N.E. Marine Towing and Constr., Inc. v. City of Ellsworth

CourtSuperior Court of Maine
DecidedApril 17, 2008
DocketHANcv-04-36
StatusUnpublished

This text of N.E. Marine Towing and Constr., Inc. v. City of Ellsworth (N.E. Marine Towing and Constr., Inc. v. City of Ellsworth) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.E. Marine Towing and Constr., Inc. v. City of Ellsworth, (Me. Super. Ct. 2008).

Opinion

STATE OF MAINE SUPERIOR COURT HANCOCK, SS. CIVIL ACTION Docket No. CV-04-36 ' \ ,. -.J I) ~ l\ I L! L;---; -" nl) J v - / ,< ~ c.~' '/'> .­

Northeast Marine Towing and Construction, Inc., Plaintiff

v. Decision and Judgment OONALDL.GARBRECHT LAW LIBRARY City of Ellsworth et aI., Defendants 1-,1 AY '.1 h .

A consolidated hearing was held on the complaint of plaintiff Northeast Marine Towing and Construction, Inc. (NEM) and on the counterclaim of defendant City of Ellsworth. At trial, a representative of NEM and counsel for NEM were present. The defendants appeared through counsel and, during portions of the trial, through representatives of those parties. The pending claims arise out of a contract between NEM and the City, under which NEM agreed to dredge a portion of the City's harbor in the Union River. For the reasons stated in this order, the court concludes that NEM materially breached its contract and that the City terminated the contract for cause. On this basis, the court awards relief to the City. The court also concludes that defendant Woodard & Curran, Inc. (W&C) was not a party to the contract, that it acted entirely as the City's agent and that it is not liable to NEM.

A. Findin2s of fact 1. The project and the contract The Union River extends from Union Bay, a saltwater body, to Ellsworth and beyond. In the late 1990's, the Army Corps of Engineers (ACOE) initiated a project to perform maintenance dredging of the federal navigational channel within the Union River between Union Bay and the City's harbor. The purpose of this project was to improve the quality of the channel for use by boats and other vessels. In coordination with the

1 ACOE project, the City initiated its own efforts to dredge sections of the harbor abutting the terminus of the federal channel, near the City's public boat landing. The City's dredging plans was one aspect of a harbor revitalization program. The proposed City dredge would encompass both intertidal and subtidal areas of the harbor, covering approximately 5 acres. The planned dredge would create a subsurface depth of five feet below mean low water, which would be similar to the dredged depth of the federal channel. The City initially estimated that, to achieve these goals, the dredge would result in the removal of 28,000 cubic yards of sediment and other spoils. The City engaged W&C to act as its agent in obtaining the permits necessary to proceed with the dredge. W&C, as the City's agent, then filed a permit application with the Maine Department of Natural Resources, which is within the Department of Environmental Protection. See exhibit 8. In that application, the City disclosed to DEP that W&C was acting as its agent. See exhibit 9b. W&C also filed a permit application with ACOE. In December 1999 and July 2000 respectively, those agencies issued permits to the City authorizing the municipal dredge project. See exhibit 18 (project manual, which includes copies of the permits). With those permits in hand, in January 2001, the City - through W&C - issued a project manual with invitations to bid, as part of the process of soliciting interest from marine dredging contractors. [d. W&C subsequently amended the January 2001 project manual to provide that projected volume of dredged material would be increased from 29,000 cubic yard to 35,500 CY. See exhibit 225. James Moody, W&C's project manager for the proposed dredge, sent a copy of the project manual to NEM's principal, Robert Twitchell. See exhibit 20. Moody forwarded the project manual to six other contractors. NEM did not submit a bid, and in fact the City received only one bid, which was from Prock Marine, a marine contractor based in Rockland. See exhibit 21. Prock was the contractor that had also contracted with ACOE to dredge the federal channel in the Union River. Prock's bid was based on a price of $13.25 per cubic yard of spoils removed from the harbor. The City decided not to accept Prock's bid because of the absence of any competitive bidding. See exhibit 23. In April 2001, W&C issued a second project manual in a renewed effort to solicit interest in the dredging project. See exhibit 24. This time, NEM submitted a bid, in which it proposed to be paid at the rate of $12.50 per cubic yard. See exhibit 27. In its

2 proposal, NEM advised that to perform the work, it intended to acquire 2 barges, each with a 250 cubic yard capacity. [d. Twitchell had intended to dump the dredged material into one of those barges while the other one, which would already be filled, was hauled to the dumping ground several miles away. This way, Twitchell planned to dredge and remove 500 cubic yards per day (one load daily in each barge). In the end, however, Twitchell purchased only one barge, which had a 300 CY capacity. Twitchell looked at a second barge and was not satisfied with its condition. However, as he testified at trial, he would not have purchased a second barge even if he had found one that was seaworthy. In its bid, NEM expressly recognized that some parts of the project area might be more difficult to dredge than others, and it therefore reserved the right to negotiate a higher rate of compensation "prior to dredging." [d. NEM chose its proposed rate of $12.50, nonetheless, for the specific purpose of attempting to underbid Prock, based on the bid that Prock submitted previously. In its written bid, NEM represented that it was "fully aware" of the terms and contents of the April 2001 project manual and the location of the area to be dredged. [d. The City viewed NEM's bid favorably, and Twitchell and the City's then-manager, Timothy King, held a pre-contract meeting on July 19,2001, to further discuss the proposed dredging project. See exhibit 30. Ultimately, on September 13,2001, NEM and the City entered into a contract under which NEM would perform the dredging operation in the harbor area. See exhibit 32. As indicated in the contract, the parties estimated that the amount of material to be dredged was 35,500 cubic yards. See id. at Bates 2347, 2349-50. Based on the amount of materials that were projected to be dredged and removed, the total expected contract price that the City would pay to NEM was $481,250 (25,000 CY at the rate of $12.50 per CY, and 11,250 CY at the rate of $15 per Cy).l See id. at Bates 2292, 2349-50. Prior to this project, the largest job that NEM had undertaken was worth approximately $40,000. In previous projects, NEM used as many as six workers. For this job, NEM began with a total of three workers, including Twitchell. One of those workers left NEM during the first season, thus leaving only two workers during the balance of the time when NEM was engaged in the dredge. Despite this history, the contract required NEM to provide

1 In January 2002, the contract price to $516,022 after the parties agreed to a change order

that affected the unit price per cubic yard of some of the spoils. See exhibit l04b.

3 competent and qualified personnel to do the work, see id. at Bates 2318, and it authorized the City to terminate the contract for cause if NEM persistently failed to provide "sufficient skilled workers or suitable materials or equipment" to conduct the dredging operation, see id. at Bates 2340. The contract expressly identified NEM and the City as the parties to the agreement. W&C was not a party to the contract, and in fact the terms of the agreement recite that W&C acted as the City's representative. See, e.g., exhibit 32 at Bates 2291, 2326. Thus, under the contractual arrangement to which NEM agreed, W&C was an agent for a fully disclosed principal. The contract further provided that W&C's involvement in the dredge project would not expose it to liability under claims sounding in "contract, tort or otherwise...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Scotia Prince Cruises Ltd.
2003 ME 78 (Supreme Judicial Court of Maine, 2003)
Down East Energy Corp. v. RMR, INC.
1997 ME 148 (Supreme Judicial Court of Maine, 1997)
Cummings v. Bean
2004 ME 93 (Supreme Judicial Court of Maine, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
N.E. Marine Towing and Constr., Inc. v. City of Ellsworth, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ne-marine-towing-and-constr-inc-v-city-of-ellsworth-mesuperct-2008.