New Wood Constr. v. North Branford Hous. Auth., No. 61361 (Dec. 31, 1992)

1992 Conn. Super. Ct. 11655
CourtConnecticut Superior Court
DecidedDecember 31, 1992
DocketNo. 61361
StatusUnpublished

This text of 1992 Conn. Super. Ct. 11655 (New Wood Constr. v. North Branford Hous. Auth., No. 61361 (Dec. 31, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Wood Constr. v. North Branford Hous. Auth., No. 61361 (Dec. 31, 1992), 1992 Conn. Super. Ct. 11655 (Colo. Ct. App. 1992).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This is an action for breach of a building contract.

By a contract made on August 25, 1980 the plaintiff agreed to construct 30 dwelling units for the defendant on the project to be numbered E-121 which was Rental Homes for Elderly citizens in North Branford. The contract required the work to start on September 1, 1980 and to be completed, except for landscaping, in 365 consecutive calendar days.

The work under the contract progressed slowly because there arose many controversies, with much bickering and arguments about the work, and how it was to be done. It would serve little purpose to detail these problem areas. The fact is that the work went forward as shown by the "Periodical Estimates For Partial Payment" under the contract. These were requisition made by the plaintiff asking for payments for work it had done up to the date of the requisition. These requisitions were reviewed by all concerned and then signed by each to indicate approval.

However, before the project was completed by a letter dated CT Page 11656 July 24, 1981 and received by the plaintiff on July 27, 1981 the plaintiff was ordered to terminate its work on the project immediately. It did so.

Nine months later, on April 2, 1982, the plaintiff filed this action in the Judicial District of Waterbury. Then on March 19, 1987, five years later, it was referred to the undersigned, who had agreed to hear it. The first day of the hearings was March 14, 1987. Four (4) years and two (2) months later, after 73 days of hearings, the evidence was completed. That day was May 14, 1992. Fifteen witnesses testified for the plaintiff, nine for the defendant. The plaintiff's brief is dated July 15, 1992, the defendant's is dated November 4, 1992 and the plaintiff's reply brief is dated December 10, 1992.

I.
Liability

The termination letter was addressed to the plaintiff, was signed by William Manzi, Chairman of the defendant Housing Authority. Copies were sent to Connecticut state Housing and to St. Paul Fire and Marine Insurance Co.

There are four reasons given for the termination. These are set out in the first paragraph of the letter of July 24, 1981. They read as follows:

"Pursuant to Sections 13 and 15 of the Contract General Conditions for the construction of North Branford Housing for the Elderly — Project E-121, this is to notify you that you are to terminate your work on said project immediately. This notice is being given by reason of your persistent disregard of the instructions of the architect and/or the Housing Authority; for failure to observe or perform the provisions of the Contract documents; for substantial violations of the provisions of the Contract documents; for failure to prosecute the work with such diligence as well as cause its completion within the time specified in the contract."

The first three reasons for the termination are governed by Paragraph 6(A) of the General Conditions of the contract between the parties. This reads in part: CT Page 11657

"All material and workmanship (if not otherwise designated by the Specifications) shall be subject to inspection, examination and test by the Local Authority, the Architect, and the Department of Community Affairs, at any and all times during manufacture or construction . . . The Local Authority, on its own initiative, or at the request of the Department of Community Affairs, shall have the right to reject defective material and workmanship, or require its correction. Rejected workmanship shall be satisfactorily corrected. Rejected material shall be promptly segregated, and removed from the premises and satisfactorily replaced with proper material, without cost to the Local Authority. If the Contractor fails to proceed at once with the replacement of defective material or workmanship, the Local Authority may by contract, or otherwise, have the defects remedied, or rejected materials removed from the site. The cost of same will be charged against any monies which may be due the Contractor without prejudice to any other rights or remedies of the Local Authority in the premises."

Under the provisions of Paragraph 13(A) of the General Conditions the plaintiff was required to follow and carry out the instructions of the architect and/or the Housing Authority, to observe and perform the provisions of the Contract Documents and not to violate in any substantial way the provisions of the Contract Documents.

It is unnecessary to discuss the details of these claimed, problems because the documents entitled "Periodical Estimate For Partial Payment" show that the plaintiff must have done the work so; required by the above numbered paragraphs set out in the Periodical estimates #1 through #5. The last one relevant to this inquiry is #5 concerning the period from January 1, 1981 to January 31, 1981.

The Clerk of the Works daily reports states that the job was shut down by the plaintiff at 2:30 P.M. on January 30, 1981 and work resumed on June 8, 1981.

Periodical Estimate #5 stated that the Total Value of Work Performed to Date was $224,154 and that the work performed during the period covered by Periodical Estimate #5 was $35,170.20. This CT Page 11658 document was signed by all concerned.

If the plaintiff has failed to follow and carry out the instructions of the architect and/or the Housing Authority, or had failed to observe and perform the provisions of the contract documents or had violated in any substantial way the provisions of the contract demands, such work would not have been paid for in Periodical Estimate #5.

After the plaintiff resumed work on the project in June 8, 1981, the architect and a representative of the defendant and of the state went over the project and prepared a check list of items which had to be corrected. It was a very thorough check, as one of the items to be corrected was the removal of a bird's nest from the attic space of one of the buildings.

Obviously, had the plaintiff disregarded the instructions of the architect concerning the work, or had failed to observe or perform the provisions of the contract documents or had violated in any substantial way the provisions of the contract documents, any work involved in these matters would not have been included in the work to be paid for and would have been on the check list of work to be done.

This conclusion follows from an examination of the various certificates to be signed in the Periodical Estimates Form.

First, the Treasurer of the plaintiff certifies that all just and lawful bills against the plaintiff and its subcontractors for labor, material and equipment employed in the performance of the contract have been paid in full in accordance with the terms and conditions of the contract.

Second, the Architect certifies that he has checked and verified this Periodical Estimate for the period stated and that to the best of his knowledge and belief it is a true statement of the value of the work performed and/or materials included in the estimate has been inspected by him or by his duly authorized assistants and that such work has been performed and supplied in full accordance with the plans and specifications of the construction contract and/or duly authorized deviations, substitutes, alternatives or additions all of which have been duly approved by the authorized agent of the Housing Authority and therefore he approves the balance due this payment. CT Page 11659

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wooley v. Williams
136 A. 583 (Supreme Court of Connecticut, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 11655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-wood-constr-v-north-branford-hous-auth-no-61361-dec-31-1992-connsuperct-1992.