NewSun Energy, LLC v. Public Utility Comm.

561 P.3d 1135, 336 Or. App. 515
CourtCourt of Appeals of Oregon
DecidedDecember 4, 2024
DocketA178808
StatusPublished
Cited by1 cases

This text of 561 P.3d 1135 (NewSun Energy, LLC v. Public Utility Comm.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NewSun Energy, LLC v. Public Utility Comm., 561 P.3d 1135, 336 Or. App. 515 (Or. Ct. App. 2024).

Opinion

No. 869 December 4, 2024 515

IN THE COURT OF APPEALS OF THE STATE OF OREGON

NEWSUN ENERGY, LLC, a Delaware limited liability company, Petitioner-Appellant, v. PUBLIC UTILITY COMMISSION, an agency of the State of Oregon, Respondent-Respondent, and PORTLAND GENERAL ELECTRIC COMPANY, Intervenor-Respondent. Marion County Circuit Court 22CV05442; A178808

Jodie A. Bureta, Judge. Argued and submitted March 18, 2024. Casey M. Nokes argued the cause for appellant. Also on the briefs were Richard G. Lorenz and Cable Huston, LLP. Dustin Buehler, Assistant Attorney General, argued the cause for respondent Oregon Public Utility Commission. Also on the brief were Ellen F. Rosenblum, Attorney General, and Benjamin Gutman, Solicitor General. Dallas DeLuca argued the cause for respondent Portland General Electric Company. Also on the brief were Kathryn P. Roberts and Markowitz Herbold, PC. Joni Sliger, Irion A. Sanger, and Sanger Law, PC, filed the brief amicus curiae for Northwest and Intermountain Power Producers. Before Ortega, Presiding Judge, Powers, Judge, and Hellman, Judge. ORTEGA, P. J. Judicial review dismissed as moot. 516 NewSun Energy, LLC v. Public Utility Comm. Cite as 336 Or App 515 (2024) 517

ORTEGA, P. J. In this administrative “other than contested case” under ORS 183.484, petitioner NewSun Energy LLC (NewSun) seeks judicial review of a circuit court judgment that dismissed its petition for lack of subject matter juris- diction. NewSun had sought review in the circuit court of a Public Utility Commission (PUC) order approving Portland General Electric Company’s (PGE) 2021 request for pro- posal (RFP) to acquire energy resources as part of its utility resource planning process. The circuit court concluded that PUC’s order was not a “final order” subject to judicial review and dismissed the petition. NewSun seeks review of that decision. While the case was pending in this court, PGE filed a motion to dismiss the case as moot because it has completed the 2021 RFP process and a decision from this court will not have a practical effect on the rights of the par- ties. We conclude that this case is moot, and we decline to exercise our discretion to review the case under the author- ity in ORS 14.175. Thus, we dismiss. We set out the background necessary to provide context for our disposition. Prior to a rate-making case, reg- ulated utilities, like PGE, engage in a utility resource plan- ning process. In short, that planning has two steps: First, the utility files an integrated resource plan for future resource needs, which PUC acknowledges in an order. See OAR 860-027-0400 (integrated resource plan filing and review). Second, the utility engages in a competitive resource pro- curement process for certain resource acquisitions, which includes development of an RFP to solicit bids, among other steps. See OAR 860-089-0010 - 860-089-0550 (resource pro- curement for electric companies). As part of that process, PUC approves the proposed RFP in an order. OAR 860-089- 0250 (request for proposal design and approval). Following that approval, the utility solicits bids, scores those bids as provided in the RFP, and prepares a shortlist of top bid- ders. See OAR 860-089-0400 (bid scoring and evaluation). Following input from an independent evaluator and others, PUC acknowledges the shortlist before the utility negotiates with bidders. OAR 860-089-0450 (independent evaluator duties); OAR 860-089-0500 (shortlist acknowledgment). 518 NewSun Energy, LLC v. Public Utility Comm.

This case comes out of PGE’s 2021 RFP process. In May 2021, PUC acknowledged PGE’s update to its 2019 inte- grated resource plan, which contemplated major resource acquisitions through a single RFP process. In April 2021, PGE started the resource procurement process through ini- tiation of PUC Docket Number UM 2166. As part of that process, PGE designed and submitted a draft RFP. After taking comments from interested parties, stakeholders, PUC staff, and the independent evaluator, in December 2021, PUC issued Order 21-460 approving PGE’s RFP with modifications. NewSun sought judicial review of PUC’s approval order by initiating this case in the circuit court. In its peti- tion, NewSun asserted that PUC exceeded its authority in issuing the order because “it failed to give effect to key pro- visions” of a new law, House Bill (HB) 2021 (2021), that went into effect on September 25, 2021. See Or Laws 2021, ch 508, §§ 2, 40. NewSun sought an order from the circuit court requiring PUC to comply with HB 2021, section 2, para- graph 2, by requiring modifications to PGE’s RFP “such as by scoring criteria, preferences, or other measures related to in-state siting.”1 NewSun also sought an injunction staying the order and the 2021 RFP process. PUC, joined by PGE, filed a motion to dismiss NewSun’s petition on the basis that the order was not a reviewable “final order” under the Oregon Administrative Procedures Act (APA). The circuit court granted that motion, and NewSun now seeks review of that decision. Before briefing was completed in this case, PGE, joined by PUC, brought a motion to dismiss. While NewSun’s case proceeded, so did PGE’s 2021 RFP process. In August 2022, PUC acknowledged PGE’s final shortlist of bidders. At 1 HB 2021, section 2, paragraph 2, was codified as ORS 469A.405(2) and provides: “It is the policy of the State of Oregon: “* * * * * “(2) That electricity generated in a manner that produces zero green- house gas emissions also be generated, to the maximum extent practicable, in a manner that provides additional direct benefits to communities in this state in the forms of creating and sustaining meaningful living wage jobs, promoting workforce equity and increasing energy security and resiliency[.]” Cite as 336 Or App 515 (2024) 519

that point, PGE negotiated with bidders and entered into contracts with the successful bidders. PUC staff also filed a letter acknowledging the completion of the 2021 RFP pro- cess. As a result, PGE asserts that NewSun’s judicial review case is moot. We typically will not decide cases that have become moot. State v. K. J. B., 362 Or 777, 785, 416 P3d 291 (2018). “[A] case becomes moot when a court’s decision ‘will no lon- ger have a practical effect on the rights of the parties.’ ” Id. (quoting Brownstone Homes Condo. Ass’n v. Brownstone Forest Heights, LLC, 358 Or 26, 30, 361 P3d 1 (2015)). The burden is on the party moving for dismissal to establish that the case is moot. Id. The responding party then “must identify any collateral consequences that he or she contends has the effect of producing the required practical effects of a judicial decision.” Id. at 786. The moving party then has the burden to demonstrate that the identified collateral conse- quence “either does not exist or is legally insufficient.” Id. Here, PGE asserts that the case is moot because the 2021 RFP process is complete—PGE has negotiated and signed contracts with the successful bidders. PGE argues that, as a result, a court’s decision on NewSun’s petition challenging PUC’s order approving the RFP would have no practical effect on the rights of the parties. NewSun, however, argues that the case is not moot because its petition is primarily concerned with ensuring that PUC complies with the law through the judicial review process in ORS 183.484.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Searles v. Board of Parole
Court of Appeals of Oregon, 2026
Justice Resource Center v. Dept. of Corrections
338 Or. App. 643 (Court of Appeals of Oregon, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
561 P.3d 1135, 336 Or. App. 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newsun-energy-llc-v-public-utility-comm-orctapp-2024.