Nelson v. Chicago, Milwaukee & St. Paul Railway Co.

19 N.W. 52, 60 Wis. 320, 1884 Wisc. LEXIS 122
CourtWisconsin Supreme Court
DecidedApril 8, 1884
StatusPublished
Cited by13 cases

This text of 19 N.W. 52 (Nelson v. Chicago, Milwaukee & St. Paul Railway Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson v. Chicago, Milwaukee & St. Paul Railway Co., 19 N.W. 52, 60 Wis. 320, 1884 Wisc. LEXIS 122 (Wis. 1884).

Opinion

LyoN, J.

The gravamen of the defense is the alleged negligence of the plaintiff which caused the collision of the two trains. The question whether the failure of the plaintiff to discover that the new time-table put train No. 38 on the road on the night the collision happened, was negligence, was submitted to the jury and resolved in the negative. It is now claimed, on behalf of the railway company, that the plaintiff was bound to discover from the time-table that No. 38 would be on the road that night, and to wait for it at Hickory Grove, and hence that his failure to do so was negligence in law. If this is a correct position, the defendant’s counterclaim was established, and the plaintiff was not entitled to judgment for the balance of his wages, because the damages to the defendant, caused by his negligence, greatly exceeded his demand.

A vital question in the case, therefore,- — one which.underlies many, if not all, of the other propositions argued by the learned counsel for the defendant, — is, whether, under the facts of this case, the question of the alleged negligence of the plaintiff was a question of fact for the jury or of law for the court.

In Hill v. Fond du Lac, 56 Wis., 242, it is said, in the opinion by Mr. Justice Cassoday: “Negligence is almost always to be deduced as an inference of fact from several [324]*324facts and circumstances disclosed by the testimony, after their connection and relation to the matter in issue have been traced, and their weight and force considered. In such cases, if unbiased men would differ as to such inferences, then they cannot be made without the intervention of a jury, although all the witnesses agree in their statements, or there be but one statement which is consistent throughout.” Page 24G. It is only when the inference of negligence, or the absence of it, from the undisputed facts proved, is inevitable that the court will direct a verdict. In all cases in which such inference is in doubt, giving to'the testimony the construction most favorable to the party charged therewith, the question of negligence is for the jury. A very large proportion of actions for negligence are of the latter class. Sutton v. Town of Wauwatosa, 29 Wis.,. 21; Kenworthy v. Town of Ironton, 41 Wis., 647; Townley v. C., M. & St. P. R'y Co., 53 Wis., 626.

In this case the facts are undisputed, but several of them are essential to be considered, and the relative weight of each determined, before the inference therefrom of negligence, or the want of it, can properly be drawn. We will briefly refer to them. The time-table which went into operation Eebruary 20, 1881, was first placed in the hands of defendant at ten o’clock A. M. of that day. It could be ascertained from such time-table that train No. 38 was not to start from Savanna until five minutes after midnight, but it required a mental process to determine that this slight change of tea minutes would put that train on the road on Sunday night instead of Saturday night, as theretofore. The plaintiff and his conductor would naturally examine first to see if there was a change in the time of their train, or in the hour or place of meeting other trains. This they did, and fully learned the time-table in these respects. But they both failed to discover the fact that a change of ten minutes in the running time of No. 38 worked a change of twenty-four [325]*325hours once in each week. In this particular they failed to trace out the change in time to its logical result.

It is impossible for us to say that the plaintiff had sufficient time after he received the time-table to master its contents and learn accurately the movements of all trains the running time of which affected the movements of his train. That time-table is in evidence, and to a layman it might appear difficult to understand it thoroughly after close study of it for two hours or a day. This might not appear so to an expert. But how the fact is this court does not know. If the defendant company did not furnish the new time-table to plaintiff long enough before he was required to start his train to enable him to master its contents, then certainly he should not be held negligent because he did not understand it fully, if he made a reasonable effort to understand it. This consideration alone is sufficient to send the question of his negligence to the jury. In this connection it may be observed that the fact that the conductor of No. 7 (presumably competent) failed also to discover that No. 38 should be on the road on that Sunday night, is not without significance in determining the question whether the plaintiff was negligent. It was for the jury, not the court, to say how much weight this fact was entitled to.

Moreover, it appeared that the plaintiff was continuously on duty with his locomotive from two A. M. on Frida}*-until ten P. M. on Saturday —■ forty-four hours — save about three hours on Saturday morning. The weather was very severe. It was said in argument that the railway was impeded with snow, and the plaintiff during that time was engaged in clearing the track. The great snow-fall of that winter, and the difficulties encountered by all railway companies in this latitude in keeping their roads open, are matters of common knowledge, and we can readily believe the statement of counsel in this behalf. A jury might well say that a failure by the plaintiff fully to comprehend the time-table during [326]*326the brief time he had in which to examine it, was not negligence on his part, in view of the protracted and probably severe service which the company had so recently required of him. Under these circumstances it would be grossly unreasonable to require of him the same accuracy of reasoning and ability to comprehend all the results of the apparently slight change in the running time of No. 38, as might justly be required had he not been so recently subjected to such a severe and protracted physical and mental strain. The weight which ought to be given to this important element of the res gestae is peculiarly for the determination of the jury.

The circuit court refused to allow the plaintiff to show that he was not feeling well on that Sunday (probably the result of his severe labors); that he wished to be relieved from duty on the night of the collision for that reason; and that the foreman of the company refused to relieve him. On what principle this testimony was rejected we are at a loss to comprehend. The testimony ought to have been received, although, probably, the error is not available to the plaintiff on this appeal.

The position that the plaintiff was bound, at all hazards, to understand and know fully all the results of the' changes in the running time of trains made by the new time-table, is untenable. To sustain it would be to apply, in this case, a rule which-has never been applied to any other class of actions for negligence. The true rule is thus stated by Ooolet, 3"., in Page v. Wells, 37 Mich., 415: “Whoever bargains to render services for another, undertakes for good faith and integrity, but he does not agree that he 'will commit no errors. For negligence, bad faith, or dishonesty he would be liable to his employer, but, if he is guilty of neither of these, the master or employer must submit to such incidental losses as may occur in the course of the employment, because these are incident to all avocations, and no one, by any im[327]*327plication of law, ever undertakes to protect another against them.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guild v. More
155 N.W. 44 (North Dakota Supreme Court, 1915)
Forest County v. Shaw
136 N.W. 642 (Wisconsin Supreme Court, 1912)
Noble v. Libby
129 N.W. 791 (Wisconsin Supreme Court, 1911)
Leque v. Madison Gas & Electric Co.
113 N.W. 946 (Wisconsin Supreme Court, 1907)
Tishacek v. Milwaukee Electric Railway & Light Co.
85 N.W. 971 (Wisconsin Supreme Court, 1901)
Powell v. Ashland Iron & Steel Co.
73 N.W. 573 (Wisconsin Supreme Court, 1897)
Thoresen v. La Crosse City Railway Co.
58 N.W. 1051 (Wisconsin Supreme Court, 1894)
Valin v. Milwaukee & Northern Railroad
51 N.W. 1084 (Wisconsin Supreme Court, 1892)
Kennedy v. Denver, South Park & Pacific R'y Co.
10 Colo. 493 (Supreme Court of Colorado, 1887)
Dahl v. Milwaukee City Railway Co.
22 N.W. 755 (Wisconsin Supreme Court, 1885)
Hoye v. Chicago & Northwestern Railway Co.
23 N.W. 14 (Wisconsin Supreme Court, 1885)
Kaples v. Orth
21 N.W. 633 (Wisconsin Supreme Court, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
19 N.W. 52, 60 Wis. 320, 1884 Wisc. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-v-chicago-milwaukee-st-paul-railway-co-wis-1884.