NextG Networks of California, Inc. v. County of Los Angeles

522 F. Supp. 2d 1240, 2007 U.S. Dist. LEXIS 82776, 2007 WL 3306774
CourtDistrict Court, C.D. California
DecidedJune 20, 2007
DocketCV 07-2425 ABC (CTx)
StatusPublished
Cited by4 cases

This text of 522 F. Supp. 2d 1240 (NextG Networks of California, Inc. v. County of Los Angeles) is published on Counsel Stack Legal Research, covering District Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NextG Networks of California, Inc. v. County of Los Angeles, 522 F. Supp. 2d 1240, 2007 U.S. Dist. LEXIS 82776, 2007 WL 3306774 (C.D. Cal. 2007).

Opinion

ORDER GRANTING IN PART PLAINTIFF’S MOTION FOR PRELIMINARY INJUNCTION

AUDREY B. COLLINS, District Judge.

On April 19, 2007, Plaintiff NextG Networks of California, Inc. (“Plaintiff’) filed the instant motion for a preliminary injunction. Defendant County of Los Ange-les (the “County”) opposed on May 21, 2007, and Plaintiff replied on May 29, 2007. The hearing on this matter was held on June 18, 2007. Based on the arguments of the parties and the pleadings in this case, the Court hereby GRANTS IN PART the motion for a preliminary injunction.

I. INTRODUCTION

Title 22 of the Los Angeles County Municipal Code, the County’s zoning ordinance, has been in effect since 1927. However, that ordinance has now come into conflict with the federal Telecommunications Act (the “TCA”), 47 U.S.C. § 253 (1996), and the Court must decide which law prevails.

Plaintiff is a telecommunications company seeking to utilize the rights-of-way in the County for its telecommunications services. The County seeks to manage the rights-of-way for the ten-million-plus people in Los Angeles County. To do that, the County has imposed on Plaintiff the Conditional Use Permits Ordinance (“CUP”), section 22.56 of the County Code, a process through which Plaintiff can gain approval for erecting its equipment on public property. Plaintiff claims the process is so cumbersome so as to erect a *1243 barrier to its entry into the telecommunications market.

In the TCA, Congress anticipated this precise conflict and determined that any state or local laws erecting such barriers must be preempted. The Court finds that, in this case, this Congressional mandate trumps and section 22.56 must be preempted.

II. FACTUAL AND PROCEDURAL BACKGROUND

Plaintiff is a communications service provider and a “telephone corporation” as defined by California law. Specifically, Plaintiff holds a “Certificate of Public Convenience or Necessity” from the California Public Utilities Commission, which authorizes it to operate as a telephone corporation under California law. (Declaration of Patrick S. Ryan (“Ryan Deck”) ¶ 4.) Plaintiff provides the “transport” of voice and data communications between points designated by customers without altering the communications. (Declaration of Nicole Mason (“Mason Deck”) ¶ 5.) Plaintiffs customers are not end-users, but are typically providers of retail wireless services which in turn provide services to end-users. (Id.)

Plaintiffs typical telecommunications service offering involves a communication signal handed off from Plaintiffs customer to Plaintiff, which Plaintiff then transports over a network of fiber optic facilities. (Id. ¶ 5.) These handoffs take place via equipment called “nodes” located on utility or streetlight poles in public rights-of-way or in private utility easements. (Id. ¶ 6.) These nodes, which include, inter alia, antenna, fiber optic lines, and a power supply, are all owned, operated, and maintained by Plaintiff. (Id.) Plaintiffs equipment also includes a fiber optic network that carries signals to a “base station,” a structure often on private property, which is where Plaintiff then returns the signal to the customer. (Id. ¶ 7.)

To construct the nodes and lay the fiber optic cabling, Plaintiff must have access to County rights-of-way. (Id. ¶ 8.) Timing of this access has become critical to Plaintiff because it has undertaken contractual obligations that impose strict timelines on providing service. (Id. ¶ 11.) For example, under its current contracts, Plaintiff must have both the fiber optics and the nodes ready for one customer by November 30, 2007 and for another customer, by December 31, 2007. (Id.) This is apparently no easy task, requiring Plaintiff to undertake at least the following steps:

• Coordinating with other utilities using any right-of-way, which can take anywhere from sixty to ninety-plus days;
• Securing a[CUP] under the County’s ordinances;
• Securing an encroachment permit once a CUP is approved;
• Constructing the nodes on existing utility poles, which takes at least 20 days;
• Obtaining electric services once the nodes are installed;
• Testing and optimizing the newly installed equipment, which itself takes two to three weeks minimum; and
• Engineering and installing fiber optics aerially and/or underground, which entails a multi-step process of route selection, design, and field surveys.

(Declaration of Todd Schultz (“Schultz Deck”) ¶¶ 8-9.) Plaintiff asserts that the only way to meet its current contractual deadlines is to initiate construction of the nodes and fiber optics by September 30, 2007. (Id. ¶ 11.)

Plaintiff has worked with the County on these projects in the past. (Declaration of Patrick S. Ryan (“Ryan Deck”) ¶3.) For example, in August 2005, Plaintiff sought *1244 three encroachment permits from the County, which the County summarily rejected, forcing Plaintiff instead to undertake the more cumbersome CUP process set forth in section 22.56 of the County’s zoning code. (Id.) Plaintiff claims that, although its proposed installations are similar to many other facilities that are located in the rights-of-way pursuant to encroachment permits, the County insisted on imposing the CUP process on it. (Id.) Plaintiff submitted CUP applications in January 2006, which the County approved in November 2006 and issued some two months later. (Id.)

Similarly, in early 2006, Plaintiff sought approval for another significant project. (Id. ¶ 4.) Plaintiff informed the County that it qualified as a telephone corporation under California law and must be treated nondiscriminatorily, but the County still required Plaintiff to proceed via the CUP process. (Id.) Because the parties disputed the application of the CUP process to Plaintiffs activities, the County agreed to “expedite” treatment of Plaintiffs CUP applications. (Id. ¶7.) Plaintiff then successfully deployed that project, which took six months. (Mason Deck ¶ 20.)

For the projects arising from Plaintiffs current contractual obligations, Plaintiff applied for CUPs on March 1, March 15, and April 3, 2007. (Id. ¶ 18.) The County has not agreed to expedite the consideration of these applications, however. (Id. ¶ 19.) Plaintiff fears the CUP approval process will delay commencing construction beyond its September 30, 2007 deadline. (Id.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
522 F. Supp. 2d 1240, 2007 U.S. Dist. LEXIS 82776, 2007 WL 3306774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nextg-networks-of-california-inc-v-county-of-los-angeles-cacd-2007.