Newell Brands, Inc. v. Kirsch Lofts, LLC

207 F. Supp. 3d 760, 2016 WL 4940210, 2016 U.S. Dist. LEXIS 125987
CourtDistrict Court, W.D. Michigan
DecidedSeptember 15, 2016
DocketCASE NO. 1:15-CV-597
StatusPublished

This text of 207 F. Supp. 3d 760 (Newell Brands, Inc. v. Kirsch Lofts, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newell Brands, Inc. v. Kirsch Lofts, LLC, 207 F. Supp. 3d 760, 2016 WL 4940210, 2016 U.S. Dist. LEXIS 125987 (W.D. Mich. 2016).

Opinion

MEMORANDUM OPINION AND ORDER

ROBERT J. JONKER, UNITED STATES DISTRICT JUDGE

Newell Brands, Inc. owns contaminated property near Sturgis, Michigan, and is obligated to remediate it and neighboring parcels under a consent decree. Newell filed this action to obtain access to Kirsch Lofts’ property to conduct a portion of the remediation. The parties reached agree[763]*763ment on the access itself, but Kirsch’s counterclaim remains in dispute. The counterclaim asserts that Newell is liable under Mich. Comp. Laws 324.20135a(1)(a) (“the Access Statute”) for damages relating to this Court’s grant of access to Newell to conduct remediation efforts on property-owned by Kirsch. Newell seeks summary judgment dismissing Kirsch’s counterclaim or limiting any recovery to $72,964, New-ell’s estimated value of the access damages (ECF No. 88). Kirsch opposes summary judgment and claims its damages are $9.75 million, based principally on delay of commercial and residential development Kirsch had planned for its property (ECF No. 100). The Court heard oral argument on this motion on September 8, 2016.1

BACKGROUND

Kirsch Lofts, LLC, is a Michigan single-member limited liability company that owns a former manufacturing facility (the Facility”) on a parcel of real estate located at 308 N. Prospect Street, in Sturgis, Michigan (the “Property”). It bought the Property in 2009 from a third party, who had bought the property from Newell. Scott T. Bosgraaf (“Bosgraaf’) runs Kirsch. In 1997, Newell acquired a large industrial parcel, including the parcel later sold to Kirsch, from Cooper Industries. Newell’s acquisition included assumption of responsibility for remediation activities under a consent decree that requires TCE cleanup to a level not greater than 100 parts per million.

I. Kirsch’s Purchase and Initial Development of the Property

Kirsch Lofts purchased its parcel on July 10, 2009, for $57,544.25 (EFC No. 88-13, PageID.1920). Kirsch’s proposed development plan included three phases: (1) residential, (2) commercial, and (3) more residential. Id. at PageID.1936. This plan included building thirty to fifty condominiums on the Property and selling them for an average of $125,000. Id. at Pa-geID.1943. Kirsch claims that, at the time of purchase, remediation activities being conducted on .the Property were consistent with, and could coexist with, its redevelopment plans (ECF No. 100, PageID.2842). According to Kirsch, it did not anticipate remediation activities beyond the groundwater treatment that existed at the time it purchased the Property. Id. Moreover, Kirsch claims that some contamination at manageable levels was actually necessary for its development plans, which depended on “Brownfield” and related tax credits.2

To ' finance its development efforts, Kirsch partnered with the City of Sturgis and obtained the following tax credits and incentives: (1) MDEQ Loan and Grant for $2 million3; (2) Brownfield Michigan Business Tax Credit for $1.6 million (ECF No. 41-3); (3) Brownfield TIF Reimbursement for $3.2 million (ECF No. 41-4, Pa-geID.412); and (4) New Markets Tax Credit Allocation for $4.2 million (ECF No. 41-5). Kirsch says that each of these [764]*764incentives was time sensitive and Newell does not contest the general point, though its experts dispute some of the details of Kirseh’s claims. The Brownfield MBT Tax Credit required Kirsch to complete all three phases of the rehabilitation project by October 10, 2018 (ECF No. 41-3). The NMTC required that Kirsch close on the transaction and begin construction by July 31, 2010 (ECF No. 41-5). The Brownfield TIF reimbursed costs for a period limited to thirty years (ECF No. 41-4).

High levels of TCE were discovered in the Property’s soil in late 2009, and the MDEQ, in a letter to Kirsch dated January 27, 2010, requested that it suspend work on its development (ECF No. 41-7). At the time, Kirsch had been following its approved work plan, the next step of which required the installation of a vapor barrier and the pouring of a new concrete floor in the buildings (ECF No. 41-8). Further, on March 22, 2010, the MDEQ sent another letter to Kirsch, which premised final approval for moving forward with the next step of the construction plan on Newell’s conducting the soil TCE/PCE investigation and the DNRE’s determination of the appropriate remedial actions (ECF No. 41-10, PageID.508). In short, Kirsch says that it was unable to move forward with its development plans.

II. Newell’s Investigation and Remediation

A few months later, as part of the soil investigation procedure, Newell began drilling operations on the Property. These included twenty-eight borings of sixty feet, one boring at thirty-two feet, five borings at twelve feet, and nine borings at two feet. Some of these borings were located in existing buildings. Even though this activity amounted to actual, physical intrusion of its property, Kirsch is making no claim for damages associated with this activity (ECF No. 88, PageID.1714; ECF No. 88-2, PageID.1736). In any event, the intrusion occurred years before any court-ordered access and would not appear to trigger a statutory right to recovery.

On September 9, 2010, Dr. Meiri, Newell’s environmental consultant, provided Newell with several different options for remediating the contaminated soil: (1) In Situ Chemical Oxidation (“ISCO”); (2) In Situ Thermal Treatment (“Thermal”); and (3) Soil Vapor Extraction (“SVE”) (ECF No. 41-11, PageID.533). Each method had a different cost and different estimated time of use: (1) Thermal—one year; (2) ISCO—a few months; (3) SVE—six years (ECF No. 41-14, PageID.559-562). In general, the shorter remediation options cost more to implement.4 Kirsch claims that Newell selected the SVE method because it was the most cost-effective, saving Newell approximately $16-19 million (ECF No. 100, PageID.2846). It was also the method that took the longest to complete. The SVE method consisted of excavating and disposing of the top two feet of soil and installing and operating a SVE well system on the Property.

[765]*765By September 2010, Kirsch stopped its construction on the Property (ECF No. 8, PageID.126). At that time, the construction efforts consisted of a 103,387 square foot building on the Property without interior finish, windows, heating/eooling, plumbing fixtures or electrical fixtures (ECF No. 88-13, PageID.1931). In January 2011, Kirsch notified Newell that it would no longer be allowed new access to the Property, even if necessary for remediation.5 The parties continued negotiating regarding access.

In early 2011, Newell presented a project schedule to the MDEQ (ECF No. 41-lb). The first step of that schedule involved the performance of a leach test on the soil of the Kirsch parcel to determine the applicable level of cleanup criteria (ECF No. 41-15, PageID.584). Further, Newell’s project schedule states that excavation of the top two feet of soil and installation of the SVE system were set to begin on March 2012 and completed by July 23, 2012 (ECF No. 41-15, PageID.416). Later on, however, Newell submitted a revised project schedule. Under this schedule, leach testing is estimated to begin on April 29, 2013, and be completed on June 10, 2015 (ECF No. 41-16, PageID.587). Further, remediation is no longer set to be conducted concurrently with other tasks, but set to begin in May 2016. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Connecticut National Bank v. Germain
503 U.S. 249 (Supreme Court, 1992)
Spectrum Health Hospitals v. Farm Bureau Mutual Ins Co of Michigan
492 Mich. 503 (Michigan Supreme Court, 2012)
State Farm Fire & Casualty Co. v. Old Republic Insurance
644 N.W.2d 715 (Michigan Supreme Court, 2002)
In Re Powerhouse Licensing, LLC
441 F.3d 467 (Sixth Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
207 F. Supp. 3d 760, 2016 WL 4940210, 2016 U.S. Dist. LEXIS 125987, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newell-brands-inc-v-kirsch-lofts-llc-miwd-2016.