Next Modular, LLC v. Holmes

CourtDistrict Court, W.D. Michigan
DecidedAugust 23, 2023
Docket1:22-cv-00421
StatusUnknown

This text of Next Modular, LLC v. Holmes (Next Modular, LLC v. Holmes) is published on Counsel Stack Legal Research, covering District Court, W.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Next Modular, LLC v. Holmes, (W.D. Mich. 2023).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

NEXT MODULAR, LLC,

Plaintiff, Case No. 1:22-cv-421 v. Hon. Hala Y. Jarbou QADREE R. HOLMES, Trustee of the Qadree R. Holmes Trust, et al.,

Defendants. ___________________________________/ OPINION Plaintiff Next Modular, LLC brings this suit against Qadree R. Holmes and Troy W. Holmes, each as trustee of their respective trusts, for breach of contract and unjust enrichment. Defendants bring counterclaims against Plaintiff for breach of contract and to quiet title. Before the Court is Plaintiff’s motion for summary judgment (ECF No. 29) as well as Defendant’s motion for partial summary judgment (ECF No. 32). For the reasons stated below, the Court will grant in part and deny in part both motions. I. FACTUAL BACKGROUND On August 31, 2020, Plaintiff and Defendants entered into a contract (the “Construction Contract”) whereby Plaintiff agreed to build and Defendants agreed to buy a home located at 80 Pershing Street in South Haven, Michigan. (See Constr. Contract, ECF No. 34-1, PageID.259.) The Construction Contract sets a base price of $111,895.00. (Id., PageID.260.) However, [a]ny and all site work apart from the factory-built modular home structure is not calculated into the above price, and shall be detailed in the attached document titled “SITE WORK SPECIFICATIONS – APPENDIX B,” including all estimated costs regarding the same. Buyer understands and agrees that all site work detailed in Appendix B is subject to final bid, and agrees to pay for all costs arising from Builder’s efforts to coordinate for the completion of this work, which shall be detailed in Appendix B. (Id.) The following provisions in the Construction Contract are also relevant to this dispute: SITE WORK ESTIMATES AND MANAGEMENT FEES: “Site Work” shall refer to any work on the property, listed on “Appendix B” of this contract, that is completed by Subcontractors and coordinated by Builder. “Site Work Management Fees” shall refer to Builder markup and profits assigned to the site work. Buyer understands and agrees that any representation from Builder of expected costs regarding any subcontracted site work is subject to final bid. Any change orders to the scope of work detailed on Appendix B shall be detailed on a written change order, including applicable Site Work Management fees and must be approved in writing by the Buyer. . . . SUBCONTRACTORS: For the purpose of coordinating the work listed under “SITE WORK SPECIFICATIONS – APPENDIX B” Builder shall, using Builder’s best judgment, procure material and equipment and enter into contracts with various Subcontractors in order to cause this work to be completed. At any time Buyer shall have the right to procure, review, request changes to or reject any: 1) Subcontractor or laborer that Builder deems sufficient to complete the required work, 2) estimate or quote from any Subcontractor or laborer for completion of the work, or 3) equipment or materials purchased, delivered, or installed on the property, with the understanding that Buyer shall be wholly responsible for any costs incurred as a result. If Buyer rejects Builder’s Subcontractor or laborer then Builder shall not be liable for errors, omissions or negligence by any Subcontractor that w[as] not chosen by the Builder. CHANGE ORDERS: Any changes to this contract must be in writing and executed by all parties to the contract . . . . (Id. (emphasis in original).) Appendix B to the Construction Contract lists the estimated charges for site work including, for example, the cost of electric, flooring, appliances, tree removal, landscaping, and a garage. (Id., PageID.273.) It further states that [i]t is understood by all parties that these estimates are subject to final bid. Buyer shall be responsible for any and all monetary liabilities that arise from Builder’s efforts to complete the specific above noted tasks in [a] good faith effort to complete Builder’s responsibilities arising from the execution of this contract. (Id.) The Construction Contract estimated that the total cost of the home—including the home itself, options and upgrades, site work, and a contingency allowance—would be $303,072.00. (Id., PageID.279.) In 2022, Plaintiff informed Defendants that the total cost of the home was now $321,313.70. (Comino Statements, ECF No. 32-3, PageID.236.) This new total includes the

entirety of the $22,450.00 contingency allowance as well as $18,241.70 in project overage. (Id.) Plaintiff’s owner, Joel Comino, explained that the price increased as a result of an “unprecedented spike in the construction material and labor markets” that affected the cost of the site work. (2/21/2022 Comino Email, ECF No. 32-8, PageID.243.) Defendants previously paid $199,117.00 of that total amount, and Plaintiff filed this lawsuit seeking the remainder, $122,196.70. (Id.) However, Defendants dispute the validity of this remaining amount. Defendants believe that Plaintiff improperly increased the amount owed for the site work and, thus, is only entitled to $94,606.00. On February 24, 2023, the parties entered into a partial settlement agreement (“Settlement

Agreement”). Under the Settlement Agreement, Defendants agreed to pay $94,606.00, or the amount that is not disputed between the parties. (Settlement Agreement, ECF No. 35, PageID.286.)1 Accordingly, it appears that the amount remaining in dispute is $27,590.70, or $122,196.70 if Defendants have yet to abide by the Settlement Agreement.2

1 Plaintiff filed an affidavit from Joel Comino. (See Comino Aff., ECF No. 31-1.) In this affidavit, Comino avers that Plaintiff is still owed the entire $122,196.70, meaning Defendants have yet to pay the amount listed in the Settlement Agreement. The Local Rules require all affidavits filed in support of or in opposition to a motion “bear a scanned image of all original manuscript signatures.” L.Civ.R. 5.6(d)(iii). Comino’s affidavit lacks a manuscript signature. Accordingly, the Court will not consider it as evidence when ruling on the pending motions. 2 Defendants argue that the amount in dispute is actually $23,091.70. Defendants arrived at this number by adding the contingency allowance ($22,450.00) to the project overage ($18,241.70) and then subtracting the alleged total amount of five separate charge orders ($17,600.00). However, Defendants have only provided the Court with one charge order for $2,400.00. (See Charge Order, ECF No. 32-5.) Without more evidence, the Court cannot discern II. LEGAL STANDARD Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). A fact is material if it “might affect the outcome of the suit.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A material fact is genuinely disputed when there is “sufficient

evidence favoring the nonmoving party for a jury to return a verdict for that party.” Id. at 249 (citing First Nat’l Bank of Ariz. v. City Serv. Co., 391 U.S. 253, 288-89 (1961)). Summary judgment is not an opportunity for the Court to resolve factual disputes. Id. The Court “must shy away from weighing the evidence and instead view all the facts in the light most favorable to the nonmoving party and draw all justifiable inferences in their favor.” Wyatt v. Nissan N. Am., Inc., 999 F.3d 400, 410 (6th Cir. 2021). “This standard of review remains the same for reviewing cross-motions for summary judgment.” Ohio State Univ. v. Redbubble, Inc., 989 F.3d 435, 411 (6th Cir. 2021).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
McDonald v. Farm Bureau Insurance
747 N.W.2d 811 (Michigan Supreme Court, 2008)
In Re EGBERT R SMITH TRUST
745 N.W.2d 754 (Michigan Supreme Court, 2008)
Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
JPMorgan Chase Bank, N.A. v. Winget
510 F.3d 577 (Sixth Circuit, 2007)
Port Huron Education Ass'n v. Port Huron Area School District
550 N.W.2d 228 (Michigan Supreme Court, 1996)
Wolverine World Wide, Inc. v. Wolverine Canada, Inc.
653 F. Supp. 2d 747 (W.D. Michigan, 2009)
Suzanne Derbabian v. Bank of America, N.A.
587 F. App'x 949 (Sixth Circuit, 2014)
Innovation Ventures v. Liquid Manufacturing
885 N.W.2d 861 (Michigan Supreme Court, 2016)
EMW Women's Surgical Ctr. v. Andrew Beshear
920 F.3d 421 (Sixth Circuit, 2019)
Rita Kendzierski v. County of MacOmb
931 N.W.2d 604 (Michigan Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Next Modular, LLC v. Holmes, Counsel Stack Legal Research, https://law.counselstack.com/opinion/next-modular-llc-v-holmes-miwd-2023.