Neuss, Hesslein & Co. v. Lane Cotton Mills

118 So. 485, 167 La. 13, 1928 La. LEXIS 1999
CourtSupreme Court of Louisiana
DecidedJuly 20, 1928
DocketNo. 27051.
StatusPublished

This text of 118 So. 485 (Neuss, Hesslein & Co. v. Lane Cotton Mills) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neuss, Hesslein & Co. v. Lane Cotton Mills, 118 So. 485, 167 La. 13, 1928 La. LEXIS 1999 (La. 1928).

Opinions

BRUNOT, J.

Plaintiff is a partnership composed of Edgar J. Hesslein, Eugene Beyer, and John Staudt. The suit is for $116,356.-64, for damages suffered by plaintiff as the result of defendant’s alleged breach of three contracts, the first of "which called for the delivery, during the time beginning October, 1916, and ending March 30, 1917, of 10,000 pieces of coverts; the second for 10,000 pieces of coverts, of which 2,500 pieces per month were to be delivered during the months of June, July, August, and September, 1917; and the third for 3,000 pieces of denims, of which 1,000 pieces per month were to be delivered during the months of June, July, and August, 1917. It is alleged that partial deliveries were made from time to time under each of said contracts, but no deliveries were made under the second contract during the four months of June, July, August, and September, 1917, and that such deliveries as were made under each of said contracts were far short of the quantity called for by the contracts.

The defendant filed an exception of vagueness and an exception of no cause of action. Both exceptions were heard and overruled, the answer was filed June 4, 1919, and further proceedings in the case were held in abeyance from that, time until December 12, 1922, on which date plaintiff filed a supplemental and amended petition. In its answer to the supplemental petition, defendant excepted thereto upon the ground that the original and supplemental petitions contained inconsistent demands; that plaintiff should be ordered to elect; and that the supplemental petition did not set forth a cause of action. These exceptions were referred to the merits, the case was tried, and plaintiff appealed from a judgment rejecting its demands, at its cost.

The innumez-able letters and documents offered on the trial show that there is no material disagreement as to the facts of the case. The real contention between counsel is as to the legal consequences of the admitted facts. The trial judge in his reasons for judgment correctly says:

“The court believes that if the rights of plaintiff and defendant are ascertained as of date May 4^6, 1918, it will then be manifest as to whether or not the plaintiff has a standing in court. To arrive at this conclusion, it will be *15 necessary to briefly state the mutual obligations and rights of the party litigants from the date of the first contract of September 26, 1916.
“This suit is based on the difference between the contract price of these three contracts and the alleged market price of date May 4-6, 1918. The first contract, Exhibit A, dated September 26, 1916, was for 10,000 pieces of coverts to be shipped from October, 1916 to March 30, 1917; that is, the contract should have been completely fulfilled by the 30th of March, 1917. It is well to note that the time of fulfilling the first contract had completely expired before the other two contracts were made. Before taking up these other contracts, let us * * * see what deliveries had been made under the first contract before the expiration of the time mentioned therein. On April 1, 1917, there had been delivered under the contract, which called for 10,000 pieces, an average yardage of 55 to the piece, totaling 550,000' yards, only 2',OSO pieces, containing a total yardage of 113,074 yards, — in round figures approximately only one-fifth of the contract. Notwithstanding this fact, on April 10, 1917, without attempting to place the defendant in default, or to buy in the open market, as the plaintiff would have had a right to do and charge the defendant with the difference between the price thus paid and the contract price, the plaintiff entered into two additional contracts.
“Contract No. 2, dated April 10, 1917, was for 10,000 pieces of coverts, to contain between 50 and 60 yards, said coverts to be shipped 2,500 pieces each during the months of June, July, August and September, 1917. Under this contract no shipment was made during the time specified therein. The only shipment ever made under this contract was made on the 13th day of January, 1918, on which date 434 pieces containing 24,483% yards were shipped.
“The third contract was on the same date as the second, to wit, April 10, 1917, and called for 3,000 pieces of denims to be shipped 1,000 pieces each June, July and August, 1917. Not a single shipment or delivery under this contract was made during the time specified in the contract, the first shipment being- made on the 21st day of January, 1918.
“So in September, 1917, as regards the deliveries under the contracts, the following is a résumé:
“The first contract. Under this contract there had been delivered 6,220 pieces out of a total of 10,000 pieces due, or a total of 320,723 yards delivered out of 550,000 yards called for by the contract. As will be seen, from March 30, 1917, the date on which the time specified in the contract had expired, defendant had delivered under this contract, up to September, 1917, an additional 4,140 pieces containing a total yardage of 207,649, all of these deliveries being made during the months ■ of April, May, June and July, of 1917, the last delivery being made on the 20th of July, 1917.
“The second contract. No deliveries at all.
“The third contract. .No deliveries at all.
“The time having expired on all three contracts.
“Certainly it is not claimed that a putting in default was accomplished at this time. On the contrary, very agreeable and solicitous telegrams were exchanged. For example, on September 4th, 1917, plaintiff wired defendant as follows: ‘Reference pending orders can you give anything definite when will resume deliveries.’ To which telegram defendant answered, on the 7th of September, 1917: ‘Answering telegram fourth expect to resume deliveries in about five weeks.’ The conclusion is inevitable that plaintiff there and then abandoned any idea of ever enforcing its rights as regards the time in which deliveries should be made under the contracts. They accepted this indefinite promise on the part of the defendant corporation to fill these contracts practically at its own pleasure. The correctness of this conclusion is shown by the interchange of correspondence in December, 1917, three months later. On December 24, 1917, plaintiff wired defendant as follows: ‘Your letter 17th, our contract 2:4468 (third contract), your order 329 Blue Denims, when can we expect goods to begin? How many per week? Wire reply.’
“And on December 28th, defendant wrote plaintiff as follows:
“ ‘Contract 24468. Your letter December 24th. We have advised you by wire that we will be in a position to furnish about 200' pieces commencing about January 10th.
“ ‘We have these goods in work now, and unless nothing unforeseen happens, we should be able to pack from 30 to 35 cases monthly. In view of this, we would thank you to let us have shipping instructions now, so that we can forward these goods promptly when put up.’
“From all of which it is apparent, as above stated, that the thought of insisting upon the performance of these three contracts, in December, 1917, seems never to have entered the mind of the officials of plaintiff corporation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. F. Bonsor & Co. v. Simon Rice Milling Co.
92 So. 711 (Supreme Court of Louisiana, 1922)
National Wholesale Grocery Co. v. Simon Rice Milling Co.
92 So. 713 (Supreme Court of Louisiana, 1922)
Monumental Brewing Co. v. Southern Rice Milling Co.
99 So. 401 (Supreme Court of Louisiana, 1924)
J. H. Garrison & Son v. Sherill Hardwood Lumber Co.
100 So. 253 (Supreme Court of Louisiana, 1924)
Eugster & Co. v. Joseph West & Co.
35 La. Ann. 119 (Supreme Court of Louisiana, 1883)

Cite This Page — Counsel Stack

Bluebook (online)
118 So. 485, 167 La. 13, 1928 La. LEXIS 1999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neuss-hesslein-co-v-lane-cotton-mills-la-1928.