Nerco Minerals Co. v. Morrison Knudsen Corp.

90 P.3d 894, 140 Idaho 144, 2004 Ida. LEXIS 59
CourtIdaho Supreme Court
DecidedApril 12, 2004
Docket29352
StatusPublished
Cited by20 cases

This text of 90 P.3d 894 (Nerco Minerals Co. v. Morrison Knudsen Corp.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nerco Minerals Co. v. Morrison Knudsen Corp., 90 P.3d 894, 140 Idaho 144, 2004 Ida. LEXIS 59 (Idaho 2004).

Opinion

KIDWELL, Justice.

This case involves professional malpractice, fraudulent concealment and fraudulent misrepresentation. Nerco Minerals Company and Nerco Delamar Company (collectively “Nerco”) appeal from the district court’s grant of summary judgment in favor of the defendant, Morrison Knudsen Corporation and Morrison Knudsen Engineers, Inc. (collectively “MK”), in an action by Nerco alleging, inter alia, breach of contract, fraudulent misrepresentation, and fraudulent concealment by MK. Summary judgment was granted on the basis that the actions were barred by statutes of limitations. The judgment of the district court is affirmed.

I.

FACTUAL AND PROCEDURAL BACKGROUND

In July and August of 1986, Nerco entered into negotiations with MK for development of a heap leach pad at a mine owned by Nerco. Heap leaching is a method used to salvage precious metals from low-grade ore. Development of the project was separated into four phases: Phase I — pad design and conceptual planning; Phase II — feasibility studies; Phase III — detailed engineering; and Phase IV — construction management.

On or about October 1, 1986, MK entered into a contract with Nerco to perform Phase I of the project. MK completed performance in December of 1986, and provided Nerco a report containing the conclusion that the heap leach pad was “acceptable and safe.” The report did not suggest that the conclusion was based upon incomplete data. In December of 1986, MK contracted with Nerco to perform Phase II of the project. MK completed the feasibility studies and submitted a report to Nerco in February 1987. In both reports, MK divided the heap leach pad into three modules for construction and production purposes.

MK then offered to contract to perform Phases III and IV of the project. However, in April of 1987, Nerco awarded these contracts to Conveyer Engineering, Inc. (“Conveyer”). Conveyer contracted to construct the entire heap leach pad, adopting MK’s methodology of dividing the pad into three modules. On April 29, 1987, MK provided Nerco with preliminary drawings and a prehminary diagram that MK had previously produced in connection with its work on Phases I and II. MK did not perform further work on the project.

Conveyer completed construction of the first module in November of 1987. In January 1990, while the second module was under construction, the first module of the heap leach pad showed signs of failure. Nerco retained the services of several outside engineering firms to investigate the cause of the pad failure and recommend further actions. *147 Nerco’s legal counsel received a report from one of these firms during July of 1990. While Nerco was investigating the pad failure, Nerco and MK entered into an agreement to toll the running of the applicable statutes of limitation. The agreement was effective from December 17, 1991, until November 24, 1993, for a total of twenty-three months and seven days.

On November 24, 1993, Nerco filed complaints against MK in both the United States District Court for the District of Idaho and the District Court for the Third Judicial District of the State of Idaho, in and for the County of Owyhee. In both eases, Nerco alleged breach of contract and breach of express and implied warranties, negligence/professional malpractice, negligenee/duty to warn or disclose, and negligent misrepresentation. Nerco served MK with a summons and complaint for the federal action on November 24, 1993, but did not inform MK of the state action until September 14,1995. On August 9,1995, despite Nereo’s failure to serve MK with the complaint in the state action within six months as required by Rule 4(a)(2), I.R.C.P., Judge Goff issued an order retaining the case for six months. On September 25, 1995, Nerco voluntarily dismissed the federal action due to lack of diversity jurisdiction.

On October 31, 1995, Nerco amended its state court complaint to include claims for fraudulent concealment and fraudulent misrepresentation. Nerco served MK with the amended complaint on the same day. MK thereafter filed a motion to transfer venue to Ada County or, in the alternative, to dismiss the action. On May 21, 1996, venue was transferred from Owyhee County to Ada County. Judge Goffs assignment to the case ended upon the transfer of the case to Ada County.

On August 6, 1996, Nerco filed a second Complaint in Ada County, alleging five claims for relief: breach of contract; negligence/professional malpractice; negligent misrepresentation; fraudulent concealment; and fraudulent misrepresentation. MK was served with the complaint on January 31, 1997.

On August 5, 1997, all of Nerco’s claims against MK in the first state action (dated November 24, 1993) were dismissed due to Nerco’s failure to serve the complaint within six months, as required by court rule. This Court affirmed in Nerco Minerals Co. v. Morrison Knudsen Corp., 132 Idaho 531, 976 P.2d 457 (1999).

On February 19,1997, MK filed its Answer to Nerco’s second Complaint, filed August 6, 1996, and on February 27, 2001, MK filed a Motion for Summary Judgment asking the district court to grant summary judgment in its favor as to all counts.

On November 20, 2001, the district court entered its Memorandum Opinion and Order on MK’s Motion for Summary Judgment. With the exception of Nerco’s claim based upon the theory of breach of contract, the district court granted MK’s motion as to all claims by Nerco because they were barred by the statute of limitations.

On August 22, 2002, MK moved for a second summary judgment as to the remaining count. In the alternative, MK requested that the district court reconsider its previous ruling as to the interpretation and application of Idaho Code § 5-241(b), which resulted in the denial of MK’s motion for Summary Judgment as to the contract claim.

On December 5, 2002, the district court granted MK’s motion for summary judgment as to Nerco’s sole remaining claim based on the theory of breach of contract. The district court concluded that the rule of law pronounced in Lapham v. Stewart, 137 Idaho 582, 51 P.3d 396 (2002), governed the lawsuit; and because Lapham controlled, it was not necessary to address MK’s alternative argument regarding I.C. § 5-241(b). Nerco appeals to this Court.

II.

STANDARD OF REVIEW

On appeal from the grant of a motion for summary judgment, this Court employs the same standard as used by the district court originally ruling on the motion. Griffin Const., Inc. v. City of Lewiston, 135 Idaho 181, 185, 16 P.3d 278, 282 (2000). *148 Summary judgment is proper “if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” I.R.C.P. 56(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VanRenselaar v. Batres
Idaho Supreme Court, 2025
IDHW v. Beason
Idaho Supreme Court, 2024
Keller v. Keller
D. Idaho, 2021
Davis v. Tuma
469 P.3d 595 (Idaho Supreme Court, 2020)
Swafford v. Huntsman Springs Inc
Idaho Supreme Court, 2017
Michael S. Molen v. Ronald D. Christian
388 P.3d 591 (Idaho Supreme Court, 2017)
Eagle Equity Fund, LLC v. TitleOne Corp.
386 P.3d 496 (Idaho Supreme Court, 2016)
Robert L. Kroenlein Trust ex rel. Alden v. Kirchhefer
2015 WY 127 (Wyoming Supreme Court, 2015)
Jay Brown v. Auga Greenheart
Idaho Supreme Court, 2014
Brown v. Greenheart
335 P.3d 1 (Idaho Supreme Court, 2014)
McCormack v. Caldwell
266 P.3d 490 (Idaho Court of Appeals, 2011)
Beach v. Bank of America (In Re Beach)
447 B.R. 313 (D. Idaho, 2011)
Robert M. Michael v. Stephen F. Smith
Idaho Court of Appeals, 2010
McCabe v. Craven
188 P.3d 896 (Idaho Supreme Court, 2008)
Darrel McCabe v. Olivia Craven
Idaho Court of Appeals, 2007
Western Corporation v. Stan L. Vanek
158 P.3d 313 (Idaho Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
90 P.3d 894, 140 Idaho 144, 2004 Ida. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nerco-minerals-co-v-morrison-knudsen-corp-idaho-2004.