New Orleans Glass Company v. Roy Anderson Corporat

632 F. App'x 166
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 1, 2015
Docket15-60083
StatusUnpublished
Cited by2 cases

This text of 632 F. App'x 166 (New Orleans Glass Company v. Roy Anderson Corporat) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Orleans Glass Company v. Roy Anderson Corporat, 632 F. App'x 166 (5th Cir. 2015).

Opinion

W. EUGENE DAVIS, Circuit Judge: *

Defendant-Appellant Roy Anderson Corp. (“RAC”) appeals from the district court’s denial of its motion to compel arbitration. Because we conclude that the subcontract at issue requires arbitration under these circumstances, we reverse and remand.

I. Background

This dispute arises out of the construction of the Sea Breeze Condominiums and *167 Resort (“Project”) in Biloxi, Mississippi. The Project was owned and developed by Sea Breeze I, LLC (“Developer”), and owners of individual units belonged to the Sea Breeze Condominiums and Resort Owners’ Association (“Owners’ Association”). The Developer engaged RAC as its general contractor. RAC in turn engaged a number of subcontractors, including Plaintiff-Appellee New Orleans Glass Co. (“NOG”). RAC and NOG executed a subcontract dated January 27, 2005 (“RAC-NOG Subcontract”), which is central to this dispute.

Following completion of work in 2007, the Developer and Owners’ Association were unhappy with the quality of the construction and/or design of the Project, and both initiated arbitration proceedings (later consolidated) against RAC and the architect. The Developer’s demand sought “damages, as well as undetermined amounts for repairs to the pool, windows, curtain walls, and transfer slab,” while the Owners’ Association demand asserted similar claims, referring to issues with the “pool and pool deck area, windows, curtain walls, the slab and foundation and various other parts of the building____”

Based, on its investigation, RAC determined that the arbitration demands concerned certain of its subcontractors’ work, and it filed a Third-Party Demand for Arbitration on March 7, 2014, against many of its subcontractors, including NOG, followed by a Second Amended Third-Party Demand for Arbitration on April 18, 2014. In its arbitration demand, RAC invoked the broad defense and indemnity clause of Section 19.1 of each of its subcontracts, which provides:

To the fullest extent permitted by law, the Subcontractor covenants to defend, indemnify, save harmless, protect, and exonerate both the Contractor (its agents, employees, representatives, and sureties) and the Owner, separately and severally, from any and all liability, claim, losses, suits, actions, demands, ar-bitrations, administrative proceedings, awards, judgments, expenses, attorneys’ fees, and costs pertaining to economic loss or damages, labor disputes, safety requirements, performance or nonperformance of obligations, certifications, property rights of third parties, personal injury, bodily injury, sickness, disease, death, or damage to or destruction of property (including loss of use thereof) which are caused in whole or in part, which arise from or occur in connection with work undertaken or to be performed by the.Subcontractor, its subcontractors, or the agents or employees of any of them or which arise from or occur in connection with any other act or omission relating to the Subcontractor, its subcontractors, or the agents or employees of any of them, or. to this Subcontract or to the Subcontract Work. The foregoing covenants and indemnity obligations shall apply to the fullest extent permitted by law. The Subcontractor’s indemnity obligation and liability to the Contractor shall extend to the maximum extent allowed by applicable law.

In addition, RAC asserted that in all of its subcontracts, each subcontractor agreed to arbitrate disputes between it and RAC. In a footnote, it explained that the RAC-NOG Subcontract “contains different dispute resolution language, but nevertheless binds [NOG] to appear in this arbitration proceeding.” Specifically, RAC invoked Section 27.3 of the RAC-NOG Subcontract, which provides:

If the Contractor has a claim or dispute involving the same general subject matter, either in whole or in part, with any third party if elected by the Contractor, the Subcontractor shall assert its claims and defenses in and shall be bound by *168 the same forum and in the same proceeding which has jurisdiction over the claims or disputes between the Contractor and such third party.

Instead of joining the consolidated arbitration proceeding, NOG filed a Complaint for Declaratory Relief in the United States District Court for the Southern District of Mississippi. In its complaint, it summarized the same facts set out above but disputed that Section 27.3 applies here, claiming that Section 27.3 “applies in circumstances where RAC and NOG each have similar claims against third parties, and it does not apply to claims between RAC and NOG.” In NOG’s reading, Section 27.3 is irrelevant to claims solely between RAC and NOG, which it asserts are governed by Sections 27.4 and 27.5 (discussed below), which require RAC and NOG to litigate claims between them unless they specifically agree to arbitrate them. NOG prayed for a declaratory judgment declaring that:

A. RAC and NOG did not agree to arbitrate their claims or disputes arising under the RAC-NOG Subcontract;
B. Any claims or disputes arising under the RAC-NOG Subcontract must be litigated in a court of competent jurisdiction located either in Harrison County, Mississippi, if a state court action, or in the Southern District of Mississippi, if a federal court action;
C. This Court is a court of competent jurisdiction for the purpose of litigating claims or disputes arising under the RAC-NOG Subcontract, including RAC’s claim for contractual indemnity;

Thus, the primary purpose of NOG’s declaratory judgment is to avoid arbitration. NOG has also prayed for a declaratory judgment declaring that RAC’s contractual indemnity claim is premature because RAC asserted it prior to any judgment against RAC. This appeal will determine which forum may address that question.

Soon after NOG filed its declaratory judgment action, RAC filed a Motion to Compel Arbitration and to Dismiss in the district court, re-asserting its argument that under Section 27.3 of the RAC-NOG Subcontract, NOG is required to arbitrate its dispute with NAC in the existing arbitration.

The district court denied RAC’s motion. In a Memorandum Opinion and Order, the district court rejected RAC’s interpretation of the RAC-NOG Subcontract and adopted NOG’s. Specifically, the district court interpreted Section 27.3 to apply “when the subcontractor has a claim or dispute with a third party,” while “Section 27.4 controls when the subcontractor has a claim or dispute with the contractor.” 1 Because it found no contractual basis for requiring NOG to arbitrate its dispute with RAC, it denied RAC’s motion. It also stayed the proceedings in the district court pending the outcome of RAC’s ongoing consolidated arbitration. RAC appealed.

II. Standard of Review and Applicable Law

“This Court reviews de novo the grant or denial of a motion to compel arbitration.” 2 As the district court noted, this *169 ease falls under the Federal Arbitration Act (“FAA”), 9 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daniels v. Seahorse Underwriters
S.D. Mississippi, 2024
Noel v. Paul
N.D. Texas, 2022

Cite This Page — Counsel Stack

Bluebook (online)
632 F. App'x 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-orleans-glass-company-v-roy-anderson-corporat-ca5-2015.