New Kent County v. Worley Aviation, Inc.

496 S.E.2d 70, 255 Va. 186, 1998 Va. LEXIS 17
Supreme Court of Virginia·Decided January 9, 1998·No. Record 970236·Published·Cited by 4 cases

Opinion

JUSTICE KINSER delivered the opinion of the Court.

In this appeal, we first consider the jurisdictional requirements under Code §§ 15.1-550 and 15.1-552 for an appeal from an action of a county board of supervisors to the circuit court. Next, we address whether a lessee of land owned by a county is entitled, under the terms of the lease, to recover the fair market value of a capital improvement on the leased premises. Because we find that the lessee satisfied the jurisdictional requirements and constructed a capital improvement pursuant to a capital improvements plan approved by the board of supervisors, we will affirm the circuit court’s judgment in favor of the lessee.

I.

In accordance with a Lease Agreement dated January 24, 1985, New Kent County (the County) leased the New Kent County Airport to Worley Aviation, Inc., (Worley) for an initial term of ten years, with a right to renew the lease for an additional ten-year term under certain conditions. The lease provisions at issue in this appeal provided a mechanism by which Worley could construct a capital improvement on the airport premises and later recover the fair market value of the improvement if the County did not renew the lease for an additional term. Specifically, we are concerned with portions of Sections VI and VII of the lease. In addition to establishing the initial ten-year term of the lease, commencing on January 1, 1985, and ending on December 31, 1994, the relevant portion of Section VII includes the following provisions:

A. If by December 31, 1989, 1) Lessee submits to Lessor a capital improvements plan for the construction of aviation related facilities on the airport property which plan shall specify the size, type and estimated costs of improvements shown thereon together with a committment [sic] by Lessee to begin construction of such improvements if the plan is approved, and *189 2) such plan or a variation of the same acceptable to both parties is approved by the Board of Supervisors of New Kent County, and 3) Lessee actually completes construction on the improvements shown in the plan, then Lessee shall have the right to extend the term of this lease until December 31, 2004, provided a written request for such renewal is submitted to Lessor not less than six (6) months nor more than nine (9) months before the end of the initial ten (10) year term. Notwithstanding a written request for extension from Lessee, Lessor reserves the right to terminate this agreement at the end of the initial ten (10) year term provided the provisions of Section VI paragraph D are complied with. Lessor shall provide written notice of any such termination to Lessee at least six (6) months prior to the end of the term.

Section VI(D), referenced in Section VII, and Section VI(E) contain the following terms:

D. If Lessor is found in breach of this agreement or exercises its right to terminate this lease at the end of the first ten (10) year term and if Lessee has constructed capital improvements on the premises pursuant to an approved capital improvements plan as set out in Section VII paragraph A, then Lessor shall pay to Lessee the fair market value of such improvements at the time of such breach or termination.
E. If lessee fails to exercise a right to renew this lease for an additional ten (10) year term or in the event this lease is terminated because of Lessee’s failure to perform or for any other reason other than breach of this agreement by Lessor, then Lessee shall receive no compensation for any improvements constructed by Lessee and Lessee shall have no right to remove such improvements.
In the event Lessee fails to construct improvements in accordance with the provisions of Section VII paragraph A and Lessor exercises its right to terminate under Section VII paragraph B, then Lessee shall receive no compensation for any improvements constructed by Lessee and Lessee shall have no right to remove such improvements except as set out in Section VII, paragraph C.

*190 In a My 8, 1986, letter, Worley submitted to the County “a capital improvement plan for the construction of aviation related facility in accordance with Section VE of our Lease Agreement.” The proposed capital improvement consisted of a new maintenance aircraft hangar along with an office and terminal building. Worley requested approval of the capital improvement plan 1 by the Board of Supervisors of New Kent County (the Board) and also a renewal of its lease to December 31, 2004, in accordance with Section VK(A), provided the capital improvements were completed.

The County’s attorney provided copies of Worley’s My 8, 1986, letter and plan to the members of the Board. Worley’s request for approval was placed on the Board’s agenda for its October 20, 1986, meeting:

ITEM 5 - REPORT; REVIEW OF SITE AND CONSTRUCTION PLANS FOR NEW KENT AIRPORT TERMINAL BUILDING AND MAINTENANCE HANGER [sic] - The Board will review plans submitted by Mr. A. C. Worley, New Kent Airport Manager, for construction of a 64' x 80' aircraft maintenance hangar along with a 60' x 24' terminal building. The airport lease agreement requires Board approval of all airport capital improvement projects undertaken by the airport operator - Worley Aviation, Inc.

After discussion of the plan and a presentation by Worley, the Board approved, as stated in its minutes, “the plans for the new terminal building.” 2

Subsequent to the meeting, the County’s attorney advised Worley, in a letter dated October 22, 1986, that the Board had approved “the site and construction plans for the new terminal and hangar building .... These plans were approved by the Board in accordance with Section IV-A of the airport lease agreement.” 3 Accordingly, Worley obtained a building permit and proceeded with construction. The building inspector issued a certificate of occupancy on January 4, 1988.

*191 However, part of the present dispute concerns whether the construction was in accordance with the approved drawings because Worley included an apartment area in the building. Those drawings are no longer available, but the building inspector stated that part of his inspection was to ensure compliance with the approved plans.

Free access — add to your briefcase to read the full text and ask questions with AI

New Kent County v. Worley Aviation, Inc., 496 S.E.2d 70, 255 Va. 186, 1998 Va. LEXIS 17 (Va. 1998).

496 S.E.2d 70 (New Kent County v. Worley Aviation, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brian F. Ford, etc. v. Michael J. Tiernan
Court of Appeals of Virginia, 2025
VIKING ENT. v. County of Chesterfield
670 S.E.2d 741 (Supreme Court of Virginia, 2009)
Mansoor v. County of Albemarle
124 F. Supp. 2d 367 (W.D. Virginia, 2000)