New Jersey v. United States Nuclear Regulatory Commission

526 F.3d 98, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20122, 2008 U.S. App. LEXIS 10797, 2008 WL 2120174
CourtCourt of Appeals for the Third Circuit
DecidedMay 21, 2008
Docket06-5140, 07-1559, 07-1756
StatusPublished
Cited by3 cases

This text of 526 F.3d 98 (New Jersey v. United States Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Jersey v. United States Nuclear Regulatory Commission, 526 F.3d 98, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20122, 2008 U.S. App. LEXIS 10797, 2008 WL 2120174 (3d Cir. 2008).

Opinions

OPINION OF THE COURT

SLOVITER, Circuit Judge.

The state of New Jersey petitions this court for review of a guidance document issued by the United States Nuclear Regulatory Commission (“NRC”) which proposes a long-term control license for facilities that decommission under restricted release regulations but cannot find adequate institutional controls. We will dismiss for lack of jurisdiction.

I.

A company that holds a license from the NRC approving its use of materials subject to that agency’s control and authorization must seek its permission to decommission. It must submit a decommissioning plan to the NRC that describes how it proposes to decommission the facility. The plan must include cost estimates and must set forth the major technical actions needed to safely carry out decommissioning. See 10 C.F.R. §§ 40.42, 50.75. The NRC staff must notify and solicit comments from the public on the adoption of the decommissioning plan because such adoption would amend a license. See 10 C.F.R. § 20.1405.

Once a licensee has satisfactorily demonstrated that it has complied with its approved decommissioning plan, it must ask the NRC to terminate its license either for unrestricted release of the site or for restricted release whereby controls remain in place. A license can be terminated for restricted release only after the licensee has met certain conditions. See 10 C.F.R. § 20.1403(a)-(e). Among those conditions is the provision of “legally enforceable institutional controls” that will protect the public by restricting future land use. Id. § 20.1403(b).

The NRC’s License Termination Rule (“LTR”), found in 10 C.F.R. § 20.1401 et seq., sets forth the requirements for decommissioning the licensees’ facilities. See Radiological Criteria for License Termination, 62 Fed.Reg. 39,058 (July 21, 1997). At issue in this case is NUREG-1757, an NRC document that provides guidance on how licensees may satisfy those requirements.

Initially, licensees had difficulty in meeting the requirements set forth in the License Termination Rule for a license with restricted conditions. Licensees had particular difficulty in satisfying the institutional control requirement. In June 2002, the NRC directed its staff to analyze these difficulties. Thereafter, based on its analysis, the staff recommended that “for any [101]*101restricted release site that is unable to establish acceptable institutional controls using other available options,” a licensee could satisfy this requirement through a possession-only license for long-term control (“POL/LTC”). App. at 515. The staff analysis explained that this “is the type of institutional control, similar to EPA’s orders or permits, that provide the necessary restrictions on access or future land use. NRC would monitor, inspect, and enforce under the license authority.” App. at 515.

The NRC approved the staffs recommendations in November 2003, included them in its Draft Supplement 1 to NU-REG-1757 issued in September 2005, and sought public comments on the restricted release/institutional controls issues. See Updates to Implement the License Termination Rule Analysis, 70 Fed.Reg. 56,940 (Sept. 29, 2005). It received twelve public comments, including comments from New Jersey. In September 2006, the NRC approved revising NUREG-1757 to include the POL/LTC option. The NRC posted the revised version of NUREG-1757 on its website on October 27, 2006, and formally announced its availability on December 28, 2006. See Consolidated Decommissioning Guidance, 71 Fed.Reg. 78,234 (Dec. 28, 2006).

Shieldalloy Metallurgical Corporation (“Shieldalloy”), the licensee involved in this appeal, had filed two decommissioning plans that were rejected by the NRC for lack of sufficient information. Thereafter, it revised its decommissioning plan which included the POL/LTC option. The NRC staff accepted Shieldalloy’s revised plan in October 2006 “for the purpose of initiating the technical review of the plan that will eventually produce both a safety evaluation report (SER) and an environmental impact statement (EIS).” In re Shieldalloy Metallurgical Corp., 65 N.R.C. 341, 344, 2007 WL 2195475 (2007). On November 17, 2006, the NRC issued a Notice of Opportunity for a Hearing. See Notice of Consideration of Amendment Request for Decommissioning for Shieldalloy, 71 Fed. Reg. 66,986 (Nov. 17, 2006). There were seven requests for hearings, including those from New Jersey and Gloucester County, New Jersey. See Shieldalloy, 65 N.R.C. at 343. The Atomic Safety and Licensing Board (“ASLB”) granted only New Jersey’s request for a hearing, although Gloucester County was entitled to participate as a non-party. Id. at 343. New Jersey’s seventeen contentions before the ASLB challenge both the technical analyses in Shieldalloy’s decommissioning plan and the legality of the NRC’s decommissioning regulations, including the POL/ LTC proposed in NUREG-1757. Id. at 353-54.

On December 22, 2006, New Jersey filed a petition for review in this court.1 It also filed with the NRC a petition for rulemaking and a request for a hearing on NU-REG-1757. The petition for rulemaking was adjourned by the NRC until rulings by this court and the ASLB. The NRC denied the request for a hearing on January 12, 2007. New Jersey has filed a second petition for review of that ruling. On January 31, 2007, the NRC filed a motion to dismiss New Jersey’s petitions for jurisdictional reasons.

II.

The Administrative Orders Review Act, better known as the Hobbs Act, 28 U.S.C. [102]*102§§ 2341-2351, gives courts of appeals “exclusive jurisdiction to enjoin, set aside, suspend (in whole or in part), or to determine the validity of ... all final orders of the Atomic Energy Commission [now the NRC] made reviewable by section 2239 of title 42.” 28 U.S.C. § 2342(4). The statutory provision incorporated, which is in the Atomic Energy Act, applies to any proceeding “for the granting, suspending, revoking, or amending of any license ... [and] for the issuance or modification of rules and regulations dealing with the activities of licensees.... ” 42 U.S.C. § 2239(a)(1)(A). It subjects to judicial review “[a]ny final order entered in any [NRC] proceeding of the kind specified in subsection (a).” Id. § 2239(b)(1).

The NRC argues that NUREG1757 is a non-binding guidance document, and not a “final order.” Generally, “two conditions must be satisfied for agency action to be ‘final’: First, the action must mark the ‘consummation’ of the agency’s decisionmaking process — it must not be of a merely tentative or interlocutory nature. And second, the action must be one by which ‘rights or obligations have been determined,’ or from which ‘legal consequences will flow.’ ” Bennett v. Spear,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Chemours Company FC, LLC v. EPA
109 F.4th 179 (Third Circuit, 2024)
Morse v. Allied Interstate, LLC
65 F. Supp. 3d 407 (M.D. Pennsylvania, 2014)
Clarke v. Ross
57 V.I. 737 (Virgin Islands, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
526 F.3d 98, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20122, 2008 U.S. App. LEXIS 10797, 2008 WL 2120174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-jersey-v-united-states-nuclear-regulatory-commission-ca3-2008.