New Orleans Channel 20, Inc. v. Federal Communications Commission

830 F.2d 361, 265 U.S. App. D.C. 213, 63 Rad. Reg. 2d (P & F) 1559, 1987 U.S. App. LEXIS 13124
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 6, 1987
Docket17-1075
StatusPublished
Cited by20 cases

This text of 830 F.2d 361 (New Orleans Channel 20, Inc. v. Federal Communications Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Orleans Channel 20, Inc. v. Federal Communications Commission, 830 F.2d 361, 265 U.S. App. D.C. 213, 63 Rad. Reg. 2d (P & F) 1559, 1987 U.S. App. LEXIS 13124 (D.C. Cir. 1987).

Opinion

Opinion for the court filed by Circuit Judge BUCKLEY.

BUCKLEY, Circuit Judge:

Appellants challenge an FCC decision terminating their right to construct and operate a new television station in New Orleans, Louisiana. The FCC awarded the construction permit in 1980. New Orleans Channel 20, Inc. (“NOC”) obtained the permit by assignment in 1983. As of 1985, construction had yet to begin. NOC sought to transfer the permit to LeSea Broadcasting, Inc. (“LeSea”), but the FCC rejected the proposed assignment. The Commission concluded that permit holder NOC had not made a “specific and detailed showing” that the failure to construct the station was due to causes beyond the permittee’s control. 47 C.F.R. § 73.3534 (1985). Appellants do not contest this finding. The FCC also concluded that LeSea, the proposed assignee, failed to demonstrate that its plans for constructing the station were sufficiently definite to “justify the extension” of the construction permit. Id. Appellants cite three instances in which the agency permitted an extension on allegedly similar facts and argue the present denial violates the agency’s obligation to treat like cases alike.

Because the agency’s decision in this case was neither arbitrary or capricious, nor clearly contrary to a line of decisions in other cases, we affirm the FCC’s order and opinion.

I. Background

In October 1980, the FCC awarded the WULT-TY, Channel 20 construction permit to a joint venture known as New Orleans Area Telecasters (“NOAT”). The permit was to expire on April 10, 1982 according to the following terms:

[The permit] shall be automatically forfeited if the station is not ready for operation within the time specified or within such further time as the Commission may allow unless completion of the station is prevented by causes not under the control of the permittee.

Brief for Appellee at 3.

NOAT made absolutely no progress in starting construction. Ultimately, in March 1983, the FCC approved transfer of the permit to the NOC group, which was consummated in June 1983. Notwithstanding two extensions, NOC failed even to begin construction. Consequently, in May 1984, NOC submitted a letter stating that due to the “drain” on its “time and resources” and its “lack of success in finding a suitable [transmitter] site,” it had decided to assign the permit to a better qualified entity, anticipating the assignment application to be filed before May 81, 1984. Joint Appendix (“J.A.”) at 76-77.

Two months later, on July 10,1984, NOC filed its third extension request (the appli *363 cation on appeal in this case) seeking a further six-month extension in order to permit the assignment to LeSea and give it time to complete construction of Channel 20. LeSea is controlled by the Lester Sum-rail family, who also controls the Lester Sumrall Evangelistic Association, Inc., the licensee of two operating television stations. In the July 10 filing, NOC stated it was about to sign an assignment agreement with a party as yet unnamed [LeSea] who had authorized the representation that it was in the process of acquiring a new transmitter site (to be specified in the near future) and that it would begin construction immediately after the assignment, “mak[ing] every effort” to complete construction as soon as possible.

In supplemental filings on December 13, 1984, J.A. at 122, and January 15, 1985, J.A. at 119, LeSea by letter represented that it had actually secured the transmitter site and would soon file an application to modify Channel 20’s permit, placed a contingent $2.5 million equipment order, located a suitable studio site, reached agreements in principle for the station’s Operations Manager and Chief Engineer, and estimated that it would commence operation 210 days following acquisition of the permit. The FCC emphasizes that “[n]o documents were provided by LeSea to support these claims.” Brief for Appellee at 10.

On June 4, 1985, the Commission’s Mass Media Bureau denied NOC’s extension request and, in addition, cancelled the construction permit, deleted the WULT call sign, and dismissed the assignment application as moot. New Orleans Channel 20, Inc., 100 F.C.C.2d 1401 (1985). The Bureau found that NOC did not have a transmitter site and had not begun construction or even ordered equipment, notwithstanding a four-year delay since the award of the permit to predecessor NOAT or the two extensions to NOC. The Bureau noted that extension applications are not automatically granted even if coupled with an application to assign the permit to a party representing its desire to complete construction. The Bureau concluded that it could not find that construction had been prevented by causes beyond NOC’s control or that there were other matters warranting an extension.

NOC and LeSea appealed to the Commission. The agency rule applicable to NOC’s extension request, though subsequently modified, read in pertinent part:

[An application for extension of construction permit] will be granted upon a specific and detailed showing that the failure to complete was due to causes not under the control of the grantee, or upon a specific and detailed showing of other matters sufficient to justify the extension.

47 C.F.R. § 73.3534 (1985) (prior to substantial revision effective December 10, 1985) (emphasis added). The FCC in its brief concedes that the “or” must be read disjunctively — a party can justify its failure to complete or show that “other matters ... justify the extension.” Brief for Appellant at 19.

On the first count — NOC’s failure to complete — the Commission concluded that business considerations, not causes beyond NOC's control, explained the inaction:

[NOC’s] continued lack of [a] site was not attributable to the actual, physical unavailability of potential transmitter sites, but to Glazer’s [Mutual’s principal] business decisions to reject sites as undesirable or too expensive and his failure to reach agreements with owners of potential sites____ [Glazer’s] statements detail various business judgments made by [him] in rejecting sites on which WULTTV’s transmitter could have been constructed.

104 F.C.C.2d at 313. NOC does not challenge this finding on appeal.

Thus the disposition of this case turns on the FCC’s evaluation of LeSea’s qualifications. Appellants argued that the pendency of the assignment application was an “other matter[ ]” warranting the extension. The FCC catalogued the representations made by LeSea but concluded that the proposed assignee had “provided no information to demonstrate the firmness of [the equipment] order” and no “information to show that its putative transmitter or studio *364 sites are actually available.” 104 F.C.C.2d at 314. After referring to “the record in this case,” the FCC concluded:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amgen Inc. v. Hargan
285 F. Supp. 3d 351 (D.C. Circuit, 2018)
Amgen Inc. v. Price
District of Columbia, 2018
Universal Studios LLLP v. Peters
308 F. Supp. 2d 1 (District of Columbia, 2004)
Metro-Goldwyn-Mayer Studios, Inc. v. Peters
309 F. Supp. 2d 48 (District of Columbia, 2004)
Lakeshore Bcast Inc v. FCC
D.C. Circuit, 1999
Kelly v. United States
34 F. Supp. 2d 8 (District of Columbia, 1998)
Orion Comm Ltd v. FCC
D.C. Circuit, 1997
United States v. Reco Vondell Johnson
28 F.3d 151 (D.C. Circuit, 1994)
Keystone Shipping Co. v. United States
801 F. Supp. 771 (District of Columbia, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
830 F.2d 361, 265 U.S. App. D.C. 213, 63 Rad. Reg. 2d (P & F) 1559, 1987 U.S. App. LEXIS 13124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-orleans-channel-20-inc-v-federal-communications-commission-cadc-1987.