New Hope Crushed Stone and Lime Company v. DEP

CourtCommonwealth Court of Pennsylvania
DecidedJuly 18, 2018
Docket1373 C.D. 2017
StatusUnpublished

This text of New Hope Crushed Stone and Lime Company v. DEP (New Hope Crushed Stone and Lime Company v. DEP) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Hope Crushed Stone and Lime Company v. DEP, (Pa. Ct. App. 2018).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

New Hope Crushed Stone : and Lime Company, : Petitioner : : v. : : Department of Environmental : Protection, : No. 1373 C.D. 2017 Respondent : Argued: June 7, 2018

BEFORE: HONORABLE RENÉE COHN JUBELIRER, Judge HONORABLE ANNE E. COVEY, Judge HONORABLE DAN PELLEGRINI, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE COVEY FILED: July 18, 2018

New Hope Crushed Stone and Lime Company (NHCS) petitions this Court for review of the Environmental Hearing Board’s (Board) September 7, 2017 order dismissing NHCS’ appeal from the Department of Environmental Protection’s (DEP) January 29, 2016 letter modifying NHCS’ November 30, 2015 Reclamation Plan (January 2016 Letter). NHCS presents the following issues for this Court’s review: (1) whether the Board’s July 31, 2014 Adjudication (July 2014 Adjudication) wherein it determined that the NHCS quarry (Quarry) was a nuisance is valid and can serve as the basis for the Department’s January 2016 Letter; (2) whether the Board erred by holding that the determination that the Quarry was a nuisance was subject to collateral estoppel and administrative finality when those matters were not actually litigated and essential to the judgment; (3) whether the Board improperly restricted discovery NHCS sought from the Solebury School (School) relating to the conditions of the School grounds adjoining the Quarry that DEP alleged were impacted by Quarry activities; (4) whether the Board properly precluded NHCS from presenting expert evidence, evidence of other alternatives and a proposed work plan that DEP should have considered relating to the conditions alleged to have caused sinkholes; and, (5) whether DEP should have considered other alternatives to certain of the January 2016 Letter’s requirements, and acted arbitrarily and capriciously by basing its requirements on the amount of manpower, equipment, and permit limitations at one point in time, rather than any scientific or engineering principles.

Background The Quarry is located in Solebury Township (Township) and operates as a noncoal surface mine pursuant to Permit No. 7974SM3. The School is a co- educational college preparatory day and boarding school located on approximately 90 acres in the Township, and serves approximately 230 day and boarding students in grades 7 through 12. On July 31, 2014, the Board issued the July 2014 Adjudication rescinding a depth correction DEP had issued to NHCS, which would have allowed NHCS to mine 50 feet deeper to a level of 170 feet below mean sea level (-170 MSL), and determining that the Quarry’s mining and dewatering of the water table was creating a public nuisance by causing numerous sinkholes to open on the School’s campus and on other surrounding properties. NHCS filed an appeal from the July 2014 Adjudication with this Court, but discontinued the appeal before any decision was rendered. DEP subsequently requested NHCS to submit appropriate documentation and revisions to its surface mining permit, National Pollutant Discharge Elimination Permit (NPDES), and reclamation plan in order to bring both permits into compliance with the July 2014 Adjudication and address the existing public nuisance. Thereafter, DEP repeatedly asked NHCS to submit a reclamation plan that would expeditiously abate the public nuisance. DEP’s objective was to restore groundwater beneath the School and in the 2 surrounding area as soon as possible to abate the public nuisance. However, the reclamation plans NHCS submitted to DEP were based on the amount of time NHCS needed to remove all mineable mineral reserves from the Quarry, instead of being determined by the amount of time required to restore the groundwater levels to pre- mining conditions to abate the public nuisance. On October 1, 2015, DEP issued a Compliance Order (October Compliance Order) requiring NHCS to modify its reclamation plan to expeditiously abate the public nuisance, and to submit to DEP a reclamation plan based on the amount of time required to reclaim the Quarry rather than remove mineable reserves. The October Compliance Order stated that NHCS was in violation of Sections 7(c)(5) and 10 of the Noncoal Surface Mining Conservation and Reclamation Act (Act)1 and mandated NHCS to submit a revised reclamation plan and other requested information by October 30, 2015. By November 2015 Order (November Compliance Order), NHCS’ deadline was extended to November 30, 2015. NHCS appealed from both the October and November Compliance Orders (Compliance Orders). NHCS submitted a revised reclamation plan to DEP on November 30, 2015 (November 30, 2015 Plan). Thereafter, on February 11, 2016, NHCS entered into a Consent Assessment of Civil Penalty (CACP) with DEP. Pursuant to the CACP, NHCS agreed to pay a $4,000.00 penalty and withdraw its appeals from the Compliance Orders within five days. NHCS withdrew the appeals from the Compliance Orders on February 12, 2016. The November 30, 2015 Plan involved backfilling the Quarry and allowing the water levels to rise in the pit. Reclamation by backfilling is performed by piling up soil at the top of a quarry highwall and pushing it over the edge with a bulldozer. The slope is then built out until it reaches the appropriate reclamation

1 Act of December 19, 1984, P.L. 1093, as amended, 52 P.S. §§ 3307(c)(5) and 3310 (relating to reclamation plan and public notice timetables). 3 slope, which is the angle of repose, or the angle at which a given material will naturally settle if placed in a pile. The November 30, 2015 Plan indicated a reclamation crew of two people, one using a loader/excavator and one using a haul truck, moving 100 cubic yards of fill material per hour. In addition, the November 30, 2015 Plan provided that stream restoration work on Primrose Creek would be completed in May 2017, upon which time reclamation would begin and be completed in July 2022, approximately 5.23 years later. NHCS proposed to lower its pumping rate to 500,000 gallons per day (gpd) after the completion of reclamation in July 2022. According to the November 30, 2015 Plan, the water level in the quarry pit would be at -2 MSL in July 2022 with a goal of reaching a final elevation of +98 MSL at an undetermined point in the future. The November 30, 2015 Plan set forth that mining and reclamation would occur simultaneously and that reclamation would be conducted 46 weeks per year, allowing two weeks for holidays, two weeks for vacation, and two weeks for inclement weather.

Facts On January 29, 2016, DEP issued the January 2016 Letter determining that the November 30, 2015 Plan remained deficient because, among other things, it did not expeditiously abate the previously-identified public nuisance. In the January 2016 Letter, DEP required additional personnel and equipment and a greater amount of fill, and lowered the Quarry’s pumping rate to 500,000 gpd. After reviewing the November 2015 Plan, DEP performed its own reclamation timetable calculations based upon the information NHCS provided, and determined that NHCS could reasonably complete reclamation and stream restoration work in approximately 3.12 years. DEP modified NHCS’ reclamation schedule as proposed in the November 2015 Plan by adding two additional people to work on reclamation, one using a 65-ton haul truck and one using a bulldozer with equipment 4 already present onsite. In the January 2016 Letter, DEP allowed for further modification of the reclamation plan if safety or environmental concerns arose, and permitted NHCS to submit an alternative modified reclamation plan, subject to DEP’s approval. NHCS appealed from the January 2016 Letter to the Board. On August 9, 2016, in response to NHCS’ discovery requests,2 the School filed a Motion for Protective Order (Motion). On September 16, 2016, the Board granted the Motion with the exception of requiring the School to produce its communications with DEP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramey Bor. v. Com., Dept. of Env. Res.
351 A.2d 613 (Supreme Court of Pennsylvania, 1976)
PA. GAME COMM. v. PennDER
509 A.2d 877 (Commonwealth Court of Pennsylvania, 1986)
J.S. Ex Rel. H.S. v. Bethlehem Area School District
794 A.2d 936 (Commonwealth Court of Pennsylvania, 2002)
In Re Estate of R. L. L.
409 A.2d 321 (Supreme Court of Pennsylvania, 1979)
Ainjar Trust v. Department of Environmental Protection
806 A.2d 482 (Commonwealth Court of Pennsylvania, 2002)
McNeil v. Jordan
894 A.2d 1260 (Supreme Court of Pennsylvania, 2006)
United Refining Co. v. Department of Environmental Protection
163 A.3d 1125 (Commonwealth Court of Pennsylvania, 2017)
Doheny v. Commonwealth, Department of Transportation, Bureau of Driver Licensing
171 A.3d 930 (Commonwealth Court of Pennsylvania, 2017)
Commonwealth v. Wheeling-Pittsburgh Steel Corp.
348 A.2d 765 (Commonwealth Court of Pennsylvania, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
New Hope Crushed Stone and Lime Company v. DEP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-hope-crushed-stone-and-lime-company-v-dep-pacommwct-2018.