Newmech Companies v. Independent School District No. 206

558 N.W.2d 22, 1997 Minn. App. LEXIS 115, 1997 WL 29517
CourtCourt of Appeals of Minnesota
DecidedJanuary 28, 1997
DocketC5-96-1434
StatusPublished

This text of 558 N.W.2d 22 (Newmech Companies v. Independent School District No. 206) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newmech Companies v. Independent School District No. 206, 558 N.W.2d 22, 1997 Minn. App. LEXIS 115, 1997 WL 29517 (Mich. Ct. App. 1997).

Opinion

OPINION

DAVIES, Judge.

Appellant NewMech Cos., Inc. (NewMech), challenges the district court’s award, from an injunction bond, of attorney fees to respondents, claiming that the district court misinterpreted the injunction bond law. We reverse and remand.

FACTS

NewMech commenced an action alleging that respondents Independent School District No. 206 (School District) and Manning Mechanical, Inc. (Manning), violated Mnn. Stat. § 177.41 (the Prevailing Wage Act) in contracting for Manning to provide the mechanical portions of a new school. New-Mech, which had submitted the second lowest bid, sought a declaratory judgment that: (1) the School District, in letting bids, was required to comply with the Prevailing Wage Act; (2) the award of contracts to Manning violated the Prevailing Wage Act; and (3) the School District must rebid the mechanical contract to comply with the Prevailing Wage Act. NewMech also sought to enjoin Manning from beginning work on the school building and the School District from issuing bids and awarding contracts in violation of the Prevailing Wage Act. 1

On June 16, 1993, the district court: (1) temporarily enjoined the School District and Manning from carrying out any activities in connection with their contract for the mechanical elements of the school; and (2) required NewMech to file a $50,000 bond or other security to cover expenses arising from the temporary injunction, payable if the injunction was ultimately found to have been wrongfully issued. See Minn. R. Civ. P. 65.03(a) (temporary injunction is not to be issued without the appellant giving security to cover costs and damages incurred by party wrongfully enjoined).

Four weeks later, on July 12, 1993, the district court dismissed the complaint on the merits and awarded reasonable costs and disbursements to the School District and Manning. NewMech appealed, this court reversed in part, and the Minnesota Supreme Court, in turn, reversed this court’s decision and affirmed the district court’s judgment against NewMech. NewMech Cos. v. Independent Sch. Dist. No. 206 and Manning *24 Mechanical, Inc., 540 N.W.2d 801 (Minn.1995).

The School District and Manning then moved the district court for attorney fees incurred at the district court level and in connection with their appeals to this court and the Minnesota Supreme Court. They asked that payment be made from the injunction bond. The district court granted the motion, awarding $33,726.51 in attorney fees to the School District and $19,389 to Manning.

ISSUE

Was it error for the district court to order that all the attorney fees incurred by the School District and Manning be paid from the injunction bond posted by NewMeeh?

ANALYSIS

A reviewing court is not bound by and need not give deference to a trial court’s decision on a purely legal issue. Frost-Benco Elec. Ass’n v. Minnesota Pub. Utils. Comm’n, 358 N.W.2d 639, 642 (Minn.1984).

Attorney fees for defending a motion for k temporary injunction are recoverable from an injunction bond if the injunction is dissolved when trial on the merits determines that the party who obtained the temporary injunction was not entitled to that relief. Lamb v. Shaw, 43 Minn. 507, 508, 45 N.W. 1134, 1135 (1890). Only those expenses that are “naturally incidental” to the issuance of the injunction may be recovered from the injunction bond. Nielsen v. City of Albert Lea, 87 Minn. 285, 287, 91 N.W. 1113, 1114 (1902). According to Lamb and Nielsen, the School District and Manning are entitled to recover, from the bond, attorney fees incurred resisting the issuance of the injunction.

The School District and Manning are not entitled, however, to attorney fees and expenses related to defending the substantive claims for declaratory relief and permanent injunction. NewMeeh asked for a temporary injunction only to preserve the status quo until the legality of the Manning contract could be determined.

To recover on an injunction bond, the one seeking damages must establish that he suffered damages proximately caused by a restraining order to which the opposing party was not entitled.

Hubbard Broadcasting, Inc. v. Loescher, 291 N.W.2d 216, 219-20 (Minn.1980) (footnote omitted).

The School District and Manning rely on Pelkey v. National Sur. Co., 143 Minn. 176, 179, 173 N.W. 435, 436 (1919) (party temporarily enjoined may recover attorney fees incurred in defending substance of complaint if sole relief sought was injunction because attorney fees accrued defending substance of complaint are then “an item of damage within the terms of the bond”). We decline to rely on Pelkey for two reasons.

First, this case does not fit within Pelkey ⅛ one-form-of-relief test. Few cases do, in fact, meet the Pelkey test, for “Conjunctive relief is a remedy and not, in itself, a cause of action, and a cause of action must exist before injunctive relief may be granted.” Ryan v. Hennepin County, 224 Minn. 444, 448, 29 N.W.2d 385, 387 (1947) (quoting Shell Oil Co. v. Richter, 52 Cal.App.2d 164, 125 P.2d 930, 932 (1942)).

Second, Pelkey fails to identify the controlling principle: that the bond required for an injunction covers only expenses arising from the delay caused by the injunction if wrongfully issued. Hubbard, 291 N.W.2d at 219-20. The heart of the matter is delay. In this case, there were no actual costs from delay. The district court issued the temporary injunction on June 16 and decided the underlying issue and lifted the injunction just four weeks later, on July 12. Construction of the school building went ahead during that four-week period because the mechanical work covered by the Manning contract was not yet required. The only costs arising from the injunction were the attorney fees expended opposing it.

Manning and the School District are entitled to no more attorney fees for litigating the merits of the underlying action, which is independent of the injunction delay issue, than a party to any other civil action would be. Respondents point to no statutory or *25 contractual authority for imposing attorney fees in the action. It is well established that, in general, there must be either statutory or contractual authority before attorney fees will be awarded. State by Spannaus v. Carter, 300 Minn. 495, 497, 221 N.W.2d 106, 107 (1974).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frost-Benco Electric Ass'n v. Minnesota Public Utilities Commission
358 N.W.2d 639 (Supreme Court of Minnesota, 1984)
State Ex Rel. Spannaus v. Carter
221 N.W.2d 106 (Supreme Court of Minnesota, 1974)
Newmech Companies v. Independent School District No. 206
540 N.W.2d 801 (Supreme Court of Minnesota, 1995)
Hubbard Broadcasting, Inc. v. Loescher
291 N.W.2d 216 (Supreme Court of Minnesota, 1980)
Shell Oil Co. v. Richter
125 P.2d 930 (California Court of Appeal, 1942)
Pelkey v. National Surety Co.
173 N.W.2d 435 (Supreme Court of Minnesota, 1919)
Ryan v. Hennepin County
29 N.W.2d 385 (Supreme Court of Minnesota, 1947)
Lamb v. Shaw
45 N.W. 1134 (Supreme Court of Minnesota, 1890)
Nielsen v. City of Albert Lea
91 N.W. 1113 (Supreme Court of Minnesota, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
558 N.W.2d 22, 1997 Minn. App. LEXIS 115, 1997 WL 29517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newmech-companies-v-independent-school-district-no-206-minnctapp-1997.