NEWMAN MARCHIVE PART. v. City of Shreveport

923 So. 2d 852, 2006 La. App. LEXIS 370, 2006 WL 437554
CourtLouisiana Court of Appeal
DecidedFebruary 24, 2006
Docket40,512-CA
StatusPublished
Cited by9 cases

This text of 923 So. 2d 852 (NEWMAN MARCHIVE PART. v. City of Shreveport) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NEWMAN MARCHIVE PART. v. City of Shreveport, 923 So. 2d 852, 2006 La. App. LEXIS 370, 2006 WL 437554 (La. Ct. App. 2006).

Opinion

923 So.2d 852 (2006)

The NEWMAN MARCHIVE PARTNERSHIP, INC., Plaintiff-Appellee
v.
CITY OF SHREVEPORT, Defendant-Appellant.

No. 40,512-CA.

Court of Appeal of Louisiana, Second Circuit.

February 24, 2006.
Rehearing Denied April 5, 2006.

*854 Weems, Schimpf, Gilsoul, Haines & Carmouche by Brian D. Landry, Carey Schimpf, Kenneth P. Haines, Shreveport, for Appellant.

Mayer, Smith & Roberts by Caldwell Roberts, Wiener, Weiss & Madison by John M. Madison, Jr., M. Allyn Stroud, Shreveport, for Appellee.

Before BROWN, PEATROSS, and LOLLEY, JJ.

BROWN, C.J.

This litigation arises out of a February 18, 1994, contract that the City of Shreveport entered into with an architectural firm for renovations to Independence Stadium. The project spanned three mayoral administrations and was to be done in three phases. The first phase was designed to accommodate the needs of the Shreveport Pirates, a Canadian Football League team, and was completed by July 1994. In 1999, the new administration of Mayor Keith Hightower determined that the work of the architectural firm was completed. The architectural firm sued the City of Shreveport on an open account claiming an unpaid balance of $248,394.51 on its $1,208,097.86 fee, termination expenses of 10% of the total compensation owed ($120,809), and loss of anticipated profits on future projects of $587,000.[1] The City filed a reconventional demand against the firm and its president; however, this claim was dismissed on an exception of prescription.

A jury awarded the architectural firm $251,304.34. Although the jury verdict did not provide a specific breakdown of the award, plaintiff asserts that the jury award was only for the open account claim. Both defendant and plaintiff have appealed. For the reasons set forth below, we amend in part and, as amended, affirm.

Facts and Procedural Background

On February 18, 1994, the City of Shreveport ("the City"), through its then mayor, Hazel Beard, and the Newman Partnership, Inc. (hereinafter referred to as the "Newman Partnership") entered into a contract for renovations to the Independence Stadium in Shreveport. Although the work was to be accomplished in three phases over the course of several years, it was considered to be one project. The initial phase had a short time frame, until July 1994, in which the stadium would be readied to accommodate the Shreveport Pirates, a Canadian Football League team. Canadian football is played on a larger field than its American counterpart and changes to the existing stadium structure were necessary to widen the playing surface.

Through the administrations of Mayors Hazel Beard and Robert "Bo" Williams, 1994-1999, the Newman Partnership provided architectural services to the City on various stadium projects under the 1994 contract. Toward the end of Mayor Williams' administration, the Newman Partnership was told to proceed with a project to repaint the stadium. Work commenced on the basic phase of the painting project prior to Mayor Keith Hightower taking office.

In the early months of the first term of Mayor Hightower, the City and the Newman Partnership maintained a good working relationship. However, in the summer of 1999, the City's Chief Administrative Officer ("CAO") Ken Antee became concerned with the necessity of the architectural cost associated with the painting *855 project. The Newman Partnership's president, Mike Newman, took notes and memorialized a September 1, 1999 meeting as follows: "Mr. Antee indicated that the scope of work for the '94 project was already completed and that the current work was part of a piece by piece extension that really did not comply ... Mr. Antee restated that this was a maintenance project and just does not need an architect;" and "Mike (Newman) stated that if the City did not want us involved with the project that we would just as soon not be involved and we don't want to continue." Thus, the Newman Partnership's work under the 1994 contract ended on September 1, 1999. The City paid the Newman Partnership for phase one of the painting project but not for the final two phases or for reimbursable expenses paid by the Newman Partnership to the company which provided air monitoring services at the stadium.

The Newman Partnership filed a petition on an open account against the City on February 11, 2002, seeking an unpaid balance of $248,394.51.[2] The City answered and asserted a reconventional demand against the Newman Partnership as well as a third party claim against its president, Michael Newman. Thereafter, the Newman Partnership filed a first and second amended and supplemental petition seeking termination expenses in the amount of $50,816.90 and lost profits in the amount of $1,142,607.51, and reasserting its claim for $248,394.51. The City answered with a general denial. At trial, and without amending its petition, the Newman Partnership claimed termination expenses of $120,809 which represented 10% of the total compensation claimed.

On the first day of the trial, which began on July 12, 2004, and continued through July 16, 2004, Newman and the Newman Partnership filed an exception of prescription to the City's reconventional demand. This exception was granted and the reconventional demand was dismissed by judgment rendered on July 15, 2004.

The jury found that the Newman Partnership was due remuneration from the City "either under contract or value of services" and, "after considering the claims of both parties," determined that the City owed the Newman Partnership the amount of $251,304.34. The verdict form did not provide a specific breakdown and the jury did not itemize its award. Furthermore, as noted by both parties, the amount awarded by the jury, $251,304.34, does not match up with any combination of the specific amounts sought by the Newman Partnership.

Discussion

The City has assigned seven errors, each addressing a specific aspect of the particular amounts sought by and [apparently] awarded to the Newman Partnership, to wit, (1) fee for work on a Master Plan; (2) percentage fee on judgment in favor of All Seasons Construction which increased the contractor's claim; (3) fee for a field turf project; (4) compensation for painting project; and, (5) reimbursement at cost plus 5% for air monitoring on the painting project. In its answer, the Newman Partnership raised an assignment of error related to the sufficiency of the jury's award, i.e., that the jury erred in failing to award termination expenses. At oral argument, plaintiff's counsel announced the Newman Partnership's intention to abandon its assignment of error *856 relating to the jury's failure to award lost profits and attorney fees. In its final assignment of error, the Newman Partnership asserts that the trial court improperly denied its request for judicial interest on the judgment.

Applicable Legal Principles

A contract is an agreement by two or more parties whereby obligations are created, modified or extinguished. La. C.C. art. 1906. Legal agreements have the effect of law upon the parties, La. C.C. art. 1983. A contract is the law between the parties and courts are bound to give legal effect to all such contracts according to the true intent of the parties. La. C.C. art. 2045; Pendleton v. Shell Oil Company, 408 So.2d 1341 (La.1982); Moseley v. Mustin, 38,455 (La.App. 2d Cir.07/28/04), 880 So.2d 105. Obligations of the parties to a contract are fixed at the time the contract is entered into. Louisiana Smoked Products, Inc. v. Savoie's Sausage & Food Products, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elston v. Montgomery
70 So. 3d 824 (Louisiana Court of Appeal, 2011)
Newman Marchive Partnership v. Hightower
735 F. Supp. 2d 483 (W.D. Louisiana, 2010)
Hollenshead Oil & Gas, LLC v. Gemini Explorations, Inc.
44 So. 3d 809 (Louisiana Court of Appeal, 2010)
ABC HOME SERVICES, INC. v. Garden
986 So. 2d 254 (Louisiana Court of Appeal, 2008)
Newman Marchive Partnership, Inc. v. City of Shreveport
979 So. 2d 1262 (Supreme Court of Louisiana, 2008)
Newman v. City of Shreveport
962 So. 2d 1075 (Louisiana Court of Appeal, 2007)
NEWMAN MARCHIVE PARTNERSHIP v. Shreveport
944 So. 2d 703 (Louisiana Court of Appeal, 2006)
SCENICLAND CONST. v. St. Francis Med. Ctr.
936 So. 2d 247 (Louisiana Court of Appeal, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
923 So. 2d 852, 2006 La. App. LEXIS 370, 2006 WL 437554, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newman-marchive-part-v-city-of-shreveport-lactapp-2006.