatively sign them over to Miller Homes, before the latter could access the
funds. The Slowiks chose to deal directly with their builder and did not employ a
project manager, general contractor, designer, or homeowner’s representative to
oversee the building process.
Between June 2021 and March 2022, Guardian issued three checks,
totaling approximately $484,000, to the Slowiks. Miller Homes informed the
Slowiks contemporaneously with the first draw request that the project would not
be completed within the original timeline. According to Mr. Slowik, the couple
-2- was then informed of delays “constantly” throughout the project. (Trial Record
(“T.R.”) p. 244). Despite the delays, the Slowiks still co-signed each of the three
draw checks, allowing Miller Homes full access to the proceeds as scheduled.
In May 2022, Miller Homes requested payment for multiple change
orders that had accrued on the project.1 The Slowiks expressed unwillingness to
pay for the change orders due to continued project delays. Consequently, Miller
Homes and the Slowiks negotiated to a lower amount that the couple personally
funded and paid in June 2022. At this point approximately $78,000 remained in
the Guardian construction loan account. Miller Homes offered to complete the
house for the remaining undisbursed loan funds. The Slowiks declined this offer,
terminated Miller Homes, and hired a different builder. Guardian disbursed the
remaining money in the account to the Slowiks who paid it to their new builder.
The Slowiks then sued Guardian for breach of contract and fraudulent
misrepresentation.
PROCEDURAL HISTORY
The Slowiks filed a complaint against Guardian in August of 2023.
Guardian moved for summary judgment in February 2025, and a hearing on that
motion was held the next month. On April 1, 2025, the Kenton Circuit Court
1 Per the terms of the construction loan agreement, the Slowiks were financially responsible for all change orders.
-3- granted summary judgment in favor of Guardian. The Slowiks timely filed a
notice of appeal less than two weeks later.
STANDARD OF REVIEW
“The proper standard of review on appeal when a trial judge has
granted a motion for summary judgment is whether the record, when examined in
its entirety, shows there is no genuine issue as to any material fact and the moving
party is entitled to a judgment as a matter of law.” Motorists Mutual Ins. Co. v.
First Specialty Ins. Corp., 706 S.W.3d 120, 124 (Ky. 2024) (internal quotation
marks and citations omitted). As the appropriateness of summary judgment is
ultimately a legal question that involves no factual determinations, a trial court’s
grant of summary judgment is reviewed de novo. Lewis v. B & R Corp., 56
S.W.3d 432, 436 (Ky. App. 2001). Further, “[t]he record must be viewed in a light
most favorable to the party opposing the motion for summary judgment and all
doubts are to be resolved in his favor.” Steelvest, Inc. v. Scansteel Serv. Ctr., Inc.,
807 S.W.2d 476, 480 (Ky. 1991).
ANALYSIS
I. Noncompliant Filing
The Slowiks’ brief states that, since this case involves interpretation
of a contract, “[T]here is no reason to include any legal authority in this Brief.”
The Kentucky Rules of Appellate Procedure (“RAP”) beg to differ. Specifically,
-4- RAP 32(A)(4) states that an Appellant’s brief must contain an argument
conforming to a statement of points and authorities, with ample reference to the
specific location in the record and citations of authority pertinent to each issue of
law. Grants or denials of summary judgment, as well as matters of contract
interpretation, are questions of law subject to de novo review at the appellate level.
Stowe v. Realco Ltd. Liab. Co., 551 S.W.3d 462, 465 (Ky. App. 2018). Therefore,
the Slowiks’ refusal to tender legal authority is particularly striking since their
entire appeal is based solely on matters of law. We note that it is not the role of the
appellate court to research and construct a party’s legal arguments. Hadley v.
Citizen Deposit Bank, 186 S.W.3d 754 (Ky. App. 2005).
Despite this obvious omission, the Slowiks did cite to specific
locations in the record and advanced arguments based upon those citations.
Therefore, we decline to grant Guardian’s request to strike the Slowiks’ brief from
consideration due to noncompliance. However, counsel for the Slowiks is
reminded that “[f]ailing to comply with the civil rules is an unnecessary risk the
appellate advocate should not chance.” Curty v. Norton Healthcare, Inc., 561
S.W.3d 374, 378 (Ky. App. 2018). With this preliminary matter addressed, we
turn to the merits of the appeal.
-5- II. Breach of Contract
Three basic elements are required to support a finding of breach of
contract: (1) existence of a contract, (2) breach of the contract, and (3) damages
flowing from that breach. Barnett v. Mercy Health Partners-Lourdes, Inc., 233
S.W.3d 723, 727 (Ky. App. 2007). Both parties herein agree that a valid contract
existed. Therefore, our analysis turns on whether that existing contract was
breached.
The Slowiks and Guardian executed three agreements to govern the
terms of their contractual relationship. The first was the overall construction loan
agreement (“Loan Agreement”), that established the basic financing framework for
the project. The second and third agreements were Guardian’s standard guidelines
for construction draws (“Guidelines”) and their construction inspection and
disbursement procedures (“Procedures”), respectively. The Guidelines stated: “No
funds will be disbursed in advance of work being completed.” (T.R. p. 386). The
Procedures stated: “No funds will be released prior to work being completed.”
(T.R. p. 221).
The dispute turns on the nature of the parties’ contractual relationship
and whether the Guidelines and Procedures were inherent promises that Guardian
made to the Slowiks or simply procedural descriptions of the draw process. We
find that they were the latter. This interpretation results from our review of the
-6- Loan Agreement. At its core, the Loan Agreement is a straightforward contract
between a for-profit financial institution that lends money in order to realize a
profit and an individual borrower planning to build a house. Guardian did not gift
the Slowiks money to build a house; they lent them money with an eye toward
being able to mortgage the finished house and turn a profit on the transaction.
Guardian and the Slowiks had a clear creditor-debtor relationship. Accordingly,
the Loan Agreement was drafted to protect Guardian’s financial interest in the
collateral property with provisions that required the Slowiks to construct a house
valued at a certain dollar amount, as well as provisions that expressly reserved
Guardian’s right to waive its Guidelines and Procedures at any time with or
without the Slowiks’ input or consent.2 The Slowiks argue that the Guidelines and
Procedures were promises to them that the project would be completed according
to their expectations, but this is a mischaracterization of the nature of the parties’
underlying relationship. Guardian’s reassuring name notwithstanding, the Loan
Agreement, as written, does not contain any discernible intent to forge a fiduciary
relationship. And courts have repeatedly found that—in almost all
circumstances—banks do not have fiduciary relationships with their debtors. See,
e.g., Scott v. Forcht Bank, NA, 521 S.W.3d 591 (Ky. App. 2017) (citing De Jong v.
Leitchfield Deposit Bank, 254 S.W.3d 817, 822 (Ky. App. 2007)); see also Sparks
2 See Loan Agreement, § 2, Paragraph 1 and Paragraph 3.
-7- v. Fifth Third Mortgage Company, No. 5:17-450-KKC, 2018 WL 6424699, at *2-3
(E.D. Ky. Dec. 6, 2018) (bank administering a construction loan is not an insurer
or a fiduciary of its debtor). The contractual terms here established a typical
creditor-debtor relationship, and Guardian met all its contractual obligations.
Therefore, there was no breach.
Finding that no breach occurred, it is unnecessary to determine
whether damages ensued. However, to the extent the Slowiks allege they sustained
losses, any such damages were self-inflicted. Miller Homes was willing to
complete the house—at a loss—for the $78,000 remaining in the loan account and
communicated their willingness to do so to the Slowiks. The Slowiks, however,
refused this offer, terminated Miller Homes, and procured a new builder who,
presumably, charged the full completion cost for the remaining work. Just as
Guardian cannot be charged with fiduciary responsibility for the project’s timeline
or alignment with the Slowiks’ personal preferences, it likewise cannot be charged
with financial responsibility for an independent decision that compounded, rather
than mitigated, the Slowiks’ potential financial deficit.
III. Fraudulent Misrepresentation
The Slowiks also assert a tort claim for fraudulent misrepresentation.
A finding of fraud requires clear and convincing proof of six elements: (1) a
material representation made to the plaintiff, (2) the representation was false, (3)
-8- the declarant knew the representation was false or made it recklessly, (4) the
declarant induced the plaintiff to act upon the false representation, (5) the plaintiff
relied upon the misrepresentation, and (6) the misrepresentation injured the
plaintiff in some way. Flegles, Inc. v. TruServ Corp., 289 S.W.3d 544 (Ky. 2009).
The Slowiks specifically alleged that Guardian misrepresented the
amount of work completed, prematurely issued draw checks based on these alleged
misrepresentations, and failed to obtain required documentation before issuing
checks. The evidence shows that Guardian’s disbursement policy is based on
completion of major project benchmarks, i.e., 25% for the laying of a foundation,
25% for installation of the roof and windows, 25% for interior framing and
drywall, and 25% upon final project completion. Individual line items like the hot
water heater and kitchen backsplash that the Slowiks referenced, do not factor into
the bank’s disbursement methodology. The reports the Slowiks characterize as
fraudulent representations are actually internal working documents compiled for
Guardian’s in-house recordkeeping. (T.R. p. 219; T.R. p. 227). Those reports
were never intended to serve as a progress check or punch list for the Slowiks’
personal reference. Despite some acknowledged errors in the inspection reports
regarding individual components, there is no evidence that Guardian ever deviated
from its established disbursement policy that ties construction draws to project
-9- benchmarks. Nor is there any evidence that these project benchmarks had not been
met when the draw checks were issued to the Slowiks.
Additionally, given their access and ability to inspect the project for
themselves, the Slowiks assertion that they relied to their detriment on Guardian’s
representations is unavailing. The contract terms did not imbue Guardian’s in-
house inspection reports with an express warranty or assurance that certain project
components beyond the benchmarks had been completed. Guardian’s actions also
in no way prohibited the Slowiks from performing their own inspections or some
other level of basic due diligence during the building process. Further, it was not
Guardian’s responsibility to shepherd the project to completion by a certain date.
The bank’s role here was to disburse funds when key project benchmarks were
reached in order to protect its collateral interest.
As to the Slowiks’ claim that Guardian failed to procure required
documentation prior to issuing draw checks, the record shows that Guardian
obtained a sworn builder’s affidavit from Miller Homes for each of the three
checks issued as well as reviewed photographs of the site’s progress taken by its
own inspector. Ultimately, however, the Slowiks’ fraudulent misrepresentation
claim primarily fails due to their inability to identify any specific fraudulent
misrepresentation. The complaint did not identify any such misrepresentation.
-10- And, most notably, when Mr. Slowik was questioned under oath, he could not
identify a single fraudulent misrepresentation put forth by Guardian. (T.R. p. 250).
Thus, the record supports the trial court’s determination that Guardian
made no false representations of past or present material facts to the Slowiks.
Therefore, the summary judgment standard as set forth in Steelvest was satisfied.
CONCLUSION
For the foregoing reasons, the Kenton Circuit Court’s order granting
summary judgment to Guardian is hereby AFFIRMED.
ALL CONCUR.
BRIEFS FOR APPELLANT: BRIEF FOR APPELLEE:
Steven A. Taylor Daniel J. Knecht Fort Mitchell, Kentucky N. Kathleen Dudgeon Jeffrey M. Hendricks Fort Wright, Kentucky
-11-