Nelson Engr. Constr. v. Austin Bldg. & Design

CourtNebraska Court of Appeals
DecidedMay 2, 2023
DocketA-22-319
StatusPublished

This text of Nelson Engr. Constr. v. Austin Bldg. & Design (Nelson Engr. Constr. v. Austin Bldg. & Design) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson Engr. Constr. v. Austin Bldg. & Design, (Neb. Ct. App. 2023).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

NELSON ENGR. CONSTR. V. AUSTIN BLDG. & DESIGN

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

NELSON ENGINEERING CONSTRUCTION, INC., APPELLEE, V.

AUSTIN BUILDING & DESIGN INC., APPELLANT.

Filed May 2, 2023. No. A-22-319.

Appeal from the District Court for Dakota County: BRYAN C. MEISMER, Judge. Appeal dismissed. Ethan E. Zweig and Joseph E. Cavasinni, of Hall & Evans, L.L.C., and Michael T. Eversden and Brian T. McKernan, of McGrath, North, Mullin & Kratz, P.C., L.L.O., for appellant. David C. Briese and Daniel L. Hartnett, of Crary, Huff, Ringgenberg, Hartnett & Storm, P.C., for appellee.

PIRTLE, Chief Judge, and MOORE and WELCH, Judges. MOORE, Judge. INTRODUCTION Ingredion Incorporated (Ingredion) is the owner of property that is the subject of a construction project in Dakota County. Austin Building & Design Inc. (Austin) is a general contractor on the project, and Nelson Engineering Construction, Inc. (Nelson), is a subcontractor. The contract between Ingredion and Austin calls for resolution of its disputes in state court, while the contract between Austin and Nelson calls for resolution of any claims through arbitration. Nelson filed an action against Ingredion and other lienholders, including Austin, in Dakota County District Court seeking to foreclose on construction liens and to recover in quantum meruit for expenses and labor provided for the project.

-1- Austin later filed a motion to compel arbitration in the U.S. District Court for District of Nebraska (federal court) and filed a motion to stay proceedings in district court. The district court denied Austin’s motion to stay, and in its order addressed the merits of the arbitrability issue pending before the federal court. Austin appeals, arguing that the district court effectively converted its motion to stay into a motion to compel arbitration. We conclude that Austin has not appealed from a final order and dismiss its appeal. STATEMENT OF FACTS On November 30, 2018, Ingredion and Austin entered into a written contract (the prime contract) in which Ingredion retained Austin to design and construct a pea protein isolate facility in Sioux City, Nebraska. Austin subsequently entered into two subcontracts with Nelson, for concrete foundation work and steel work related to the project. Section 2.6.1 of the prime contract requires that any subcontractor “must agree to abide [sic] all terms and conditions” of the prime contract. Section 1.1.1 of the general conditions of the subcontracts Austin entered into with Nelson specify that the prime contract is included under the definition of the subcontract documents and is “fully a part of the Subcontract as if attached to this Subcontract or repeated herein.” Section 13.5 of the prime contract provides that “any claim or cause of action . . . arising under or relating to this Agreement . . . shall be brought in District Court 6 for Dakota County, Nebraska.” Section 2.2.9 of the general conditions of the subcontracts states “[a]ny claim that [Nelson] may have against Austin . . . or any claim that Austin may have against [Nelson] . . . shall be resolved exclusively through arbitration.” On October 7, 2021, Nelson filed a complaint against Ingredion and other lienholders, including Austin. Nelson sought to foreclose the construction lien it had filed against the real property owned by Ingredion where the project was performed. The complaint noted that Nelson included Austin as a defendant solely due to Austin’s status as a junior lienholder. Nelson also included a claim to recover in quantum meruit, asserted only against Ingredion, for labor, materials, and services that Nelson provided for the project, totaling $2.5 million. The complaint included no claims asserted against Austin directly. On December 20, 2021, Austin filed a complaint in federal court seeking an order compelling Nelson to arbitrate its claim against Austin. On the same day, Austin filed a motion to stay the district court action pending determination of arbitrability by the federal court. Austin’s federal complaint is not a part of our record, but is referenced in its motion to stay. A telephonic hearing on Austin’s motion to stay was held on January 31, 2022. At the hearing, the district court received copies of the prime contract and the subcontracts. In an order entered on April 1, 2022, the district court denied Austin’s motion to stay. The court found the language in the subcontracts providing for arbitration to be contrary to the language of the prime contract, which provides for disputes to be resolved in district court. The court further found that the prime contract contained language binding parties entering into subcontracts to the prime contract, and therefore the prime contract controlled. The court also noted that it had previously addressed this issue in a prior order entered in another case involving Ingredion, Austin, and Nelson, and that it was reaching the same conclusion as it had in that case. The court concluded that because the dispute resolution provisions of the prime contract were applicable, and the

-2- arbitration provisions in the subcontract did not apply, there was no reason to stay the action pending the federal court’s ruling on arbitration. We note that although the prior case noted by the district court was appealed to us, the parties stipulated to dismiss the appeal before we had an opportunity to address the jurisdiction question. See Austin Building & Design Inc. v Ingredion Inc., 30 Neb. App. xvi (No. A-21-454, July 27, 2021). Austin appeals. ASSIGNMENTS OF ERROR Austin assigns that the district court erred in (1) denying Austin’s motion to stay pending the resolution of the petition to compel arbitration before the federal court; (2) basing its decision regarding Austin’s motion to stay on an improper resolution of an issue not before it by failing to consider the appropriate factors for determining the issue; and (3) finding that the contract between Austin and Nelson does not contain an enforceable arbitration agreement. STANDARD OF REVIEW A jurisdictional question that does not involve a factual dispute presents a question of law. Shasta Linen Supply v. Applied Underwriters, 290 Neb. 640, 861 N.W.2d 425 (2015). ANALYSIS Before reaching the legal issues presented for review, it is the duty of an appellate court to determine whether it has jurisdiction. Shasta Linen Supply v. Applied Underwriters, supra. An appellate court lacks jurisdiction to entertain an appeal unless it is from a final order or a judgment. Id. The threshold question before us is whether the district court’s order, which denied Austin’s motion to stay the state court proceedings pending resolution of its motion to compel arbitration filed in the federal court, is a final, appealable order. When the district court denied Austin’s motion to stay, it also reached the merits of the arbitrability issue pending before the federal court, concluding that the arbitration provisions of the subcontract did not apply and that there was no reason to stay the action. Austin asserts that the district court’s order is therefore substantively similar to the denial of a motion to compel arbitration. Our appellate caselaw has contemplated jurisdictional questions related to motions to compel arbitration and motions to stay judicial proceedings pending arbitration. See Pearce v. Mutual of Omaha Ins. Co., 293 Neb. 277, 876 N.W.2d 899 (2016); Shasta Linen Supply v. Applied Underwriters, supra; Kremer v. Rural Community Ins. Co., 280 Neb. 591, 788 N.W.2d 538 (2010); Webb v. American Employers Group, 268 Neb. 473, 684 N.W.2d 33 (2004).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Webb v. American Employers Group
684 N.W.2d 33 (Nebraska Supreme Court, 2004)
Pearce v. Mutual of Omaha Ins. Co.
293 Neb. 277 (Nebraska Supreme Court, 2016)
Tegra Corp. v. Boeshart
976 N.W.2d 165 (Nebraska Supreme Court, 2022)
Avis Rent A Car Sys. v. McDavid
984 N.W.2d 632 (Nebraska Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Nelson Engr. Constr. v. Austin Bldg. & Design, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-engr-constr-v-austin-bldg-design-nebctapp-2023.