New York & New England Railroad v. City of Providence

19 A. 759, 16 R.I. 746, 1890 R.I. LEXIS 20
Supreme Court of Rhode Island·Decided March 1, 1890·Published

Opinion

Stiness, J.

The General Assembly, by acts passed in 1845 and 1848, gave authority to the city council of Providence to grant, upon such terms as they might deem for the public, good, to any railroad company having a terminus at said city, the right and privilege of establishing a depot upon any part of the land covered by the public waters in said city above Weybosset Bridge; of constructing such causeways, embankments, etc., as might be necessary to accommodate buildings, and of laying rails, turnouts, and spur tracks over the public lands and waters, subject to the approval of the city council.

February 9,1852, upon the petition of the Hartford, Providence, and Fishkill Railroad Company, to which company the complainant is successor, the city council of Providence passed the resolutions appended as Exhibit A, to the bill. These resolutions, as amended and reenacted, March 29,1852, Exhibit B, are the foundation of the complainant’s claim of title to the land in question; tbe claim being that they constitute a grant of the tide-flowed land therein described, for railroad purposes, upon condition that it should be filled by the company.

It is to be observed that these resolutions do not purport to *747 make such a grant. On the contrary, the city council simply consented to the location and construction of the railroad in the city, upon condition that the company would fill a certain defined area of the Cove lands within a certain limited time. The reclamation of the land was not a privilege granted, but a condition exacted, upon which the consent of the city to the location of the road was made to depend. A provision followed, the 6th, which authorized the company to construct depots, engine houses, and other buildings for railroad purposes only, on land so to be filled, south of a proposed street. This provision is the only one which gives the railroad company any right whatever upon this land outside of its location. It was also provided that the resolutions should be null and void if the filling was not completed before January 1, 1857. The filling was not completed at that time. The question now is, whether the complainant, as successor to the Hartford, Providence, and Fishkill Railroad Company, has an equitable right to land which the latter company failed to fill, but which was subsequently filled by the city ; no question being made by the respondents as to the complainant’s title to the land actually filled prior to January 1, 1857. It is not very clear from the testimony how far this filling extended, but our conclusion is, that it was substantially as shown on respondent’s Exhibits V. and VI., since these plats were made nearest the time of the work, and before it was possible to confuse the line with that of work done by the city afterwards. The opinions of witnesses, after so long a time and without landmarks to guide them, that the line of filling was about as shown on Exhibit II., is too indefinite to satisfy us that it is the true line. The line as claimed by the respondent is corroborated by the building of the fence substantially in agreement with it, i. e. along the straight bank and stopping short at Gaspee Street; and also by the occupation of the land on the north side for many years. The adoption of this line in .this case leaves a small piece of land north of that occupied by the complainant, which, consequently, is not embraced in this decision.

As we have seen from the resolutions, under which the complainants claim, no title was granted, but only an easement or permission to occupy the land, if it should be filled within the time limited. It is not, then, a question of forfeiture of title for breach *748 of condition; for, in so far as tbe filling is a condition subsequent, it applies, not to a grant of land, but to consent to tbe location and construction of the road. Under the charter of the Providence and Plainfield Railroad Company, granted June, 1846, the railroad company had no authority to lay out or construct its road in the city of Providence, except with the consent of the city council and upon such terms as the council might impose. The city council, in dealing with its successor, the Hartford, Providence, and Fishkill Railroad Company, acted under this provision of the charter, instead of making a grant under authority of the statute, as was done with the Providence and Worcester Company, where such authority was expressly recited. The parties may have supposed that the resolutions amounted to a grant, but in terms they only attached conditions to the layout oE the road in Providence. We cannot enforce a grant where none was made, nor assume an act to have been done under one authority which was clearly done under another. In respect to the layout, the conditions were conditions subsequent; but in respect to use of the land the condition of filling was precedent, since the right to occupy was made to depend upon the completion of the filling within the time named, and no such right was to be acquired unless and until that should be done. It is therefore a sufficient and conclusive answer to the complainant’s claim of right to land not so filled that the condition was not performed. But the complainant sets up the action of the city by way of equitable excuse for non-performance of the condition. In March, 1858, the contract in regard to the retaining wall was modified, so that the railroad company should be released from building it, by paying to the city its estimated cost, which was to be expended by the city in building a wall along the channel of the river. The city received the money, but did not build the wall until long after 1857. The complainant claims that this neglect of the city made it impossible, or at least impracticable, to complete the filling ; because, without the wall, it would have been washed away. Some testimony was put in on this point. We think opinions to the effect that the work could not be done are overborne by the facts that the larger part of the stipulated filling was done before the wall was built, without washing away; and that, in the winter of 1857-1858, the balance of the land was *749 filled by tbe city with equally good result. Tbe land filled by the company was a long way from tbe channel of the river and washed only by tbe tides. It seems to have stood as any bank, at the bead of tide waters, away from tbe current, might be expected to stand, and it sustained the tracks and buildings put upon it. We see no reason why the additional filling would not have stood as well, and do not think that the company was prevented from performing its agreement by the failure of the city to build the wall.

Free access — add to your briefcase to read the full text and ask questions with AI

New York & New England Railroad v. City of Providence, 19 A. 759, 16 R.I. 746, 1890 R.I. LEXIS 20 (R.I. 1890).

19 A. 759 (New York & New England Railroad v. City of Providence) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.