New York State National Bank v. Whitehall Water Power Co.

161 A.D. 304, 146 N.Y.S. 769, 1914 N.Y. App. Div. LEXIS 5398
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 13, 1914
StatusPublished
Cited by2 cases

This text of 161 A.D. 304 (New York State National Bank v. Whitehall Water Power Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New York State National Bank v. Whitehall Water Power Co., 161 A.D. 304, 146 N.Y.S. 769, 1914 N.Y. App. Div. LEXIS 5398 (N.Y. Ct. App. 1914).

Opinion

Kellogg, J.:

The plaintiff’s assignor constructed an addition to the defendant’s mill and there is unpaid on the contract price $11,618.96, for which, and for certain alleged extra work, the plaintiff seeks recovery. By the contract, dated May 3, 1905, the work was to be completed September 1, 1905, within three months and twenty-eight days. It was in fact completed July 1, 1906 — thirteen months and twenty-eight days after the date of the contract and ten months after the agreed time. The contract provided $50 per day as liquidated damages to the defendant for each day’s delay in the completion of the work, and that the delays should be apportioned. The defendant, by its coun[305]*305terclaim, seeks to recover such liquidated damages for three hundred and three days. The judgment appealed from determines that the deepening of the wheelpit three and one-half feet, which was provided for by a supplemental agreement, extended the contract so that the time did not begin to run until January 1, 1906, thus driving the work into cold weather, which made great delay in laying the brick and placing the floor beams, and such work, which should have been completed in one month in seasonable weather, required three months, thus extending the contract time two months more, with the result that forty-seven days of the delay were chargeable to the contractor, the balance to the defendant.

This case was before us in 140 Appellate Division, 740, and it is unnecessary to repeat the facts there stated. When the contract was made it was understood that the wheelpit, which lay at the very foundation of the work, was to he lowered one foot or more below the depth specified in the contract, for which the contractor was to receive two dollars and fifty cents per cubic foot, and that the contractor was to be notified of the depth required as soon as a determination was made. We held that until the contractor was so notified the original contract practically remained in suspense and that the time intervening was not a part of the contract time. This was not upon the theory that the owner or the architect had delayed the work, but that the parties had in substance agreed that the work need not be entered upon until the nature of this foundation work was agreed upon. We also held that if this extra work necessarily required extra time for its completion, with reference to the work itself or the extra cofferdam made necessary for it, such extra time was to be added to the contract time. This did not mean that the time which the contractor might spend upon the work, or in experimenting upon the cofferdam, was to be added to the contract time, but that the situation as it actually existed was to. he considered, and if engineers competent for such work, who had full knowledge of the condition of the bed of the lake and the other conditions, with adequate machinery and appliances, proper supervision and working to capacity would be engaged a certain time in the necessary [306]*306performance of such work, such time should be added to the contract time. ■ The law implies that where, by a supplemental agreement, additional work, which lies at the very foundation of the contract work, is agreed upon, the term of the original contract is extended by the time which is necessary for the performance of such extra work. It is evident that the wheelpit could not be lowered three feet and a half without taking some time. It is also apparent that in agreeing to deliver the building in three months and twenty-eight days the contractor had undertaken to do a great deal of work in a very short time. It must have been within the understanding that the deepening of the wheelpit would necessarily cause some extension of the contract time. The parties not having agreed upon the extended time, it follows that the extension was for such time as the extra work at the place where it is to be performed reasonably requires under favorable conditions.

The important questions for consideration are when the contractor was notified that the wheelpit was to be lowered three and one-half feet, and how much time was added to the contract on that account. It was assumed upon the former appeal that such notice was given July seventh when the blue prints for the work were finished. Upon a careful consideration of the present record it is clear that the contractor had due notice on June eighth and should then have entered upon the work. According to the plaintiff’s theory the contractor had substantially built the cofferdam in which the wheelpit mentioned in the original contract was to be placed; that such work was done in reliance upon the original contract and without expectation that the wheelpit was to be deepened and that the change of plan made necessary a new cofferdam. It is evident that the contractor cannot have an extension of the contract upon the theory that it remained in suspense'awaiting the determination as to the deepened wheelpit and at the same time be credited with the construction of the first cofferdam which he claims was built upon the theory that there was to be no deepening of the wheelpit. The facts do not justify the claim that the first cofferdam was constructed upon the theory that there was to be no change in the wheelpit. Upon May twenty-fourth, twenty-one days after the date of the contract, the architect wrote [307]*307the contractor that nothing was being done with reference to the cofferdam, and he urged him to begin work upon it, saying, “as the change which is contemplated in this work will not affect the size of cofferdam required or the extent to which it will be carried.” The contractor replied upon the twenty-fifth of May that he would take immediate steps in progressing the work. He began the work June first. He gave the order for the iron June first. June third some of the order was can- ' celed “ to the extent of the wheelpit and the top of the turbine pit iron. Daggett [the contractor’s superintendent] informed us that there would be a change in that iron.” The work upon the cofferdam was done by the carpenters and masons and the ordinary workmen employed upon the job. No man familiar with such work laid it out or determined as to its condition or supervised it. After it was built the contractor was unable to free it from water. In the contract it was specified that the contractor should satisfy himself as to the nature and location of the work bid for and “of the quality of the materials required and all other matters which can in any way influence their contract, and no misunderstanding upon these matters will in any way relieve the contractor from any risks or from filling the terms of the contract.” On June fifth the contractor wrote the architect that he had not received information “ as to the depth of the wheelpit and the arrangement of the beams in the wheelpit chamber so it is impossible to order these beams. ” The architect replied the next day that he would be at Whitehall Thursday morning and if the contractor and the superintendent would be there the matter of the wheelpit would be settled; that the style of wheel to be used had delayed the determination, but that matter would be settled Thursday. The evidence shows that on June eighth, at Whitehall, the depth of the wheelpit was determined and the contractor’s superintendent duly notified. Clausson, the engineer of the firm which was to furnish the iron, swears that upon the ninth Gilroy, the architect’s representative, came to Albany “ and told us to order the beams to the wheelpit according to certain sizes and dimensions that we worked out. * * * They were ordered under his instructions June twelfth.” There is no substantial denial of the fact that on June eighth the contractor was noti

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Janowitz Bros. Venture v. 25-30 120th Street Queens Corp.
75 A.D.2d 203 (Appellate Division of the Supreme Court of New York, 1980)
Quinn-Meissner, Inc. v. State
268 A.D. 936 (Appellate Division of the Supreme Court of New York, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
161 A.D. 304, 146 N.Y.S. 769, 1914 N.Y. App. Div. LEXIS 5398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-york-state-national-bank-v-whitehall-water-power-co-nyappdiv-1914.