N.E.A. Cross, Inc. v. National Fuel Gas Supply Corp.

600 A.2d 228, 410 Pa. Super. 451, 16 U.C.C. Rep. Serv. 2d (West) 1056, 1991 Pa. Super. LEXIS 3912
CourtSuperior Court of Pennsylvania
DecidedDecember 19, 1991
Docket600
StatusPublished
Cited by13 cases

This text of 600 A.2d 228 (N.E.A. Cross, Inc. v. National Fuel Gas Supply Corp.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.E.A. Cross, Inc. v. National Fuel Gas Supply Corp., 600 A.2d 228, 410 Pa. Super. 451, 16 U.C.C. Rep. Serv. 2d (West) 1056, 1991 Pa. Super. LEXIS 3912 (Pa. Ct. App. 1991).

Opinion

TAMILIA, Judge:

Appellant, N.E.A. Cross Inc. (NEA), appeals from the judgment nunc pro tunc in favor of appellee, National Fuel Gas Supply Corporation (National).

The present dispute relates to an overpayment by National involving Gas Purchase Agreement No. 37061, executed in February, 1982. The parties stipulated to the following facts before the trial court. Between 1977 and 1982, NEA and National entered into a series of gas purchase agreements, which developed into transactions involving often in excess of $1,000,000 per month. National issued checks to NEA monthly, based on check requisitions detailing the amount of gas purchased. In turn, based on these figures, NEA would make monthly payments of a one-eighth share to various landowners. Mistakes by National in the collection of data necessary for preparation of check requisitions *453 and in the computation of payments were not uncommon. Thus, in Agreement No. 37061, the parties made the following allowance for mistakes:

ARTICLE IX(c): If any error or inaccuracy in chart information, payments, statements, calculations or determinations is discovered, proper adjustment and correction thereof shall be made as promptly as practicable thereafter.

When issuing a check for the gas purchased during July/August, 1982, National overpaid NEA by $7,181.50. The mistake was a result of an error by National in recording information received from meter readings for gas received during the months in question. The error was detected by National and the check requisition for September/October, 1982, was issued accordingly with the notation “volume adjustment.” Because only a limited amount of fuel was provided during that period, however, National was able to recoup only $2,096.96, leaving an outstanding balance of $5,084.54. Although check requisitions for October/November, 1982, and November/December, 1982, show sufficient quantities of gas were delivered so that National could have deducted the amount due from NEA, National erred in failing to do so. National continued to purchase gas from NEA under Agreement 37061 but apparently forgot about the credit it was due until March, 1988, when it deducted $5,084.54 from its payment to NEA.

NEA filed the underlying action, arguing National was not entitled to recovery because, pursuant to the terms of the purchase agreement, it waited too long to try to recoup the overpayment. Argument was held and the trial court, without a jury, found in favor of National. Although the Order in National’s favor was entered May 23, 1990 and amended June 5, 1990, judgment was not entered until May 7, 1991. The court held, in light of the relationship of the parties, the process of determining amounts of gas purchased and the ongoing, complex billing process, the delay in the set-off was “reasonable.” (Slip Op., Bozza, J., 3/21/ 91, pp. 3-4.) The court reasoned the oversight was under *454 standable considering the volume of business exchanged by the parties. Also, the parties’ continuing relationship meant recoupment would not in any way be burdensome to NEA.

NEA now argues National’s attempt to correct a billing error more than five years after it was discovered was untimely under the terms of the contract, which directly governs the present dispute. In short, National did not correct the problem “as promptly as practicable” and, therefore, should be precluded from adjusting the payments to NEA more than five years later.

National contends it made two mistakes in the preparation of check requisitions for payment to NEA, and each of these errors was corrected almost immediately after it was discovered. Thus, National did correct the errors which led to the over-collection “as promptly as practicable.” In the alternative, National contends the language of the agreement was ambiguous and, therefore, the trial court correctly considered extrinsic evidence in deciding whether National’s actions were in compliance with the contract.

Whether the trial court has correctly interpreted a writing, in ascertaining the legal duties which arise from it, is a question of law which this Court may review. Loeffler v. Mountaintop Area Joint Sanitary Authority, 101 Pa. Cmwlth. 514, 516 A.2d 848 (1986); citing Cowen v. Krasas, 438 Pa. 171, 264 A.2d 628 (1970). As cited above, the following provision in the contract was subject to the trial court’s interpretation:

If any error or inaccuracy in chart information, payments, statements, calculations or determinations is discovered, proper adjustment and correction thereof shall be made as promptly as practicable thereafter.

Although the trial court did not find that National corrected the problem “as promptly as practicable,” it found under the circumstances the more than five year delay was commercially reasonable. In support of its interpretation, the trial court cited 13 Pa.C.S. § 2309(a), Shipment, delivery or *455 other action, which states: “[T]he time for shipment or delivery or any other action under a contract if not provided in this division or agreed upon shall be a reasonable time.” We agree with NEA the trial court erred in applying this provision of the Pennsylvania Commercial Code because the parties clearly agreed that time for performance would be “as promptly as practicable.”

“When a contract is clear and unequivocal, its meaning must be determined by its contents alone.” Department of Transportation v. Manor Mines, Inc., 523 Pa. 112, 119, 565 A.2d 428, 432 (1989). In PBS Coals, Inc. v. Burnham Coal Co., 384 Pa.Super. 323, 558 A.2d 562 (1989), we stated:

The paramount goal of contractual interpretation is to ascertain and give effect to the intent of the parties. In determining the intent of parties to a written agreement, the court looks to what they have clearly expressed, for the law does not assume that the language of the contract was chosen carelessly.

Id., 384 Pa.Superior Ct. at 328, 558 A.2d at 564 (citations omitted). Here, the trial court ignored the language of the contract and substituted the requirement that corrections be made a reasonable time thereafter.

The obvious purpose of the contractual requirement that corrections be made “as promptly as practicable” is to allow the parties to close the books on past transactions. NEA argues as follows:

If a correction could be made more than five years after discovery, then [NEA] would not know for at least five years later whether National Fuel would seek reimbursement for an earlier mistake by National Fuel. [NEA] also makes payments to landowners who own the property on which the gas wells are located. [NEA] bases its payments to the landowners based on National Fuel’s payments. Thus, the longer National Fuel waits to correct errors, the greater chance that [NEA] may be caught in the middle and prejudiced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiley, C. v. Brooks, J.
2021 Pa. Super. 190 (Superior Court of Pennsylvania, 2021)
Ducas, M. v. Pinecrest Development
Superior Court of Pennsylvania, 2021
Driscoll, R. v. Arena, J.
Superior Court of Pennsylvania, 2019
Bausch, J. v. Green, J.
Superior Court of Pennsylvania, 2018
West v. West
27 Pa. D. & C.4th 9 (Berks County Court of Common Pleas, 1995)
Aloe Coal Co. v. Department of Transportation
643 A.2d 757 (Commonwealth Court of Pennsylvania, 1994)
Carpenter v. Federal Insurance
637 A.2d 1008 (Superior Court of Pennsylvania, 1994)
Katzeff v. Fazio
628 A.2d 425 (Superior Court of Pennsylvania, 1993)
Meeting House Lane, Ltd. v. Melso
628 A.2d 854 (Superior Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
600 A.2d 228, 410 Pa. Super. 451, 16 U.C.C. Rep. Serv. 2d (West) 1056, 1991 Pa. Super. LEXIS 3912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nea-cross-inc-v-national-fuel-gas-supply-corp-pasuperct-1991.