New Cingular v. Candia, NH, et al.

2011 DNH 063
CourtDistrict Court, D. New Hampshire
DecidedApril 19, 2011
Docket09-CV-387-SM
StatusPublished

This text of 2011 DNH 063 (New Cingular v. Candia, NH, et al.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Cingular v. Candia, NH, et al., 2011 DNH 063 (D.N.H. 2011).

Opinion

New Cingular v . Candia, NH, et a l . 09-CV-387-SM 4/19/11 UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

New Cingular Wireless PCS, LLC, Plaintiff

v. Case N o . 09-cv-387-SM Opinion N o . 2011 DNH 063 Town of Candia, New Hampshire, and the Zoning Board of Adjustment of the Town of Candia, Defendants

O R D E R

New Cingular Wireless, PCS (“AT&T”) seeks to construct a

telecommunications tower and related facilities in Candia, New

Hampshire, at the site of an existing (but unrelated) radio

tower. Initially, AT&T applied for a special exception and a

variance to construct a 180-foot lattice tower at the site, and

proposed to remove the existing tower. Subsequently, however, it

amended its applications, offering to build a monopole-style

tower at a height of either 150, 115, or 100 feet. The Candia

Zoning Board of Adjustment (the “Board”) denied AT&T’s

applications.

By prior order, the court held that because the Board

addressed only one of AT&T’s four proposed tower heights (i.e.,

the 180-foot lattice tower), its decision to deny AT&T’s

applications for a special exception and a variance was not

supported by substantial evidence. Order dated August 1 1 , 2010 (document n o . 2 3 ) . Rather than enter an order directing the

Board to grant a special exception (and, depending on the height

of the tower, a variance), the court instead remanded the matter

to the ZBA for further proceedings. In that remand order, the

court instructed the Candia ZBA to “issue an adequate written

decision with regard to each of the three remaining proposals,

i.e., for towers of 150, 115, and 100 feet.” Id. at 1 2 .

On remand, the Board granted AT&T’s request for a special

exception to the local zoning ordinance and authorized the

construction of a 100-foot monopole telecommunications tower and

related support facilities. It also approved AT&T’s request to

employ a diesel generator at the site, to supply electrical power

in case of outages. The Board denied AT&T’s proposed tower

alternatives of 115 and 150 feet because, unlike the 100-foot

tower, each of the taller towers would also require a variance

from the “fall zone” setback provisions of the town’s zoning

ordinance. And, said the Board, AT&T failed to meet its burden

of proving entitlement to such a variance.

AT&T challenges the Board’s latest decision, again saying it

is not supported by substantial evidence. See generally 47

U.S.C. § 332(c)(7)(B)(iii) of the Telecommunications Act of 1996

(“TCA”), Pub.L. N o . 104-104, 110 Stat. 56 (codified as amended in

scattered sections of 47 U.S.C.). And, despite earlier

2 representations that it would be satisfied with a 100-foot tower,

it now seeks a court order requiring the defendants to permit

construction of a 120-foot monopole telecommunications tower.1

Defendants object.

Legal Background

I. The Telecommunications Act.

As the Supreme Court has observed, Congress enacted the

Telecommunications Act of 1996:

to promote competition and higher quality in American telecommunications services and to encourage the rapid deployment of new telecommunications technologies. One of the means by which it sought to accomplish these goals was reduction of the impediments imposed by local governments upon the installation of facilities for wireless communications, such as antenna towers.

To this end, the TCA amended the Communications Act of 1934, to include § 332(c)(7), which imposes specific limitations on the traditional authority of state and local governments to regulate the location, construction, and modification of such facilities. Under this provision, local governments may not “unreasonably discriminate among providers of functionally equivalent services,” take actions that “prohibit or have the effect of prohibiting the

1 Although it applied to the Board for a 115-foot tower, AT&T asks this court to order defendants to allow it to construct a 120-foot tower, “for the simple expedient that monopoles are ordinarily manufactured in lengths divisible by 10.” Plaintiff’s memorandum (document n o . 40) at 2 0 , n . 1 4 . The parties recently came to an agreement - of sorts - on this issue. They have stipulated that, if AT&T prevails in this forum, it should be permitted to construct a 120-foot tower. I f , on the other hand, the Board prevails, AT&T will be permitted to construct the previously-approved 100-foot tower. See Stipulation for Entry of Final Judgment (document n o . 4 2 ) .

3 provision of personal wireless services,” or limit the placement of wireless facilities “on the basis of the environmental effects of radio frequency emissions.” They must act on requests for authorization to locate wireless facilities “within a reasonable period of time,” and each decision denying such a request must “be in writing and supported by substantial evidence contained in a written record.”

City of Rancho Palos Verdes v . Abrams, 544 U.S. 113, 115-116

(2005) (citations and internal punctuation omitted). Subject to

the exceptions identified by the Supreme Court, however, the “TCA

preserves state and local authority over the siting and

construction of wireless communication facilities.” Second

Generation Properties, L.P. v . Town of Pelham, 313 F.3d 620, 627

(1st Cir. 2002) (citing 47 U.S.C. § 332(c)(7)(B)).

At issue in this case is the TCA’s requirement that the

Board’s decision be in writing and supported by substantial

evidence. 47 U.S.C. § 332(c)(7)(B)(iii). “If a board decision

is not supported by substantial evidence, . . . then under the

Supremacy Clause of the Constitution, the local law is pre-empted

in order to effectuate the TCA’s national policy goals.” Second

Generation Properties, 313 F.3d at 627. 2

2 Although raised in its complaint as count 3 , AT&T no longer contends that the Board’s decisions amount to an effective prohibition of the provision of wireless services in Candia. See generally 47 U.S.C. § 332(c)(7)(B)(i)(II).

4 II. AT&T’s Burden of Proof.

As noted above, in order to construct either a 115-foot or a

150-foot monopole tower at the site in question, AT&T must obtain

a variance from the fall zone setback requirement of the Candia

zoning ordinance. That ordinance provides:

No buildings, roads or driveways that are not part of the tower site shall be built within 150% of the height of any tower that is located in any zone. Towers must be set back a distance equal to 150% of the height of the tower from any unaffiliated structure, parking areas or lots, driveways, roads, developed areas or property lines.

Town of Candia Zoning Ordinance, Article V I , Section 6.01(G).

To secure the required variance, AT&T bore the burden of

showing, among other things, that literal enforcement of the

ordinance would impose upon it an “unnecessary hardship.” See,

e.g., Garrison v . Town of Henniker, 154 N.H. 2 6 , 30 (2006). See

also Second Generation Properties, 313 F.3d at 628 (“In order to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consolo v. Federal Maritime Commission
383 U.S. 607 (Supreme Court, 1966)
City of Rancho Palos Verdes v. Abrams
544 U.S. 113 (Supreme Court, 2005)
Mills v. Social Security
244 F.3d 1 (First Circuit, 2001)
Daniels v. Town of Londonderry
953 A.2d 406 (Supreme Court of New Hampshire, 2008)
In re the Governor & Executive Council
846 A.2d 1148 (Supreme Court of New Hampshire, 2004)
US Cellular v. City of Concord
2006 DNH 096 (D. New Hampshire, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2011 DNH 063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-cingular-v-candia-nh-et-al-nhd-2011.