NewSun Energy, LLC v. PUC

346 Or. App. 545
CourtCourt of Appeals of Oregon
DecidedJanuary 22, 2026
DocketA181991
StatusPublished

This text of 346 Or. App. 545 (NewSun Energy, LLC v. PUC) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NewSun Energy, LLC v. PUC, 346 Or. App. 545 (Or. Ct. App. 2026).

Opinion

No. 22 January 22, 2026 545

IN THE COURT OF APPEALS OF THE STATE OF OREGON

NEWSUN ENERGY LLC, a Delaware limited liability company, Petitioner, v. PUBLIC UTILITY COMMISSION OF OREGON, an agency of the State of Oregon, Respondent, and IDAHO POWER COMPANY, PacifiCorp dba Pacific Power, and Portland General Electric Company, Intervenor-Respondents. Public Utility Commission of Oregon A181991

Argued and submitted January 6, 2025. Jonathan Harlan argued the cause for petitioner. On the briefs were Casey M. Nokes, Richard G. Lorenz, Tyler R. Whitney and Cable Huston LLP. Jordan Silk, Assistant Attorney General, argued the cause for respondent. Also on the brief were Ellen F. Rosenblum, Attorney General, and Benjamin Gutman, Solicitor General. Jordan R. Schoonover argued the cause for intervenor-re- spondents Idaho Power Company, Pacific Power and Portland General Electric Company. Also on the brief was Adam Lowney, Lynne Dzubow and McDowell Rackner Gibson PC. Before Ortega, Presiding Judge, Hellman, Judge, and O’Connor, Judge.* HELLMAN, J. Rules held valid. _______________ * O’Connor, Judge vice Mooney, Senior Judge. 546 NewSun Energy, LLC v. PUC Cite as 346 Or App 545 (2026) 547

HELLMAN, J. In this proceeding under ORS 183.400, petitioner NewSun Energy, LLC challenges rules amended and pro- mulgated by the Public Utility Commission of Oregon (PUC) in 2023, which are part of OAR chapter 860, division 029. Specifically, PUC’s 2023 rulemaking amended or added the following rules: OAR 860-029-0005, 860-029-0010, 860- 029-0044, 860-029-0045, 860-029-0046, 860-029-0047, 860-029-0120, 860-029-0121, 860-029-0123, and 860-029- 0124 (collectively, the 2023 rules). NewSun asserts that the 2023 rules are invalid in their entirety because PUC failed to provide the notice required by ORS 183.335. NewSun also asserts that PUC exceeded its authority in adopting two specific rules—OAR 860-029-0120(2) and OAR 860- 029-0121(5)—because those rules conflict with ORS 758.525 and do not conform to legislative policy expressed in ORS 758.515. PUC, along with intervenors Idaho Power Company, PacifiCorp, and Portland General Electric Company, defend the validity of the rules. We conclude that PUC substantially complied with the notice requirement in ORS 183.335, and that PUC did not exceed its statutory authority in adopting OAR 860-029- 0120(2) and OAR 860-029-0121(5), as argued by NewSun. Therefore, we hold the 2023 rules valid. I. LEGAL AND PROCEDURAL BACKGROUND At the outset, we provide a brief description of the legal backdrop for this rule challenge, which is grounded in federal law. The federal Public Utility Regulatory Policies Act of 1978 (PURPA), 16 USC section 824a-3, requires the Federal Energy Regulatory Commission (FERC) to prescribe rules “to encourage cogeneration and small power produc- tion,” and “which rules require electric utilities to offer to (1) sell electric energy to qualifying cogeneration facilities and qualifying small power production facilities and (2) pur- chase electric energy from such facilities.” 16 USC § 824a- 3(a). Qualifying cogeneration facilities and qualifying small power production facilities are called “qualifying facilities” or QFs and are defined by rule. See 18 CFR § 292.101(b)(1) (defining qualifying facility); see also OAR 860-029-0010(50) 548 NewSun Energy, LLC v. PUC

(defining qualifying facility). PURPA also directs state agen- cies, like PUC, to implement the FERC rules with respect to electric utilities for which it has ratemaking authority. 16 USC § 824a-3(f)(1). Oregon implements PURPA and its enacting rules through ORS 758.505 to 758.555, and through PUC’s implementing rules in OAR chapter 860, division 029, which apply to the “interconnection, purchase, and sale arrangements between a public utility and facili- ties that are qualifying facilities.” OAR 860-029-0005(1); see also OAR 860-029-0001. Under those rules, PUC requires public utilities to “offer standard non-renewable avoided cost rates to eli- gible qualifying facilities,” OAR 860-029-0043, and “offer standard power purchase agreements to eligible qualifying facilities,” OAR 860-029-0120(1). Eligibility for a standard avoided cost rate and purchase agreement (standard con- tract) is provided by rule, OAR 869-020-0045, and many of the rules in OAR chapter 860, division 029, including the 2023 rules, govern those standard contracts, including by supplying standard terms and conditions. For qualifying facilities that are not eligible for a standard contract, pub- lic utilities are required to offer “nonstandard avoided cost rates and nonstandard power purchase agreements” (non- standard contracts), as provided in OAR 860-029-0130, a rule that was not amended in 2023. The rulemaking at issue here began in July 2019, when PUC opened Docket No. AR 631 for a rulemaking to address “Procedures, Terms, and Conditions Associated with Qualifying Facilities (QF) Standard Contracts.” In 2021, PUC staff informally proposed rule changes to obtain input from stakeholders, and obtained that input through workshops, public meetings, and receipt of com- ments. PUC filed the official notice of proposed rulemak- ing on November 23, 2022, and following comment and a public hearing, PUC adopted the proposed rules by order (except one), and also adopted a subsequent order contain- ing corrections to the adopted rules. In July 2023, PUC filed the final adopted rules with the Secretary of State, and NewSun brought this judicial review challenging the validity of those rules. Cite as 346 Or App 545 (2026) 549

II. ANALYSIS Under ORS 183.400(4), we may declare a rule invalid only if the rule “[v]iolates constitutional provisions,” “[e]xceeds the statutory authority of the agency,” or “[w]as adopted without compliance with applicable rulemaking pro- cedures.” NewSun challenges the 2023 rules on two of those bases: (1) The 2023 rules are invalid because PUC failed to comply with the notice requirement in ORS 183.335, and (2) PUC exceeded its statutory authority in adopting OAR 860-029-0120(2) and OAR 860-029-0121(5). In addressing NewSun’s challenges, we are limited to examining “[t]he rule under review,” “[t]he statutory provisions authorizing the rule,” and “[c]opies of all documents necessary to demon- strate compliance with applicable rulemaking procedures.” ORS 183.400(3). A. Challenge to the Adequacy of the Rulemaking Notice We first address NewSun’s challenge to PUC’s rulemaking notice under ORS 183.335. Planned Parenthood Assn. v. Dept. of Human Res., 297 Or 562, 565, 687 P2d 785 (1984) (stating that procedural challenges should be addressed before challenges to the agency’s scope of authority for the rule).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burke v. State
290 P.3d 790 (Oregon Supreme Court, 2012)
State v. Gaines
206 P.3d 1042 (Oregon Supreme Court, 2009)
Wolf v. Oregon Lottery Commission
182 P.3d 180 (Oregon Supreme Court, 2008)
Snow Mountain Pine Co. v. Maudlin
734 P.2d 1366 (Court of Appeals of Oregon, 1987)
Fremont Lumber Co. v. Energy Facility Siting Council
936 P.2d 968 (Oregon Supreme Court, 1997)
Planned Parenthood Ass'n v. Department of Human Resources
687 P.2d 785 (Oregon Supreme Court, 1984)
Sundermier v. State ex rel. Public Employees Retirement System
344 P.3d 1142 (Court of Appeals of Oregon, 2015)
Columbia Riverkeeper v. ODFW
345 Or. App. 213 (Court of Appeals of Oregon, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
346 Or. App. 545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newsun-energy-llc-v-puc-orctapp-2026.