New England Medical Center, Inc. v. Rate Setting Commission

384 Mass. 46
CourtMassachusetts Supreme Judicial Court
DecidedJuly 14, 1981
StatusPublished
Cited by13 cases

This text of 384 Mass. 46 (New England Medical Center, Inc. v. Rate Setting Commission) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Medical Center, Inc. v. Rate Setting Commission, 384 Mass. 46 (Mass. 1981).

Opinion

Abrams, J.

The main issue presented by this action is whether the Rate Setting Commission (commission) is authorized by G. L. c. 176A, § 5, to withdraw its approval of an existing interim agreement regulating reimbursement rates between Blue Cross of Massachusetts, Inc. (Blue Cross), and ninety-five Massachusetts hospitals on the ground that negotiations between the parties had not produced a proposed final contract by the commission’s deadline. The plaintiff hospitals challenge the commission’s decision on the ground that it exceeded the scope of the commission’s powers. We agree. We hold that the commission cannot disapprove an existing contract on the ground that the parties have failed to agree on a proposed contract within the time allotted the parties by the commission.3

[48]*48The plaintiff hospitals filed complaints under G. L. c. 176A, § 5, thirteenth par., in the Supremé Judicial Court for the county of Suffolk, seeking review of the commission’s decision withdrawing approval from a reimbursement agreement known as HA-28-i. The hospitals requested that the single justice stay the commission’s challenged decision, which was to become effective May 13, 1981. A single justice of this court reserved and reported the cases without decision, and entered an order staying the commission’s withdrawal of approval of the contract pending the determination of the action by judgment of the full court, or until June 16, 1981, whichever first occurred. The single justice also allowed a stipulation consolidating all the actions, and granted the request of Blue Cross that it be made a defendant for purposes of the consolidated action. On June 9, 1981, we entered an order reversing the commission’s disapproval of HA-28-i. See note 3, supra.

The facts are as follows. On November 10, 1977, the commission approved HA-27, a hospital reimbursement agreement between a number of Massachusetts hospitals and Blue Cross, the only nonprofit hospital service corporation in the Commonwealth. G. L. c. 176A, § 5. The agreement, which governed rates of reimbursement to the hospitals by Blue Cross, had a termination date of September 30, 1980. On March 12,1980, anticipating that Blue Cross and the hospitals would soon begin negotiating a successor agreement to HA-27, the chairman of the commission wrote to Blue Cross, detailing several of the commission’s concerns about the upcoming negotiations, and identifying several issues which it expected would be addressed in the successor contract.

Contracts between Blue Cross and participating hospitals are negotiated on an industry-wide basis by Blue Cross and the Massachusetts Hospital Association, Inc. (MHA), the bargaining agent for the hospitals. After a general contract is approved by Blue Cross and MHA, it is submitted to the commission for its approval or disapproval. See G. L. c. 176A, § 5, sixth & ninth pars. If the general contract is approved by the commission, Blue Cross then contracts [49]*49with each hospital individually using the industry-wide contract as a guide.

Blue Cross and MHA began to negotiate a successor contract to HA-27 in the spring of 1980, but the negotiations broke down in early June. Blue Cross then requested that HA-27 be extended from its scheduled expiration date of September 30, 1980, until December 31, 1980. On August 14, the commission approved that extension.

On November 3, 1980, a successor agreement, HA-28, was submitted to the commission for approval under c. 176A, § 5. Following a public hearing on December 1, 1980, the commission voted to disapprove HA-28. No party appealed that decision. Following the disapproval, Blue Cross asked the commission to approve an interim contract that would carry HA-27 forward for a limited period during which a new successor agreement, to be known as HA-29, could be negotiated. The commission responded that it was “favorably disposed” to approving an interim contract, but suggested that the interim contract contain a preamble that would set out a timetable for the negotiation and submission of HA-29. The commission said that it found a period of two months, from January 1, 1981, through February 28, 1981, acceptable, and that the commission “would expect to receive a copy of the new . . . contract by [March 1, 1981].” The commission stated that “[o]ur willingness to accept a new interim contract, and to approve it for the entire [October 1, 1980, to September 30, 1981] period, is predicated on your expressed sensitivity to our concerns and your expectation that you can make good progress on them. The Commission wpuld be prepared to revoke the interim contract approval if HA-29 does not show adequate progress on these concerns.”

The commission approved the interim agreement between Blue Cross and ninety-five Massachusetts hospitals on December 31, 1980. Known as HA-28-i, the contract was to take effect on January 1, 1981, and was to remain in effect until September 30, 1981. Payments made under HA-28-i, as well as administration of the interim agreement, [50]*50were to be governed by HA-27. A preamble to the contract stated that within sixty days of its approval, Blue Cross and the hospitals would enter into renegotiations toward a successor agreement to take effect October 1, 1981, and that “[i]t is the intention of the parties to submit a revised agreement to the Commission on March 1, 1981.”

However, March 1 passed without the submission of HA-29. The following day, Blue Cross and MHA jointly requested an extension of fourteen days to conclude their negotiations and to draft the new contract. The commission agreed to that extension, but reminded the parties that it expected to receive a signed copy of HA-29 by March 16. The negotiations again broke down, and, after being informed that the parties had reached an impasse, the commission voted on March 12, 1981, to withdraw its approval of HA-28-i, effective May 13, 1981. G. L. c. 176A, § 5, sixth & twelfth pars.

In a statement setting forth its reasons for disapproving the interim contract, the commission quoted its earlier communications with the parties stating that its approval of HA-28-i had been based upon the parties’ understanding that a successor agreement would be ready by March 1. The commission stated, “The interim contract was permitted upon specific assurances by the parties that this mechanism would result in a satisfactory new proposal and would avoid administrative inconvenience to Blue Cross, its subscribers and participating hospitals.”

Following the commission’s withdrawal of its approval of the interim agreement, a number of hospitals filed requests for a public hearing on the commission’s actions. G. L. c. 176A, § 5, twelfth par. After a public hearing was held on April 2, 1981, the commission voted, on April 9, to affirm its decision withdrawing approval from HA-28-i. It is the commission’s withdrawal of approval from the interim contract which the hospitals appeal, pursuant to G. L. c. 176A, § 5, thirteenth & fourteenth pars.

The commission’s authority to disapprove hospital reimbursement contracts. General Laws c. 176A, § 5, requires [51]*51that reimbursement contracts between Blue Cross and hospitals that provide services to Blue Cross subscribers be approved in advance by the commission. The statute provides that no rates of payment to the hospitals by Blue Cross may be approved “unless such rates reflect reasonable costs or are based on charges made to the general public, whichever is lower.”4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reeve v. Thompson
Massachusetts Land Court, 2021
Clear Channel Outdoor, Inc. v. Zoning Board of Appeals of Salisbury
116 N.E.3d 1219 (Massachusetts Appeals Court, 2018)
Murby v. Children's Hospital Corp.
34 Mass. L. Rptr. 1 (Massachusetts Superior Court, Suffolk County, 2016)
Lighthouse Masonry, Inc. v. Taylor
29 Mass. L. Rptr. 492 (Massachusetts Superior Court, 2012)
Ciampi v. Commissioner of Correction
892 N.E.2d 270 (Massachusetts Supreme Judicial Court, 2008)
Lewis v. Committee For Public Counsel Services
739 N.E.2d 706 (Massachusetts Appeals Court, 2000)
In re Inquest into the Death of Walton
4 Mass. L. Rptr. 653 (Massachusetts Superior Court, 1995)
Goddard Memorial Hospital v. Rate Setting Commission
532 N.E.2d 665 (Massachusetts Supreme Judicial Court, 1989)
N.O., M.T., J.O., E.I., D.V., J.D., E.H. v. Callahan
110 F.R.D. 637 (D. Massachusetts, 1986)
Camoscio v. Board of Registration
476 N.E.2d 569 (Massachusetts Supreme Judicial Court, 1985)
Public Service Commission v. Patuxent Valley Conservation League
477 A.2d 759 (Court of Appeals of Maryland, 1984)
Massachusetts Nurses Ass'n v. Dukakis
570 F. Supp. 628 (D. Massachusetts, 1983)
Addison Gilbert Hospital v. Rate Setting Commission
390 Mass. 17 (Massachusetts Supreme Judicial Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
384 Mass. 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-medical-center-inc-v-rate-setting-commission-mass-1981.