Nesbitt v. L. C. & C. Rail Road

29 S.C.L. 697
CourtCourt of Appeals of South Carolina
DecidedMay 15, 1844
StatusPublished

This text of 29 S.C.L. 697 (Nesbitt v. L. C. & C. Rail Road) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nesbitt v. L. C. & C. Rail Road, 29 S.C.L. 697 (S.C. Ct. App. 1844).

Opinion

Curia, per

O’Neall, J.

In this case, I will first consider the ground much argued, but which is really not made by the grounds of appeal — that the Judge below has no [702]*702right to order a non-suit, inasmuch as the parol proof to explain vary or contradict the written contract, was received without objection. It is most generally true, that if incompetent evidence be received without objection, it must go to the jury. But then two things occur. 1st; that the party against whom the testimony was offered might, when offered, have objected to it; and 2d; that when received it made a case on which the jury might legally find for the plaintiff. In this case neither of these exist. In the first place, the plaintiff rested his case altogether on a quantum, meruit, and undertook to show, that in that point of view, he was entitled to recover. It is true, Major McNeill said there was a written contract; but although the defendant might have said, produce that contract, yet the plaintiff could have replied, as his course in substance did, true, there is a written contract, but I will shew the work I did, and then produce the written contract, and it will then appear that my work is extra, and not embraced in it. Could the defendant have stopped him from thus travelling backward through his case 1 When, at the last, as his last piece of evidence, he presented the written contract, then the defendant had the right to read it, and say, all your proof is contrary to this instrument, and is therefore incompetent. But admit that the testimony was out, and that no objection to its incompetency could be urged, will the plaintiff be helped'? Certainly not. The defendant had the right to say, this written contract shews that all the work which you have done, and about which your evidence is given, was to be done, under it, and therefore it is not extra, and your quantum, meruit fails. This is the same thing as a demurrer to evidence. It says, taking your verbal evidence, and written evidence, you cannot recover. If it be true that the plaintiff was bound by the written contract to do the work, then it follows that he cannot recover; and if the jury had found for him again and again, we should be bound to set their verdict aside. This resolves the case into a plain legal question ; and about the right of a Judge to order a non-suit, under such circumstances, no doubt can be entertained. But as this point received much animadversion from both the plaintiff’s counsel, I may be indulged in try[703]*703ing to make a plain thing a little plainer. Suppose that to this claim for work done, the defendant had pleaded that the work was done under a written contract, and had set it out, and the plaintiff had admitted the written contract, but had averred the fact that the work done was not embraced in it; and the defendant had traversed the fact that the work was not embraced in the written contract, and issue had been joined, and the plaintiff had given the very proof now before the court, must not the Judge below have non-suited the plaintiff 1 There cannot be a doubt about it. In what respect does the plaintiff stand better now than he would then 1 In none, it seems to me. Under the plea of the general issue, non-assumpsit, he is bound to shew facts from which a promise, express or implied, is to arise. As soon as the written contract is shewn, if it covers the work done, the plaintiff fails to make a case entitling him to recover, unless he has shewn that his verbal evidence will so construe the written contract as to entitle him to regard the work as extra, or unless he has established a legal, verbal, express contract. It hence becomes necessary to examine these points of the case. Much of the learning and labor which this case has elicited, however creditable it may be to the bar, was altogether outside of the case, and I shall not attempt, therefore, to pursue it through all its ramifications. I shall, however, as I pass through the case, in the shortest way I can, endeavor to dispose of, satisfactorily, I hope, the main arguments. I admit that verbal evidence is admissible to shew a mistake in some written papers, such as a sum in a receipt, or the date of a deed, or to explain a consideration, but not entirely to contradict it, by shewing a different one. So, too, the rule of construction is, as contended for by the defendant, that the whole instrument is to be read, and not mere extracts. I am also satisfied, that where words are used susceptible of several meanings, that then the sense in which they are used, may be ascertained by proof of the subject matter to which the parties applied them. Wig-ram on Ex. Ev. 64, sec. 77. So, when words of a foreign language, or technical words of a trade, are used, then they may be explained by shewing the sense in which they were used. Wigwam Ex. Ev. 49, 58, 62, 76. So, too, the words [704]*704of a testator, or party contracting, are to be understood and judged of by the circumstances in which he was placed^ and to which his words would naturally apply. 3 Phil, by Cow. & Hill, 1408. Usage, too, may be resorted to, to explain words and terms in a contract, where they have no definite or a doubtful meaning.

Having made these admissions, which is, in general, pretty much an admission of the various legal propositions about which so much learning was displayed, I have now to shew that the whole difficulty of this case for the plaintiff arises from the fact that very little of the law cited for him applied to it. In the first place, it is necessary to construe the contract; in doing which I never have been unmindful of the rule that the whole contract is to be construed, and not parts. Read it all, and it in substance is, that the plaintiff undertook to make the line of roadway by excavations and embankments, from point to point, according to the plans and specifications; and for doing it, he was to be paid at so much (the contract reported 25-100 ; in another, 24-100 ; in others, 37-100, and 38-100,) per cubic yard of earth, which the respective sections may contain ; and if rock occurs, then additional for that, as may be determined by the engineer; and for grubbing and clearing, compensation was also to be fixed by the engineer. How can any one pretend that any work necessary to make that road, either in excavation or embankment, was extra work 1 If it were necessary to level mountains, dig through strata of iron or lead ore, or marl, or any other substance, it was to be done, because, to make the roadway, it was necessary the excavation should be made. Is the plaintiff entitled to any compensation for digging up iron ore, lead ore, or marl, if there had been any on the route 1 Read the contract. The work he was obliged to do; but he has accepted as his compensation, so much per cubic yard, for all the earth which the section may contain. By that I understand, not that you are to look to the substances which may be dug up, but after the excavation is made you measure it, and thus ascertain the cubic yards it contains. It is idle to say, when the party has stipulated to take that as his compensation, because his excavation was more difficult than he expected, that [705]*705therefore, he is to be paid for it. The defendant has the right to put his finger on the contract and say, there is what you were to do, here is what I am to pay. Could the plaintiff claim to be paid for the embankment 1 The same reason applies to it, which does to the alleged extra work of excavating hardpan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dubois v. Delaware & Hudson Canal Co.
4 Wend. 285 (New York Supreme Court, 1830)
Dubois v. Delaware & Hudson Canal Co.
12 Wend. 334 (New York Supreme Court, 1834)

Cite This Page — Counsel Stack

Bluebook (online)
29 S.C.L. 697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nesbitt-v-l-c-c-rail-road-scctapp-1844.