New Welton Homes v. Eckman

786 N.E.2d 1172, 2003 Ind. App. LEXIS 680, 2003 WL 1937202
CourtIndiana Court of Appeals
DecidedApril 24, 2003
Docket27A02-0208-CV-694
StatusPublished
Cited by4 cases

This text of 786 N.E.2d 1172 (New Welton Homes v. Eckman) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Welton Homes v. Eckman, 786 N.E.2d 1172, 2003 Ind. App. LEXIS 680, 2003 WL 1937202 (Ind. Ct. App. 2003).

Opinion

OPINION

RATLIFF, Senior Judge.

STATEMENT OF THE CASE

Defendant-Appellant - New - Welton Homes ("Welton") brings this interlocutory appeal from the trial court's denial of Weliton's motion for summary judgment in this breach of contract action brought by Plaintiffs-Appellees Lance and Karen Eckman ("the Eekmans").

We affirm.

ISSUE

Welton presents for our review the following issue that we restate as: whether a contractual limitation of action is tolled by the discovery rule in a breach of contract action.

FACTS AND PROCEDURAL HISTORY

The Eckmans own property located at 4675 South 600 East in Wabash County, Indiana. On December 29, 1998, the Eck-mans entered into an agreement with Welton to purchase a 1999 Commodore Modular Home. Welton was a retailer of manufactured homes in North Central Indiana. Part of the agreement entered into between the Eckmans and Welton involved the installation of a foundation for the placement of the modular home, installation of a perimeter drain, and backfilling the foundation area and perimeter drain with dirt and grading and seeding the area adjacent to the foundation and drain. The project was completed on June 1, 1999.

Throughout the remainder of 1999 and through April 2001, the area in Wabash County where the Eckmans reside encountered drought conditions with no sustained periods of rainfall or other precipitation. However, in the latter part of May of 2001, Wabash County experienced substantial and continuing rainfall lasting into early June of 2001. The Eckmans discovered water standing around the perimeter of the modular home and discovered that no water was being discharged from the drainage system installed around the foundation. They investigated further looking underneath the modular home and discovered a substantial amount of moisture had accumulated inside the foundation area and around the structural support system underneath the modular home. After the period of rainfall ended, the Eckmans noticed evidence of settling and cracking in *1174 side the modular home. The Eckmans investigated the crawlspace area under the home and discovered that the support systems had shifted and settled.

On December 28, 2001, the Eckmans filed a complaint against Welton for breach of contract. Their amended complaint was filed on January 8, 2002. Welton filed its answer on February 1, 2002. Welton filed its motion for summary judgment on April 15, 2002. A hearing on the motion was conducted on June 5, 2002. On June 21, 2002, the trial court entered its order denying Welton's motion for summary judgment.

At issue was the contractual limitation of action contained in the agreement between the Eckmans and Welton. The limitation states as follows:

15. ONE-YEAR PERIOD OF LIMITATION. I understand and agree that-if either of us should breach this contract-the other of us shall have only one year, after the occurrence of the breach, in which to commence an action for breach of this contract.

Appellant's App., p. 55.

Welton argued that the Eckmans were barred by the contractual limitation from bringing their cause of action because their complaint was brought more than one year after completion of the project. More specifically, Welton argued that the breach occurred upon the completion of the project, June 1, 1999, and that the complaint, which was filed on December 28, 2001, was untimely. The Eekmans argued that the contractual limitation period was tolled until such time as they could have discovered the breach of contract. They argued that because of the drought conditions encountered immediately after completion of the project, they could not have discovered the breach of contract until a period of substantial rainfall. They argued that summary judgment was not appropriate because there existed a material question of fact regarding when they knew or could have known of the breach of contract.

The trial court agreed with the Eckmans and applied the discovery rule to this cause of action. The trial court found that summary judgment was inappropriate because of the existence of the genuine issue of material fact regarding when the Eck-mans knew or should have known of the breach. This appeal ensued.

DISCUSSION AND DECISION

STANDARD OF REVIEW

Our standard of review for the denial of a motion for summary judgment is the same as that of the trial court. See Diversified Financial Systems, Inc. v. Miner, 7183 N.E.2d 293, 297 (Ind.Ct.App.1999). Summary judgment is appropriate only when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Id.; Ind. Trial Rule 56(C). This court may consider only matters that were designated at the summary judgment stage of the proceedings. See Diversified, 713 N.E.2d at 297. We give careful serutiny to the pleadings and designated materials, construing them in a light most favorable to the non-movant. Id. Finally, a trial court's decision on a motion for summary judgment enters the process of appellate review clothed with a presumption of validity. Id.

The Eckmans and Welton agree that the contract contained a one-year period of limitations for bringing an action for breach of contract. They disagree, however, regarding when the one-year period of limitations began to run.

A contractual limitation of actions provision that shortens the time within which plaintiffs must bring suit is valid *1175 and enforceable in Indiana if the parties mutually consented and agreed to the provision. Meridian Mutual Ins. Co. v. Caveletto, 553 N.E.2d 1269, 1270 (Ind.Ct.App.1990). Further, it is well-established in Indiana that, while not favored, contractual limitations shortening the time to com-menee suit are valid, at least so long as a reasonable time is afforded. See Summers v. Auto-Owners Ins. Co., 719 N.E.2d 412, 414 (Ind.Ct.App.1999). The purpose of such provisions concerns not a specific date following the loss but unreasonable delay in proceeding to enforce or pursue the claim. Id.

Therefore, while the parties agree that the contract contains the one-year limitation of action, the question before us is whether the trial court correctly applied the discovery rule to this breach of contract action in ruling on the motion for summary judgment.

The discovery rule is applicable to all tort actions. See Wehling v. Citizens Nat. Bank, 586 N.E.2d 840, 843 (Ind.1992). Therefore, in Indiana, a tort action accrues and the applicable statutes of limitations begin to run when the injured party knows or, in the exercise of ordinary diligence, could have known, that he or she had sustained an injury. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Welton Homes v. Eckman
830 N.E.2d 32 (Indiana Supreme Court, 2005)
Meisenhelder v. Zipp Express, Inc.
788 N.E.2d 924 (Indiana Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
786 N.E.2d 1172, 2003 Ind. App. LEXIS 680, 2003 WL 1937202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-welton-homes-v-eckman-indctapp-2003.