Naysmith v. City of Auburn

146 N.W. 971, 95 Neb. 582, 1914 Neb. LEXIS 278
CourtNebraska Supreme Court
DecidedApril 3, 1914
DocketNo. 17,433
StatusPublished
Cited by3 cases

This text of 146 N.W. 971 (Naysmith v. City of Auburn) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Naysmith v. City of Auburn, 146 N.W. 971, 95 Neb. 582, 1914 Neb. LEXIS 278 (Neb. 1914).

Opinion

Reese. C. J.

This is an action against the city of Auburn by plaintiffs, the owners of residence property in said city, for damages to real estate by the overflow of surface water, alleged to have been caused by a change of the sidewalk grade, and the imperfect and negligent drainage of the streets adjacent to the property, to the extent of overflowing of the lots upon which the residence is located, and thus impairing their value and their use as residence property. The action is based upon two allegations of the petition; one, that the dwelling-house was originally constructed with reference •to and corresponding with the street as it then existed, and that by a subsequent elevation of the sidewalk in front of the premises the house and lots were caused to be at a lower level from the sidewalk, the danger from overflow increased, and the value of the property thereby reduced and impaired; the other, that the city wrongfully, negligently and unlawfully constructed a ditch or waterway along and near the lot line and a drain or ditch across the street in front of the premises by which an increased flow of water was turned upon and against said lots, but without adequate drainage for the increasd flow, and by reason whereof a large volume of surface water was thrown against and over the sidewalk space and onto the lots, to the injury of plaintiffs and damage to the property, which was used as a residence. The answer consists of a denial of unadmitted facts, and alleges, in substance, that the house was orig[584]*584inally constructed upon low ground, below tbe street and sidewalk level, the top of the foundation being below the level of the street and sidewalk space; that long before the improvements of the street and sideAyalk were made the property was frequently overfloAved, the surface Avater running and collecting about the house and into the cellar thereunder; that no damage was caused to the property by anything done by the city in the Avay or by the means of the improvements of the street or the surface drainage; that the change of the elevation of the sidewalk was very limited in extent, and the improvements of both street and sidewalk, together with the excaiution of gutters and ditches, Avere necessary for the benefit of the public in the use of the street as a public thoroughfare; that the same were reasonably and carefully made, and in strict accordance with the rights and duty of the city, and without damage to plaintiffs’ property; that, if plaintiffs haATe suffered any damage by reason of the overflow of the property or the deposit of earth or debris thereon, the same has been caused by the negligence on the part of the plaintiffs by reason of the house having been built on ground lower than the grade of the street, in the natural depression thereof, without any protection or effort to prevent the natural action of the surface Avaters; that by the improvements of the street, as stated, the property of plaintiffs had been increased in value, and not in any way injured or the value decreased. Reply, a general denial. A jury trial was had, which resulted in a verdict in favor of plaintiffs, finding the damage to the property to be $180.75, upon which, after the motion for a new trial was overruled, a judgment was rendered. Defendant appeals.

The cause was tried on the part of each side with á high degree of care and skill, and, apparently, every proper phase of the case Avas presented to the jury. The same commendable care has been observed in the presentation of the cause on this appeal. However, it will not be deemed necessary to folloAV the discussions as contained in the briefs and oral argument, as the case may be disposed of to our [585]*585satisfaction by its examination, limiting onr investigation to a few plain principles which are applicable thereto.

As we view the record, the principal lines of contention were submitted to the jury on sharply conflicting testimony. Aside from the inconvenience of access to the property by the elevation of the sidewalk space in front of the lots, the already high surface as compared with the level of the property, we are scarcely persuaded that the subject merits very much attention. The surface of the lots was below the level of the street grade established by long user. The elevation of the sidewalk, the extent of which was sharply in dispute by the witnesses, was probably, in part at least, for the protection of the property in the prevention of the overflow of the surface water onto the lots from the street, but mainly for the improvement of the street and sidewalk. In the estimation of some of the witnesses this change had an injurious effect upon the value of the property, while other witnesses were of the opinion that the two lots owned by plaintiffs were benefited thereby. On this subject the conclusion to be drawn was for the jury. In addition to the oral testimony, the jury were, by order of the court, sent to view the premises, which it is presumed they did, and by that means the actual view furnished to the jurors a line of evidence not presented to the trial court, nor to this court. While not attaching so much importance to this feature of the case, we are reminded that it may have been, and probably was, considered by the jury as a partial basis for their verdict.

As we view the case, the principal element of damage as found by the jury arose from the effort of the city to take care of surface water by a system of drainage, as to which it was claimed, and the evidence introduced tended to show, that the volume of water carried in the drains was largely increased in time of rains and melting snows, and that to such an extent as to damage plaintiffs’ property. The lots are situated in the south end of the west half of the block, the west ends fronting to the west upon Sixth street, while Twelfth avenue is along the south line. There is evidence that in the construction of the drainage system [586]*586of that part of the city quite a large watershed was so ditched and drained as to carry an increased flow of surface water to the south along the west side of Sixth street until it came to a point opposite the southwest corner of plaintiffs’ property, where the drain was carried across the street in a ditch under a crosswalk, where the flow of water came in contact with the drain running to the south along the east side of the street, the outlet being from there to the east along the south line of the south lot of plaintiffs’ property; that this last named drain was not of sufficient capacity to meet the requirements of the two ditches, and at the point where the two came together the water accumulated in a body, and was forced over the embankment of the ditch onto plaintiffs’ lots. One witness testified that “the water sometimes seemed to come with greater force from the west, evidently from the greater drainage that came across the street. It came with great force. The water also from the north backed up, and the water from the west seemed to hold that from the north, and backed it up until it.came over the corner of the walk; that at the lower part or corner of the walk, the water rushed around the corner, and made an abrupt turn; that all came along the gutter so that it came around that easily, and that coming from the corner seemed to come with a rush, and as it came it swelled toward the house. Q,. Would it reach the building and porch? A. It did; we could see it. Q. Tell the jury how it ran. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hickman v. Hunkins
489 N.W.2d 316 (Nebraska Court of Appeals, 1992)
Young v. City of Scribner
106 N.W.2d 864 (Nebraska Supreme Court, 1960)
Cattin v. City of Omaha
31 N.W.2d 300 (Nebraska Supreme Court, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.W. 971, 95 Neb. 582, 1914 Neb. LEXIS 278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/naysmith-v-city-of-auburn-neb-1914.