Nicholas Slowik v. Guardian Savings Bank, Inc.

Court of Appeals of Kentucky·Decided June 5, 2026·No. 2025-CA-0468·Unpublished

Opinion

RENDERED: JUNE 5, 2026; 10:00 A.M.

NOT TO BE PUBLISHED

Commonwealth of Kentucky

Court of Appeals

NO. 2025-CA-0468-MR

NICHOLAS SLOWIK AND SPRING SLOWIK APPELLANTS

APPEAL FROM KENTON CIRCUIT COURT v. HONORABLE PATRICIA M. SUMME, JUDGE ACTION NO. 23-CI-01374

GUARDIAN SAVINGS BANK, INC. APPELLEE

OPINION

AFFIRMING

** ** ** ** **

BEFORE: THOMPSON, CHIEF JUDGE; ECKERLE AND MOYNAHAN, JUDGES.

MOYNAHAN, JUDGE: Appellants Nicholas and Spring Slowik (the “Slowiks”), appeal from a Kenton Circuit Court order granting summary judgment to Appellee Guardian Savings Bank, Incorporated (“Guardian”). After careful review, we AFFIRM.

BACKGROUND

The Slowiks set out to build a home in Kenton County in 2021. They chose Adam Miller Homes, LLC (“Miller Homes”), to construct a house in the small city of Villa Hills. The total project cost was estimated to be $576,889. The Slowiks tendered a $15,000 downpayment and contracted with Guardian to finance the remainder of the project. Under the terms of the resulting construction loan agreement, Miller Homes submitted draw requests to Guardian after key portions of the project were completed. A Guardian employee then inspected the premises to ensure the draw request was proportionate to the stage of work completed and generated a report detailing the inspection findings for Guardian’s recordkeeping. Upon receiving this verification, Guardian would issue a check in the amount of the draw request. All of the checks were made out to the Slowiks who had to affirmatively sign them over to Miller Homes, before the latter could access the funds. The Slowiks chose to deal directly with their builder and did not employ a project manager, general contractor, designer, or homeowner’s representative to oversee the building process.

Between June 2021 and March 2022, Guardian issued three checks, totaling approximately $484,000, to the Slowiks. Miller Homes informed the Slowiks contemporaneously with the first draw request that the project would not be completed within the original timeline. According to Mr. Slowik, the couple

was then informed of delays “constantly” throughout the project. (Trial Record (“T.R.”) p. 244). Despite the delays, the Slowiks still co-signed each of the three draw checks, allowing Miller Homes full access to the proceeds as scheduled.

In May 2022, Miller Homes requested payment for multiple change orders that had accrued on the project.1 The Slowiks expressed unwillingness to pay for the change orders due to continued project delays. Consequently, Miller Homes and the Slowiks negotiated to a lower amount that the couple personally funded and paid in June 2022. At this point approximately $78,000 remained in the Guardian construction loan account. Miller Homes offered to complete the house for the remaining undisbursed loan funds. The Slowiks declined this offer, terminated Miller Homes, and hired a different builder. Guardian disbursed the remaining money in the account to the Slowiks who paid it to their new builder. The Slowiks then sued Guardian for breach of contract and fraudulent misrepresentation.

PROCEDURAL HISTORY

The Slowiks filed a complaint against Guardian in August of 2023.

Guardian moved for summary judgment in February 2025, and a hearing on that motion was held the next month. On April 1, 2025, the Kenton Circuit Court

1 Per the terms of the construction loan agreement, the Slowiks were financially responsible for all change orders.

granted summary judgment in favor of Guardian. The Slowiks timely filed a notice of appeal less than two weeks later.

STANDARD OF REVIEW

“The proper standard of review on appeal when a trial judge has granted a motion for summary judgment is whether the record, when examined in its entirety, shows there is no genuine issue as to any material fact and the moving party is entitled to a judgment as a matter of law.” Motorists Mutual Ins. Co. v. First Specialty Ins. Corp., 706 S.W.3d 120, 124 (Ky. 2024) (internal quotation marks and citations omitted). As the appropriateness of summary judgment is ultimately a legal question that involves no factual determinations, a trial court’s grant of summary judgment is reviewed de novo. Lewis v. B & R Corp., 56 S.W.3d 432, 436 (Ky. App. 2001). Further, “[t]he record must be viewed in a light most favorable to the party opposing the motion for summary judgment and all doubts are to be resolved in his favor.” Steelvest, Inc. v. Scansteel Serv. Ctr., Inc., 807 S.W.2d 476, 480 (Ky. 1991).

ANALYSIS

I. Noncompliant Filing The Slowiks’ brief states that, since this case involves interpretation of a contract, “[T]here is no reason to include any legal authority in this Brief.” The Kentucky Rules of Appellate Procedure (“RAP”) beg to differ. Specifically,

RAP 32(A)(4) states that an Appellant’s brief must contain an argument conforming to a statement of points and authorities, with ample reference to the specific location in the record and citations of authority pertinent to each issue of law. Grants or denials of summary judgment, as well as matters of contract interpretation, are questions of law subject to de novo review at the appellate level. Stowe v. Realco Ltd. Liab. Co., 551 S.W.3d 462, 465 (Ky. App. 2018). Therefore, the Slowiks’ refusal to tender legal authority is particularly striking since their entire appeal is based solely on matters of law. We note that it is not the role of the appellate court to research and construct a party’s legal arguments. Hadley v. Citizen Deposit Bank, 186 S.W.3d 754 (Ky. App. 2005).

Despite this obvious omission, the Slowiks did cite to specific locations in the record and advanced arguments based upon those citations. Therefore, we decline to grant Guardian’s request to strike the Slowiks’ brief from consideration due to noncompliance. However, counsel for the Slowiks is reminded that “[f]ailing to comply with the civil rules is an unnecessary risk the appellate advocate should not chance.” Curty v. Norton Healthcare, Inc., 561 S.W.3d 374, 378 (Ky. App. 2018). With this preliminary matter addressed, we turn to the merits of the appeal.

II. Breach of Contract Three basic elements are required to support a finding of breach of contract: (1) existence of a contract, (2) breach of the contract, and (3) damages flowing from that breach. Barnett v. Mercy Health Partners-Lourdes, Inc., 233 S.W.3d 723, 727 (Ky. App. 2007). Both parties herein agree that a valid contract existed. Therefore, our analysis turns on whether that existing contract was breached.

The Slowiks and Guardian executed three agreements to govern the terms of their contractual relationship. The first was the overall construction loan agreement (“Loan Agreement”), that established the basic financing framework for the project. The second and third agreements were Guardian’s standard guidelines for construction draws (“Guidelines”) and their construction inspection and disbursement procedures (“Procedures”), respectively. The Guidelines stated: “No funds will be disbursed in advance of work being completed.” (T.R. p. 386). The Procedures stated: “No funds will be released prior to work being completed.” (T.R. p. 221).

The dispute turns on the nature of the parties’ contractual relationship and whether the Guidelines and Procedures were inherent promises that Guardian made to the Slowiks or simply procedural descriptions of the draw process. We find that they were the latter. This interpretation results from our review of the

Free access — add to your briefcase to read the full text and ask questions with AI

Nicholas Slowik v. Guardian Savings Bank, Inc., (Ky. Ct. App. 2026).

Nicholas Slowik v. Guardian Savings Bank, Inc. (Nicholas Slowik v. Guardian Savings Bank, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Flegles, Inc. v. Truserv Corp.
289 S.W.3d 544 (Kentucky Supreme Court, 2009)
Lewis v. B & R CORPORATION
56 S.W.3d 432 (Court of Appeals of Kentucky, 2001)
De Jong v. Leitchfield Deposit Bank
254 S.W.3d 817 (Court of Appeals of Kentucky, 2007)
Steelvest, Inc. v. Scansteel Service Center, Inc.
807 S.W.2d 476 (Kentucky Supreme Court, 1991)
Barnett v. Mercy Health Partners-Lourdes, Inc.
233 S.W.3d 723 (Court of Appeals of Kentucky, 2007)
Hadley v. Citizen Deposit Bank
186 S.W.3d 754 (Court of Appeals of Kentucky, 2005)
Scott v. Forcht Bank, NA
521 S.W.3d 591 (Court of Appeals of Kentucky, 2017)
Stowe v. Realco Ltd. Liab. Co.
551 S.W.3d 462 (Court of Appeals of Kentucky, 2018)
Curty v. Norton Healthcare, Inc.
561 S.W.3d 374 (Court of Appeals of Kentucky, 2018)