Navient Solutions, LLC v. BPG Office Partners XIII Iron Hill LLC
This text of Navient Solutions, LLC v. BPG Office Partners XIII Iron Hill LLC (Navient Solutions, LLC v. BPG Office Partners XIII Iron Hill LLC) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
NAVIENT SOLUTIONS, LLC, ) ) Plaintiff/ ) Counterclaim Defendant, ) ) v. ) C.A. No. N20C-04-005 AML ) BPG OFFICE PARTNERS XIII IRON ) HILL LLC and OFFICE PARTNERS ) XIII IRON HILL LLC, ) ) Defendants/ ) Counterclaim Plaintiffs. )
Submitted: February 10, 2023 Decided: April 27, 2023
POST-TRIAL MEMORANDUM OPINION
R. Karl Hill, Esq., and James S. Green, Jr., Esq. of SEITZ, VAN OGTROP & GREEN, P.A., Wilmington, Delaware, Attorneys for Plaintiff/Counterclaim Defendant Navient Solutions, LLC.
Jeffrey M. Weiner, Esq. of LAW OFFICES OF JEFFREY M. WEINER, Wilmington, Delaware, Attorney for Defendants/Counterclaim Plaintiffs BPG Office Partners XIII Iron Hill LLC and Office Partners XIII Iron Hill LLC.
LeGrow, J. The parties to this action entered into a lease agreement for a commercial
property in Delaware. The parties’ relationship throughout most of the lease term
appeared civil and cooperative. Near the end of the lease term, the tenant paid to
replace a cooling tower at the property and demanded repayment of the unamortized
costs from the landlord as required by the lease. The landlord, however, refused to
pay. Shortly thereafter, the tenant initiated this action seeking reimbursement for
the costs it expended to replace the cooling tower, and the landlord asserted a
counterclaim against the tenant. The counterclaim sought costs for items at the
property that the tenant allegedly was required to repair or replace during the term
of the lease.
The parties and the Court undertook a three-day bench trial. Before trial
began, the landlord conceded it owed the tenant the cost for the replacement cooling
tower. The tenant therefore prevails on its breach claim. Trial focused on the
landlord’s counterclaim against the tenant. After considering all the evidence, the
Court enters judgment for the landlord with respect to replacement costs for two of
the four item groups at issue in the counterclaim. But the landlord did not carry its
burden with respect to the other two item groups. The Court therefore will enter
partial judgment in the tenant’s favor on the counterclaim. The Court additionally
finds the tenant is the prevailing party and is entitled to attorneys’ fees and expenses
under the terms of the commercial lease.
1 I. BACKGROUND
Trial took place in this action over the course of three days. Twelve witnesses
testified virtually. The parties submitted post-trial briefs addressing factual and legal
issues. These are the facts as the Court finds them after assessing the witnesses’
credibility and weighing the evidence.1
A. The Parties
Plaintiff/Counterclaim Defendant Navient Solutions, LLC (“Navient”) filed
this commercial landlord-tenant breach of contract action.2 Navient is a Delaware
limited liability company and was formerly known as Sallie Mae, Inc.3
Defendants/Counterclaim Plaintiffs BPG Office Partners XIII Iron Hill LLC and
Office Partners XIII Iron Hill LLC (collectively, “BPG”) are two Delaware limited
liability companies.4 BPG asserted a breach of contract counterclaim against
Navient.5
B. The Commercial Property and the Lease Agreement
The Iron Hill Corporate Center is a three-building office complex in Newark,
Delaware (the “Office Complex”).6 The Office Complex was constructed between
1 The factual background in this post-trial decision cites: C.A. No. N20C-04-005 AML docket entries (by “D.I.” number); trial exhibits (by “JX” number); the trial transcript (“Trial Tr.” by day “I-III”); and stipulated facts set forth in the parties’ Joint Pre-Trial Order (“PTO”). 2 See Compl. ¶ 1 (D.I. 1). 3 Id. ¶ 2. 4 Id. ¶¶ 3-4. 5 PTO § 2(aa). 6 Id. § 2(a). 2 1990 and 1992 and has three wings.7 BPG acquired the Office Complex on March
31, 2008.8 On the same date, BPG leased one wing of the Office Complex—the
“Blue Wing”—to Bank of America.9 In August 2010, Bank of America subleased
the Blue Wing to Sallie Mae, Inc. with anticipated delivery to occur on or before
November 1, 2010.10 On November 20, 2012, Sallie Mae, Inc. (now Navient) and
BPG entered into a commercial lease agreement for the Blue Wing with Navient as
the tenant and BPG as the landlord (the “Lease Agreement”).11 The Blue Wing is
the subject of this action; it is a three-floor building with approximately 85,563
rentable square feet.12
C. Language of the Lease Agreement
The claims and counterclaims in this action assert various breaches of the
Lease Agreement. Several provisions in the Lease Agreement are at issue in this
case. Section 4 of the Lease Agreement, titled “Condition of Premises,” explains
Navient inspected the Blue Wing, accepted it (less the “Common Areas”) in an “as-
is” condition, and did not rely on any representations by BPG.13 Section 4
specifically states:
7 Id. § 2(b). 8 Id. § 2(c). 9 See id. § 2(c)-(d); Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 4 (D.I. 57). 10 PTO § 2(d); JX 2. 11 PTO § 2(f); JX 3 (a copy of the Lease Agreement). 12 PTO § 2(e). 13 JX 3 § 4. 3 Subject to [BPG’s] obligation, if any, to perform Landlord’s Tenant Improvement Work, the Premises [defined as the Blue Wing, “exclusive of the Common Areas”] are accepted by [Navient] in ‘as-is’ condition and configuration without any representations or warranties by [BPG]. [Navient] agrees that it has inspected the Premises and the [Blue Wing] and has agreed to lease the Premises as a result of [Navient’s] own investigations and reviews, and not in reliance of any representation or warranty made by [BPG] or by anyone on [BPG’s] behalf.14
Section 6 is titled “Surrender; Alterations and Repairs.” Section 6(a) governs
part of Navient’s obligations at the expiration of the Lease Agreement.15 Section
6(a) states in pertinent part: “At the expiration or other termination of this Lease,
[Navient] shall deliver the Premises with all improvements located thereon (except
as otherwise herein provided) in good repair and condition, reasonable wear and tear
resulting from the Permitted Use and damage due to casualty expected . . . .”16
Section 6(i) establishes Navient’s obligations relating to repairs,
replacements, and restorations. Section 6(i) states:
[Navient] shall take good care of the Premises and keep them free from waste and nuisance of any kind. [Navient] shall keep the Premises, including the Alterations installed by [Navient], in good condition and shall undertake and be responsible for all repairs, replacements, restorations and renewals necessary to keep and maintain such good condition, except as provided in Section 15(g) below. If [Navient] fails to commence the repairs described above within ten (10) business days after the occurrence of the damage or injury, [BPG] may, upon five (5) business days’ prior written notice to [Navient], at its option to make such repairs, and [Navient] shall, within thirty (30) days of its receipt
14 Id.; see also id. at Basic Lease Provisions (3) (defining “Premises”). 15 JX 3 § 6(a). 16 Id. 4 of [BPG’s] written demand therefor (together with reasonable supporting documentation), pay [BPG] the cost therefor. The performance by [Navient] of its obligations to maintain and make repairs to any Building Systems within and exclusively serving the Premises (for which [Navient] is responsible pursuant to the terms hereof) shall be conducted only by contractors and subcontractors reasonably approved by [BPG] in writing.17 Section 6(j) memorializes Navient’s obligations to repair the Blue Wing and
Free access — add to your briefcase to read the full text and ask questions with AI
IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
NAVIENT SOLUTIONS, LLC, ) ) Plaintiff/ ) Counterclaim Defendant, ) ) v. ) C.A. No. N20C-04-005 AML ) BPG OFFICE PARTNERS XIII IRON ) HILL LLC and OFFICE PARTNERS ) XIII IRON HILL LLC, ) ) Defendants/ ) Counterclaim Plaintiffs. )
Submitted: February 10, 2023 Decided: April 27, 2023
POST-TRIAL MEMORANDUM OPINION
R. Karl Hill, Esq., and James S. Green, Jr., Esq. of SEITZ, VAN OGTROP & GREEN, P.A., Wilmington, Delaware, Attorneys for Plaintiff/Counterclaim Defendant Navient Solutions, LLC.
Jeffrey M. Weiner, Esq. of LAW OFFICES OF JEFFREY M. WEINER, Wilmington, Delaware, Attorney for Defendants/Counterclaim Plaintiffs BPG Office Partners XIII Iron Hill LLC and Office Partners XIII Iron Hill LLC.
LeGrow, J. The parties to this action entered into a lease agreement for a commercial
property in Delaware. The parties’ relationship throughout most of the lease term
appeared civil and cooperative. Near the end of the lease term, the tenant paid to
replace a cooling tower at the property and demanded repayment of the unamortized
costs from the landlord as required by the lease. The landlord, however, refused to
pay. Shortly thereafter, the tenant initiated this action seeking reimbursement for
the costs it expended to replace the cooling tower, and the landlord asserted a
counterclaim against the tenant. The counterclaim sought costs for items at the
property that the tenant allegedly was required to repair or replace during the term
of the lease.
The parties and the Court undertook a three-day bench trial. Before trial
began, the landlord conceded it owed the tenant the cost for the replacement cooling
tower. The tenant therefore prevails on its breach claim. Trial focused on the
landlord’s counterclaim against the tenant. After considering all the evidence, the
Court enters judgment for the landlord with respect to replacement costs for two of
the four item groups at issue in the counterclaim. But the landlord did not carry its
burden with respect to the other two item groups. The Court therefore will enter
partial judgment in the tenant’s favor on the counterclaim. The Court additionally
finds the tenant is the prevailing party and is entitled to attorneys’ fees and expenses
under the terms of the commercial lease.
1 I. BACKGROUND
Trial took place in this action over the course of three days. Twelve witnesses
testified virtually. The parties submitted post-trial briefs addressing factual and legal
issues. These are the facts as the Court finds them after assessing the witnesses’
credibility and weighing the evidence.1
A. The Parties
Plaintiff/Counterclaim Defendant Navient Solutions, LLC (“Navient”) filed
this commercial landlord-tenant breach of contract action.2 Navient is a Delaware
limited liability company and was formerly known as Sallie Mae, Inc.3
Defendants/Counterclaim Plaintiffs BPG Office Partners XIII Iron Hill LLC and
Office Partners XIII Iron Hill LLC (collectively, “BPG”) are two Delaware limited
liability companies.4 BPG asserted a breach of contract counterclaim against
Navient.5
B. The Commercial Property and the Lease Agreement
The Iron Hill Corporate Center is a three-building office complex in Newark,
Delaware (the “Office Complex”).6 The Office Complex was constructed between
1 The factual background in this post-trial decision cites: C.A. No. N20C-04-005 AML docket entries (by “D.I.” number); trial exhibits (by “JX” number); the trial transcript (“Trial Tr.” by day “I-III”); and stipulated facts set forth in the parties’ Joint Pre-Trial Order (“PTO”). 2 See Compl. ¶ 1 (D.I. 1). 3 Id. ¶ 2. 4 Id. ¶¶ 3-4. 5 PTO § 2(aa). 6 Id. § 2(a). 2 1990 and 1992 and has three wings.7 BPG acquired the Office Complex on March
31, 2008.8 On the same date, BPG leased one wing of the Office Complex—the
“Blue Wing”—to Bank of America.9 In August 2010, Bank of America subleased
the Blue Wing to Sallie Mae, Inc. with anticipated delivery to occur on or before
November 1, 2010.10 On November 20, 2012, Sallie Mae, Inc. (now Navient) and
BPG entered into a commercial lease agreement for the Blue Wing with Navient as
the tenant and BPG as the landlord (the “Lease Agreement”).11 The Blue Wing is
the subject of this action; it is a three-floor building with approximately 85,563
rentable square feet.12
C. Language of the Lease Agreement
The claims and counterclaims in this action assert various breaches of the
Lease Agreement. Several provisions in the Lease Agreement are at issue in this
case. Section 4 of the Lease Agreement, titled “Condition of Premises,” explains
Navient inspected the Blue Wing, accepted it (less the “Common Areas”) in an “as-
is” condition, and did not rely on any representations by BPG.13 Section 4
specifically states:
7 Id. § 2(b). 8 Id. § 2(c). 9 See id. § 2(c)-(d); Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 4 (D.I. 57). 10 PTO § 2(d); JX 2. 11 PTO § 2(f); JX 3 (a copy of the Lease Agreement). 12 PTO § 2(e). 13 JX 3 § 4. 3 Subject to [BPG’s] obligation, if any, to perform Landlord’s Tenant Improvement Work, the Premises [defined as the Blue Wing, “exclusive of the Common Areas”] are accepted by [Navient] in ‘as-is’ condition and configuration without any representations or warranties by [BPG]. [Navient] agrees that it has inspected the Premises and the [Blue Wing] and has agreed to lease the Premises as a result of [Navient’s] own investigations and reviews, and not in reliance of any representation or warranty made by [BPG] or by anyone on [BPG’s] behalf.14
Section 6 is titled “Surrender; Alterations and Repairs.” Section 6(a) governs
part of Navient’s obligations at the expiration of the Lease Agreement.15 Section
6(a) states in pertinent part: “At the expiration or other termination of this Lease,
[Navient] shall deliver the Premises with all improvements located thereon (except
as otherwise herein provided) in good repair and condition, reasonable wear and tear
resulting from the Permitted Use and damage due to casualty expected . . . .”16
Section 6(i) establishes Navient’s obligations relating to repairs,
replacements, and restorations. Section 6(i) states:
[Navient] shall take good care of the Premises and keep them free from waste and nuisance of any kind. [Navient] shall keep the Premises, including the Alterations installed by [Navient], in good condition and shall undertake and be responsible for all repairs, replacements, restorations and renewals necessary to keep and maintain such good condition, except as provided in Section 15(g) below. If [Navient] fails to commence the repairs described above within ten (10) business days after the occurrence of the damage or injury, [BPG] may, upon five (5) business days’ prior written notice to [Navient], at its option to make such repairs, and [Navient] shall, within thirty (30) days of its receipt
14 Id.; see also id. at Basic Lease Provisions (3) (defining “Premises”). 15 JX 3 § 6(a). 16 Id. 4 of [BPG’s] written demand therefor (together with reasonable supporting documentation), pay [BPG] the cost therefor. The performance by [Navient] of its obligations to maintain and make repairs to any Building Systems within and exclusively serving the Premises (for which [Navient] is responsible pursuant to the terms hereof) shall be conducted only by contractors and subcontractors reasonably approved by [BPG] in writing.17 Section 6(j) memorializes Navient’s obligations to repair the Blue Wing and
caps unamortized reimbursements. Section 6(j)(i) states Navient:
agrees, at [Navient’s] sole cost and expense, to maintain, repair and replace all Building Systems exclusively serving the Building in good order and repair, and [BPG] hereby grants [Navient] an irrevocable license during the Term of the Lease . . . to access and modify all portions of the Building . . . necessary to perform [Navient’s] obligations hereunder . . . ; provided, however, that [Navient] shall repair any damage to the Building or Land caused by the existence of such rights (normal wear and tear and damage due to casualty expected). In the event all or any portion of the Building Systems exclusively serving the Building requires replacement during the Term, [Navient] shall undertake the same at its sole cost and expense, and such replacement shall be accomplished, in a Class-A manner, using materials and equipment consistent with that found in comparable office buildings in the Wilmington, Delaware metropolitan area. However, notwithstanding the foregoing . . . , if (1) the portion of the Building Systems being replaced (the “Replacement Item”) has a useful life extending beyond the Lease Term . . . , and (2) the cost of such Replacement Item would otherwise constitute a capital repair or replacement cost [if] such items were purchased by or on behalf of [BPG], then the cost of such Replacement Item shall be amortized over the useful life thereof at a rate of eight percent (8%) per annum, and [Navient] shall receive an amount from [BPG] at the expiration or sooner termination of the Lease equal to the then-remaining unamortized cost of such Replacement Item (the “Unamortized Reimbursement”).18
17 Id. § 6(i). 18 Id. § 6(j)(i). 5 Section 6(j)(ii) further explains Unamortized Reimbursements and states:
Notwithstanding the foregoing . . . , in no event shall the Unamortized Reimbursement exceed $300,000 in the aggregate; provided, however, that so long as such replacement otherwise satisfies clauses (1) and (2) of subsection [(j)](i) above, the foregoing limitation shall not apply with respect to any replacement of the cooling tower (and its component parts) serving the Premises HVAC systems, the cost of which shall be amortized over the useful life thereof at a rate of eight percent (8%) per annum and [Navient] shall receive an amount from [BPG] at the expiration or sooner termination of the Lease equal to the then- remaining unamortized cost thereof.19 Exhibit E to the Lease Agreement creates a “Tenant Fund” that Navient was
permitted to use for improvements to the premises. Exhibit E states:
(a) [BPG] hereby grants to [Navient] an allowance for completion of the Tenant Improvements in an amount up to, but not in excess of One Million Two Hundred Eighty-three Thousand Five Hundred Twenty Dollars ($1,283,520.00) (the “Tenant Fund”). In addition to the Tenant Fund, [BPG] shall provide [Navient] (upon the presentation of reasonably acceptable documentation) with an allowance of up to, but not in excess of, Six Thousand Eight Hundred Forty-five and 44/100 Dollars ($6,845.44) for an architectural “test-fit”. The Tenant Fund shall be used for: (i) Payment of the cost of preparing the Space Plans and Working Drawings, including architectural/design, mechanical, electrical, plumbing and structural drawings and of all other aspects necessary to complete the Space Plans and Working Drawings; (ii) The payment of plan checking by government authorities and for permits and license fees relating to construction of the Tenant Improvements; and (iii) Construction and Installation of the Tenant Improvements, including, without limitation, the following: (aa) Installation within the Premises of all partitioning, doors, floor coverings, ceilings, wall coverings and painting, millwork and similar items; (bb) All electrical wiring, lighting, fixtures, outlets and switches, and other electrical work to be installed within the Premises; (cc) The furnishing and installation of all duct work, terminal boxes, diffusers and accessories required for
19 Id. § 6(j)(ii). 6 the completion of the heating, ventilation and air conditioning systems within the Premises, including the cost of meter and key control for after-hour air conditioning; (dd) Any additional [Navient] requirements including, but not limited to, odor control, special heating, ventilation and air conditioning, noise or vibration control or other special systems; (ee) All fire and life safety control systems such as fire, walls, sprinklers, halon, fire alarms, including piping, wiring and accessories, installed within the Premises; (ff) All plumbing, fixtures, pipes and accessories to be installed within the Premises; (gg) Testing and inspection costs; and (hh) General conditions and contractor’s fees.20
Section 13 of the Lease Agreement, titled “Remedies and Termination Upon
Tenant Default,” defines BPG’s options if Navient defaulted under the Lease.
Section 13(b)(vi) states:
(b) During the existence of an Event of Default, [BPG] shall have the right (but not any duty) to exercise one or more of the following remedies, as well as any other remedies available at law or in equity: (vi) [BPG] may enter upon the Premises, without being liable for prosecution or any claim of damages therefor, and cure the default, and [Navient] agrees to reimburse [BPG] on demand for any expenses including, without limitation, reasonable attorneys’ fees which [BPG] may incur in effecting such cure and [Navient] further agrees [BPG] shall not be liable for any damages resulting to [Navient] from such action.21
In a similar vein regarding legal fees, Section 28(q) states: “In the event of
any litigation between [BPG] and [Navient], the unsuccessful party as determined
by a court of competent jurisdiction shall reimburse the successful party for all legal
20 Id., Ex. E § II(3)(a). 21 Id. § 13(b)(vi). 7 fees and expenses incurred by the successful party in prosecuting or defending any
such action.”22
D. Maintenance at the Blue Wing of the Office Complex
Navient services student loans; in connection with that operation, Navient
operated a call center at the Blue Wing.23 At its peak, the Blue Wing housed between
600 and 700 Navient employees.24 Navient occupied all three floors of the Blue
Wing until it started to reduce operations there in 2017.25 Navient first vacated the
third floor; it then vacated the second floor.26 Navient fully vacated the Blue Wing
by the end of 2019, which gave Navient enough time to remove furniture and
equipment before the Lease Agreement terminated on February 29, 2020.27 BPG’s
counterclaim in this action relates to four areas of Blue Wing equipment and
maintenance: (1) a transformer, (2) heat pumps, (3) rooftop fresh air units, and (4)
elevators.
1. The Cooling Tower
Navient initiated this action and brought a claim for breach of the Lease
Agreement.28 Specifically, Navient replaced the cooling tower and its component
22 Id. § 28(q). 23 Trial Tr. II at 54-55 (Muffler). 24 Id. at 55 (Muffler). 25 PTO § 2(o). 26 Id. 27 See Trial Tr. II at 57 (Muffler); see also PTO § 2(x) (stipulating that the Lease term expired February 29, 2020). 28 Compl. ¶¶ 10-19. 8 parts between April and May 2019.29 The total unamortized cost of replacing the
cooling tower and its component parts was $503,822.72.30 The Lease Agreement
specified the cost of the replacement “shall be amortized over the useful life thereof
at a rate of eight (8%) per annum and [Navient] shall receive an amount from [BPG]
at the expiration or sooner termination of the Lease equal to the then-remaining
unamortized cost of such Replacement Item [i.e., the cooling tower].”31
On January 28, 2020, Navient demanded $503,822.72 from BPG for the then-
unamortized cost of the cooling tower replacement.32 The Lease Agreement states
BPG “shall be deemed to be in default of this Lease if [BPG] fails to make any
payments to [Navient] required under this Lease and such failure continues for ten
(10) days after written notice from [Navient] to [BPG].”33 The Lease Agreement
expired on February 29, 2020.34 On March 3, 2020, Navient provided written notice
that BPG was in default of its obligations under the Lease Agreement for failing to
reimburse Navient for the unamortized costs of the cooling tower replacement.35
BPG denied its obligation to reimburse the cooling tower costs until shortly before
trial, when BPG acknowledged it owed Navient that amount.36
29 PTO § 2(t). 30 Id. 31 JX 3 § 6(j)(i)-(ii). 32 PTO § 2(v); JX 32 at NAV0001526. 33 JX 3 § 14-A(a). 34 PTO § 2(x). 35 Id. § 2(y). 36 Id. § 2(u); see also JX 3 § 6(j)(i)-(ii). 9 2. Transformer
BPG’s first claim for costs relates to a transformer Navient replaced during
the Lease term. On October 13, 2014, a transformer blew; that transformer was
installed at the time the Blue Wing was constructed.37 Shortly thereafter, Navient
personnel contacted Ralph Rossi of BPG via email to notify him of the transformer
issue.38 Mr. Rossi responded and cited Lease Agreement Sections 6(j)(i)-(iii).39
Based on that contractual language, Mr. Rossi took the position that Navient was
responsible for the “repair/replacement [of the transformer] and the capital
replacement would be amortized over its useful life,” whereupon BPG would
reimburse Navient for the unamortized cost at the end of the Lease Agreement
term.40
The next day, Stephanie Yates from Navient emailed Mr. Rossi with a
“strategy proposed by Premium Power Services for setting the transformer in a
permanent solution.”41 The Premium Power strategy included replacement of the
transformer and adjustments to the concrete pad on which the transformer rested.42
Mr. Rossi responded that BPG was “OK with this plan” but needed further
37 JX 5; Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 8 (D.I. 58); Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 10-11. 38 JX 5. 39 Id. 40 Id. at NAV0002296. 41 JX 6; see also JX 7 (displaying a copy of the Premium Power plan). 42 JX 6. 10 assurances before signing off on it.43 These assurances included: (1) “[c]uts on the
transformer being installed”; (2) a letter from a Premium Power engineer that the
course of action “is to code and industry standard”; (3) a design by Premium Power
relating to the length of the feeders; and (4) a written plan that included when the
feeders would be replaced.44 Navient’s Paul Smith emailed Mr. Rossi and stated
Navient addressed all requirements; Mr. Smith asked for permission to proceed.45
There was further clarification that the concrete pad would need to be leveled at
some point.46 BPG’s general counsel advised Mr. Rossi that BPG would be required
to provide a report to BPG’s lender that detailed the work performed and ensured
the work complied with the Lease Agreement, namely that the work was undertaken
in a “Class A manner.”47 Mr. Rossi notified Navient of BPG’s general counsel’s
concerns and also told Navient that if the report showed additional recommendations
to bring the work to such a standard, Navient would be obligated to implement those
recommendations under the Lease Agreement’s terms.48 Mr. Rossi then told Navient
it was approved to move forward with the work.49
43 Id. 44 Id. 45 JX 8. 46 JX 12. 47 JX 8. 48 Id. 49 Id. 11 Later in the day on October 14, 2014, the blown transformer was replaced.50
The concrete pad on which the replacement transformer rested was fitted with metal
shims in an attempt to level the transformer in compliance with applicable code and
the transformer manufacturer’s installation instructions.51 The replacement
transformer had a larger capacity than the original but had a two-position switching
arrangement as opposed to the original four-position switch.52 On October 14, 2014,
Premium Power’s Jeff Donnelly emailed Mr. Rossi and stated the “transformer
needs to be level and sealed in order to operate properly. [Premium Power
recommends] leveling the transformer at a later date under normal circumstances.”53
On October 24, 2014, Premium Power issued an updated report. The original report
stated the transformer replacement was intended to be a “temporary” transformer,
but the updated report stated the replacement was intended to be a “replacement”
transformer.54
Navient paid $70,000 for the replacement transformer.55 The parties disputed
whether Navient or BPG was ultimately responsible for the cost of the replacement
transformer.56 Those discussions continued for three years, until October 13, 2017,
50 JX 12. 51 Trial Tr. II at 237-39 (Alderson). 52 Id. at 244 (Alderson). 53 JX 12. 54 JX 7; JX 9. 55 PTO § 2(j). 56 Id. § 2(k). 12 when Chris Buccini from BPG sent an email to Joseph Muffler from Navient and
stated “[a]s per our discussion on the phone, [BPG] will credit [Navient] $35k of
rent . . . towards reimbursement of the approx[imately] $70k transformer that
[Navient] replaced at [the Blue Wing] a few years ago.”57 Mr. Muffler accepted that
offer via email.58 Nevertheless, BPG claims it is entitled to $140,000 because
Navient did not meet its contractual obligation to install a four-position switch and
a permanent level concrete pad under the transformer.
3. Heat Pumps
The second group of items at issue in BPG’s counterclaim was the heat pumps
for the Blue Wing. After the Lease Agreement ended, BPG employed Edward
Levering and Keith Nelson, both from Air Management and Design LLC, to survey
approximately 123 heat pumps at the Blue Wing.59 Messrs. Levering and Nelson
were expert witnesses for BPG at trial.60 On June 18, 2020, after this case was filed,
Mr. Levering submitted his first heat pump evaluation; the evaluation recommended
that “all the systems that have passed their useful life . . . should be replaced.”61 Mr.
Levering based this “useful life” analysis on a handbook published by the American
Society of Heating, Refrigerating and Air-Conditioning Engineers (“ASHRAE”),
57 JX 24. 58 Id. 59 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 12; Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 23. 60 PTO § 6. 61 JX 39. 13 which contains a median life expectancy chart for building components at issue in
BPG’s counterclaim. The median life expectancy for “commercial water-to-air”
heat pumps is 19 years.62 On March 18, 2021, Mr. Levering submitted a more
detailed evaluation of the heat pumps.63 This evaluation provided an itemized list
of, inter alia, each heat pump, the repair cost, the replacement cost, and each pump’s
date of manufacture.64 Again, Mr. Levering recommended that any heat pump that
exceeded the 19-year median useful life should be replaced.65 Mr. Levering’s
calculation for the total cost of replacement was $405,800.66
Mr. Levering identified 25 of 123 heat pump units as non-operational at the
time of his evaluation.67 Mr. Levering stated 11 of the 25 non-operational heat pump
units were below their median life expectancy, and these 11 heat pumps should be
repaired (rather than replaced) at an estimated cost of $28,750.68 Mr. Levering stated
14 of the 25 non-operational heat pumps exceeded their median life expectancy and
should be replaced at a cost of $107,100.69 Additionally, Mr. Levering identified 38
heat pumps that—although operational—exceeded their median life expectancy, and
62 JX 49 at 12. 63 JX 48. 64 Id. 65 Id. 66 Id. 67 Trial Tr. I at 48-49 (Levering). 68 JX 48. 69 See id. It appears the repair cost for these 14 units would be $42,500. See id. 14 he proposed replacing these units based solely on the fact they all were more than
19 years old.70 The cost to replace these 38 units would be $298,600.71
Scott Frenck, an engineer and expert witness for BPG, testified he
recommended replacing, rather than repairing, any heat pump units that exceed the
ASHRAE median life expectancy.72 Mr. Frenck’s expert report and testimony were
grounded in Mr. Levering’s findings.73
Navient called its own expert, Howard Alderson, an engineer who testified
there was no reason to replace a heat pump based solely on its age.74 Mr. Alderson
testified the heat pumps at the Blue Wing as of 2021 were well maintained.75
Navient also called Joe Testerman; Mr. Testerman worked at the Blue Wing as a
Raven Services76 employee from January 2012 until the end of 2017, and Mr.
Testerman then performed the same work as an independent contractor for Navient
from January 2018 through the end of 2019.77 Mr. Testerman performed “repairable
70 See id. 71 See id. 72 Trial Tr. I at 103-04 (Frenck). 73 Id. 74 Trial Tr. II at 252 (Alderson). 75 Id. at 246-47 (Alderson). Mr. Alderson’s expert report opined the standard of care for the heat pump units was met by Navient. JX 65 at 13. 76 Raven Services (“Raven”) was a third-party maintenance and engineering company hired by Navient to maintain the Blue Wing. Trial Tr. II at 57-58 (Muffler); Id. at 136-38 (Outen). Raven performed systematic and regular maintenance on the HVAC systems, the cooling tower, and related components. Trial Tr. II at 57-58 (Muffler); Id. at 136-38 (Outen). Navient entered into service contracts with Raven and paid Raven approximately $250,000 for services through the end of 2017. JX 32 at NAV0001610-36. 77 Trial Tr. II at 145-47 (Outen); Id. at 187-88, 202-05 (Testerman). 15 maintenance” at the Blue Wing.78 Mr. Testerman testified that when he left the Blue
Wing in 2019, all HVAC systems were operating.79
Additionally, Navient called Clay Outen as a witness. Mr. Outen has been a
director of facility operations for Navient in Delaware since 2015. 80 Mr. Outen
testified Raven was responsible for facility maintenance at the Blue Wing.81 Mr.
Outen confirmed Raven inspected and replaced heat pump units.82 Mr. Outen
testified 18 to 20 heat pump units were replaced during the time he was responsible
for the Blue Wing.83 Mr. Outen also testified four or five new heat pump units were
left at the Blue Wing as extra stock when the Lease Agreement expired.84
4. Rooftop Air Units
BPG’s counterclaim also included costs related to rooftop air units. The Blue
Wing has two “Dectron rooftop makeup air units.”85 These rooftop air units provide
makeup air for the Blue Wing, but BPG’s inspection showed the units were not
operational when Navient left the Blue Wing because the controls never were
programmed for the new controllers installed on the rooftop air units.86 The rooftop
78 Id. at 189 (Testerman). 79 Id. at 221-22 (Testerman). 80 Id. at 131-33 (Outen). 81 Id. at 136 (Outen). 82 Id. at 137 (Outen). 83 Id. at 142 (Outen). 84 Id. at 143 (Outen). 85 Trial Tr. I at 63 (Nelson). 86 Id. at 75 (Nelson). 16 air units were installed around 2000.87 The ASHRAE median life expectancy of
rooftop air units is 15 years.88
Mr. Frenck, BPG’s witness, testified the rooftop air units should have been
replaced based solely on the fact the units exceeded their median life expectancy.89
Mr. Frenck, however, conceded these rooftop air units could be repaired rather than
replaced.90 Mr. Frenck’s expert report indicated these rooftop air units were “in
average condition with some repairs needed.”91 Mr. Levering and Mr. Nelson also
testified these rooftop air units could be repaired rather than replaced.92 Mr. Frenck’s
estimated cost to repair both rooftop air units totaled $8,400,93 while BPG’s
estimated cost to replace the rooftop air units is between $217,200 and $240,000.94
5. Elevators
Finally, BPG counterclaimed for costs associated with the Blue Wing
elevators. Exhibit H to the Lease Agreement confirms the Blue Wing’s second floor
corridor, “together with the stairwell and elevator at the end of such corridor
providing service to the garage facility . . . is considered part of the Premises for the
87 Id. at 117 (Frenck); JX 49 at 6. 88 JX 49 at App. A. 89 Trial Tr. I at 115-16 (Frenck). 90 Id. 91 JX 49 at 6. 92 Trial Tr. I at 41 (Levering); Id. at 95 (Nelson). 93 JX 49 at App. B. 94 JX 43; JX 48. 17 purposes of this Lease [Agreement].”95 The elevator systems at the Blue Wing were
manufactured and installed in 1990.96
Mark DeCocinis, a senior associate at VDA Elevator and Escalator Consulting
and expert witness for BPG, prepared an expert report after the elevators at the Blue
Wing were surveyed in March 2021.97 Mr. DeCocinis testified, consistent with his
report, that the elevators should be modernized within three years of the date of his
report.98 In other words, Mr. DeCocinis recommended the elevators undergo
modernization by March 2024.99 Mr. DeCocinis did not recommend upgrades in
2021 because, in his view, piecemeal upgrades were not an optimal plan for
elevators.100 Mr. DeCocinis found the “operating performance” of the existing
elevators to be “fair,” and he further stated “some adjustments and improvements
[were] required.”101
Navient contracted with ThyssenKrupp Elevator Corporation to maintain the
elevators at the Blue Wing during the lease.102 Under the contract between Navient
and ThyssenKrupp in existence when the Lease Agreement expired, ThyssenKrupp
performed “regular preventative maintenance, full coverage of parts and repair and
95 JX 3, Ex. H § 15(a). 96 JX 50. 97 See id. 98 Trial Tr. II at 43 (DeCocinis). 99 Id. 100 Id. at 43-44 (DeCocinis). 101 JX 50; Trial Tr. II at 41-43 (DeCocinis). 102 JX 32 at NAV0001665; Trial Tr. II at 59 (Muffler). 18 replacement . . . , [and] quality assurance.”103 Jeff Wilmington of Navient testified
Navient paid ThyssenKrupp for its services through the end of the Lease.104 Mr.
Wilmington testified Navient received the last certificate of compliance for the
elevators in June 2019; that certificate was valid for one year.105
Between June 9 and 10, 2015, ThyssenKrupp submitted three work orders to
Navient related to controller boards, door edges, and a solid state starter. 106 BPG
complains there is no proof Navient paid for any of these three work orders.107 None
of those items, however, forms the basis of BPG’s counterclaim relating to the
elevators. Instead, BPG alleges that in September 2020 it had to repair a bracket in
one elevator for $3,345.108
E. Litigation
Navient sued BPG in April 2020.109 Navient’s sole cause of action alleged
BPG breached the Lease Agreement by failing to reimburse Navient for the
unamortized cost of replacing the cooling tower.110 Navient sought $503,822.72,
103 Trial Tr. II at 101 (Wilmington). 104 Id. at 102 (Wilmington). 105 Id. at 102-03 (Wilmington). 106 JX 32 at NAV0001671-76. 107 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 58. Navient disputes this allegation and directs the Court to JX 62. Navient argues JX 62 establishes the “proposal for the control boards was accepted and paid by Navient.” Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 21; see also JX 62. 108 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 58; JX 46 (displaying copy for elevator repair service proposal with a payment of $3,345). 109 D.I. 1. 110 See Compl. ¶ 21. 19 which the parties agree was the unamortized cost of the tower when the Lease
expired.111 BPG answered and asserted a counterclaim and affirmative defenses.112
BPG’s counterclaim alleged Navient breached the Lease Agreement by failing to:
(1) maintain, repair, and/or replace heat pump units; (2) maintain, repair, and/or
replace the rooftop air units; (3) properly replace the blown transformer and install
a permanent pad to level the transformer; and (4) maintain and repair the elevators.113
BPG requested $817,845 from Navient.114 Navient asserted affirmative defenses to
the counterclaim.115
Before trial, BPG agreed Navient is owed $503,822.72 for the replacement of
the cooling tower.116 BPG continued, however, to maintain its counterclaim.117
F. Procedural History and Parties’ Contentions
The Court held a three-day bench trial that began on May 9, 2022.118 The trial
was limited in scope to BPG’s counterclaim. After trial, the parties filed post-trial
briefs addressing the merits of BPG’s counterclaim.119 The Court held post-trial oral
111 See id. Navient also requested attorneys’ fees, expenses, collection costs, pre- and post- judgment interest, and Court costs. Id. 112 Answer & Countercl. (D.I. 6). 113 Id. 114 Id.; Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 61. BPG also requests pre- and post- judgment interest, attorneys’ fees, and other costs. See Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 61. 115 Answer to Countercl. (D.I. 8). 116 PTO § 2(z). 117 Id. 118 See Trial Trs. (D.I. 53-55). 119 See D.I. 57-60. 20 argument on February 10, 2023.120 This Post-Trial Memorandum Opinion addresses
BPG’s counterclaim, which is the only remaining substantive issue in the case.
1. BPG’s Contentions
The parties’ post-trial briefs set forth their arguments regarding BPG’s breach
of contract counterclaim. BPG contends the Court should enter judgment in its favor
in the amount of $817,845, itemized as: (1) $434,500 for heat pumps, (2) $240,000
for rooftop air units, (3) $140,000 for the transformer and pad, and (4) $3,345 for
the elevators.121 BPG also contends it is entitled to pre- and post-judgment interest,
attorneys’ fees, and other costs.122
BPG contends the evidence at trial demonstrated Navient breached the Lease
Agreement in four ways. First, BPG maintains Navient breached the Lease
Agreement by failing to maintain, repair, and/or replace heat pumps at the Blue
Wing.123 Specifically, BPG asserts the evidence demonstrated BPG is entitled to:
(1) $28,750 to repair 11 non-operational heat pumps that had not exceeded their
median life expectancy; (2) $107,100 to replace 14 non-operational heat pumps that
exceeded their median life expectancy; and (3) $298,600 to replace 38 heat pumps
that were operational but exceeded their median life expectancy.124 Second, BPG
120 D.I. 62. 121 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 61. 122 Id. 123 See id. at 32. 124 Id. 21 maintains Navient breached the Lease Agreement by failing to maintain, repair,
and/or replace two rooftop air units.125 Specifically, BPG asserts it is entitled to
$240,000 to repair or replace the rooftop air units because Navient did not properly
maintain and modernize them during the Lease period.126 Third, BPG contends
Navient breached the Lease Agreement by replacing the Blue Wing’s transformer
with a “2-position switch rather than a 4-position switch” and by installing
“makeshift metal to keep the [transformer] unit level on the [supporting] pad.”127
BPG asserts it is entitled to $140,000 because Navient installed an improper
transformer.128 Fourth, BPG contends Navient breached the Lease Agreement by
failing to maintain and repair the elevators at the Blue Wing.129 BPG asserts it is
entitled to $3,345 because BPG had to repair a bracket associated with an elevator
that was Navient’s responsibility under the Lease Agreement.130
BPG additionally contends it is entitled to fee shifting because it is the
“successful party” in this action and therefore is entitled to reimbursement of its legal
fees and expenses under Lease Agreement Section 28(q).131
125 Id. at 44. 126 Id. at 45-47. 127 Id. at 49. 128 Id. at 56, 61. 129 Id. at 57. 130 Id. at 58. 131 Id. at 59-60. BPG also argues Navient is not entitled to recoupment under the Lease Agreement if BPG is successful on its counterclaim, which Navient sets forward as an affirmative defense. See Defs.’/Countercl. Pls.’ Post-Trial Reply Br. at 24 (D.I. 59). 22 2. Navient’s Contentions
It is now undisputed that Navient is entitled to $503,822.72 for the
unamortized cost incurred when it replaced the cooling tower at the Blue Wing.132
What remains in dispute is whether that amount should be set-off, in whole or in
part, by BPG’s counterclaim. Navient contends BPG did not prove either liability
or damages with respect to its counterclaim. First, Navient maintains BPG failed to
establish Navient breached the Lease Agreement with respect to the heat pumps.133
Specifically, Navient contends the evidence at trial demonstrated Navient fulfilled
all maintenance and repair obligations with respect to the heat pumps.134 Navient
further argues Mr. Alderson’s testimony established there was no way to show
Navient caused the deficiencies in the non-operational heat pumps.135 And Navient
maintains Mr. Levering’s testimony regarding replacing heat pumps when they
exceeded their median life expectancy was disputed by Mr. Frenck’s testimony to
the contrary.136 Second, Navient asserts BPG failed to establish Navient breached
the Lease Agreement with respect to the rooftop air units because BPG’s claim was
premised entirely on its contention that the units required replacement once they
132 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 34. Navient inadvertently refers to the sum as $503,922.72, but it is clear from Navient’s briefing that it seeks $503,822.72. See, e.g., id. at 1, 3, 33 (noting Navient seeks the sum demanded in the Complaint, which is $503,822.72). 133 Id. at 26. 134 Id. at 27, 29. 135 Id. at 28. 136 Id. at 29. 23 passed their median life expectancy, even though BPG’s experts admitted the units
could be repaired, rather than replaced.137
Third, Navient contends BPG did not prove Navient breached the Lease
Agreement with respect to the transformer. Navient claims the evidence shows:
BPG was notified immediately when the transformer blew; BPG was involved in the
process and strategy to find a replacement transformer; BPG approved Premium
Power’s plan to install a replacement, which included construction of fabricated
metal shims to level the transformer; and BPG offered no evidence that the
transformer is not operating properly.138 Navient alternatively argues BPG’s
counterclaim relating to the transformer is barred by Delaware’s three-year statute
of limitations because BPG knew about the replacement transformer in October
2014.139 Fourth, Navient contends BPG offered no evidence that any defect relating
to the bracket in the elevator occurred during Navient’s occupancy or that Navient’s
alleged lack of maintenance caused the need to repair that bracket.140
Navient additionally argues that if BPG is successful on its counterclaim,
“Navient shall receive a reimbursement of those costs from BPG as the landlord
calculated as ‘then remaining unamortized cost’ of the replacement item.”141 Like
137 Id. at 29-30. 138 Id. at 24-25. 139 Id. at 26. 140 Id. at 30. 141 Pl.’s/Countercl. Def.’s Post-Trial Sur-Reply Br. at 3 (D.I. 60); see also Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 31-32. 24 BPG, Navient also contends it is entitled to fee shifting under the Lease Agreement.
Navient argues it is the successful party in this action because: (1) it was successful
on its claim relating to the unamortized cost for the cooling tower replacement, and
(2) BPG is unsuccessful on its counterclaim.142 Navient further contends that even
if BPG partially succeeds on its counterclaim, Navient remains the successful party
because it “prevailed on the predominance of all of the issues.”143
II. ANALYSIS
With those factual findings and the parties’ contentions in mind, the Court
turns to resolving the ultimate claims in this case. Each party bears the burden of
proving their respective claims and defenses by a preponderance of the evidence.144
A. Navient prevails on its claim to recover the unamortized costs of the cooling tower.
Navient initiated this action and brought a claim for breach of the Lease
Agreement.145 Specifically, Navient replaced the cooling tower and its component
parts between April and May 2019.146 When the Lease expired, the remaining
unamortized cost of replacing the cooling tower and its component parts was
142 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 32-33. 143 Id. at 33. 144 See, e.g., Reynolds v. Reynolds, 237 A.2d 708, 711 (Del. 1967) (defining the preponderance of the evidence standard); see also Oberly v. Howard Hughes Med. Inst., 472 A.2d 366, 390 (Del. Ch. 1984), abrogated on other grounds, Staats by Staats v. Lawrence, 576 A.2d 663, 666-67 (Del. Super. 1990). 145 Compl. ¶¶ 10-19. 146 PTO § 2(t). 25 $503,822.72.147 Pursuant to Sections 6(j)(i)-(ii) of the Lease Agreement, BPG
agreed to reimburse Navient for replacing “Building Systems,” which included the
cooling tower.148 The Lease Agreement specified the cost of the replacement “shall
be amortized over the useful life thereof at a rate of eight (8%) per annum and
[Navient] shall receive an amount from [BPG] at the expiration or sooner
termination of the Lease equal to the then-remaining unamortized cost of such
Replacement Item [i.e., the cooling tower].”149
On January 28, 2020, Navient notified BPG of Navient’s request for the
amount of $503,822.72 for the then-unamortized cost of the cooling tower
replacement.150 The Lease Agreement states BPG “shall be deemed to be in default
of this Lease if [BPG] fails to make any payments to [Navient] required under this
Lease and such failure continues for ten (10) days after written notice from [Navient]
to [BPG].”151 The Lease Agreement expired on February 29, 2020.152 On March 3,
2020, Navient provided written notice to BPG that it was in default of its obligations
under the Lease Agreement for failing to reimburse Navient for the unamortized cost
147 Id. 148 Id. § 2(u); see also JX 3 § 6(j)(i)-(ii). 149 JX 3 § 6(j)(i)-(ii). 150 PTO § 2(v); JX 32 at NAV0001526. 151 JX 3 § 14-A(a). 152 PTO § 2(x). 26 of the cooling tower replacement.153 BPG concedes Navient is owed $503,822.72
for the replacement of the cooling tower and its component parts.154
Navient therefore is entitled to judgment in its favor on its claim for the
unamortized cost for the cooling tower replacement plus prejudgment interest,
accruing as of March 17, 2020, which is ten business days after Navient sent BPG
notice of default.155
B. BPG’s claim relating to the transformer is barred by the statute of limitations. The original transformer at the Blue Wing blew in October 2014. 156 On
October 14, 2014, after discussions and approval by BPG, Navient replaced the
transformer and fitted the concrete pad on which the transformer rests with metal
shims in an attempt to level the transformer.157 The replacement transformer was
originally marked as a “temporary” transformer, but the contractor, Premium Power,
later issued an updated report stating the transformer was a “replacement”
153 Id. § 2(y). 154 Id. § 2(z). 155 See Delta Eta Corp. v. Univ. of Delaware, 2010 WL 2949632, at *2 (Del. July 29, 2010) (“‘The general rule [in a breach of contract action] is that interest starts on the date when payment should have been made.’” (quoting Metro. Mut. Fire Ins. Co. v. Carmen Hldg. Co., 220 A.2d 778, 782 (Del. 1966)); Balooshi v. GVP Global Corp., 2022 WL 576819, at *14 (Del. Super. Feb. 25, 2022) (“In contract actions, pre-judgment interest is computed from the date of the breach.” (citing Citadel Hldg. Corp. v. Roven, 603 A.2d 818, 826 (Del. 1992)). 156 JX 5; Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 8; Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 10-11. 157 JX 12; Trial Tr. II at 237-40 (Alderson). 27 transformer.158 Navient paid $70,000 for the replacement transformer, but later
received rent credit for half that amount.159
BPG contends Navient breached the Lease Agreement by installing a 2-
position switch transformer (as opposed to the existing 4-position or multiple 2-
position) and by installing a makeshift metal support (as opposed to a permanent
level concrete pad).160 BPG claims it suffered $140,000 in damages as a result of
Navient’s transformer replacement.161 Navient responds that BPG failed to establish
by a preponderance of the evidence that Navient breached the Lease Agreement with
respect to the transformer.162 Navient alternatively argues that BPG’s counterclaim
relating to the transformer is barred by Delaware’s three-year statute of limitations
because BPG knew about the replacement transformer in October 2014.163
There is a three-year statute of limitations for breach of contract claims in
Delaware.164 Generally, a breach of contract claim must be brought within three
years “from the date that the cause of action accrued.”165 Breach of contract claims
158 JX 7; JX 9. 159 PTO § 2(j). 160 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 56. 161 Id. at 61. 162 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 24-25. 163 Id. at 26. 164 10 Del. C. § 8106 (2023). 165 Levy v. Brownstone Asset Mgmt., LP, 76 A.3d 764, 768 (Del. 2013) (citation omitted). 28 accrue “as soon as the breach occurs, even if the aggrieved plaintiff is ignorant of
the breach.”166
Even assuming a breach occurred, BPG’s claim for the transformer is barred
by Delaware’s three-year statute of limitations. The record reflects BPG was aware
of Navient’s detailed plans to replace the transformer and level its concrete pad no
later than October 14, 2014.167 BPG received Premium Power’s plan for
replacement, and BPG stated Navient was “approved to move forward with [its]
work.”168 Accordingly, BPG was required to bring this claim no later than October
14, 2017.169 BPG did not assert this claim until June 26, 2020, when it filed its
Answer and Counterclaim.170 BPG’s claim relating to the transformer therefore is
time-barred.
166 Intermec IP Corp. v. TransCore, LP, 2021 WL 3620435, at *21 (Del. Super. Aug. 16, 2021) (citing Wal-Mart Stores, Inc. v. AIG Life Ins. Co., 860 A.2d 312, 319 (Del. 2004)). 167 See JX 5 (s email chain between Navient and BPG on October 13, 2014, explaining that the transformer at the Blue Wing needed to be replaced); JX 6 (email chain between Navient and BPG discussing Premium Power’s plan to replace the transformer); JX 8 (October 14, 2014 email from Mr. Rossi of BPG to Navient stating Navient was “approved to move forward with their work”). 168 JX 6; JX 8. 169 See 10 Del. C. § 8106 (“[N]o action based on a promise . . . shall be brought after the expiration of 3 years from the accruing of the cause of such action.”); Cont’l Fin. Co., LLC v. ICS Corp., 2020 WL 836608, at *4 (Del. Super. Feb. 20, 2020) (“Generally, the statute of limitations ‘begins to run when a plaintiff’s claim accrues[,] which occurs at the moment of the wrongful act and not when the effects of the act are felt even if the plaintiff is ignorant of the cause of action.’” (alteration in original) (quoting Silverstein v. Fischer, 2016 WL 3020858, at *4 (Del. Super. May 18, 2016)). 170 See Answer & Countercl. 29 BPG argues its claim for the transformer did not accrue until the Lease term
ended.171 BPG, however, offers neither textual nor caselaw support for this
argument. BPG’s cause of action accrued at the time the transformer blew, or at
least when the Premium Power plan was implemented,172 both of which occurred
more than five years before BPG filed its counterclaim.
C. BPG is entitled to the repair costs for the 25 non-operational heat pumps. After the Lease ended, BPG employed Messrs. Levering and Nelson to survey
the approximately 123 heat pumps in the Blue Wing.173 Mr. Levering identified 25
heat pumps that were non-operational.174 Of those 25, 11 pumps were below median
life expectancy, and Mr. Levering testified they could be repaired at an estimated
total cost of $28,750.175 Fourteen of the 25 non-operational heat pumps exceeded
their median life expectancy, and Mr. Levering opined they should be replaced at an
estimated cost of $107,100.176
BPG contends Navient breached the Lease Agreement by failing to maintain,
repair, and/or replace heat pumps at the Blue Wing. BPG asserts the evidence
171 See Defs.’/Countercl. Pls.’ Post-Trial Reply Br. at 20-21. 172 See Intermec IP Corp., 2021 WL 3620435, at *21 (“[T]he statute [of limitations in a contract action] is triggered as soon as the breach occurs, even if the aggrieved [party] is ignorant of the breach.” (citing Wal-Mart Stores, Inc., 860 A.2d at 319). 173 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 12; Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 23. 174 Trial. Tr. I at 48-49 (Levering). 175 JX 48. 176 Id. It appears the repair cost for these 14 units would be $42,500. See id. 30 demonstrated BPG is entitled to: (1) $28,750 to repair 11 non-operational heat
pumps that had not exceeded their median life expectancy; (2) $107,100 to replace
14 non-operational heat pumps that had exceeded their median life expectancy; and
(3) $298,600 to replace 38 heat pumps that were operational but had exceeded their
median life expectancy.177 Navient counters that BPG failed to establish Navient
breached the Lease Agreement with respect to the heat pumps. Navient contends
the evidence shows Navient maintained and repaired the heat pumps in accordance
with the terms of the Lease Agreement.178 Navient argues BPG did not show
Navient caused any deficiencies in the heat pumps such that Navient is responsible
for any costs associated with the units.179
To prove Navient breached the Lease Agreement with respect to the heat
pumps, BPG must demonstrate (1) the existence of a valid contract, (2) breach of an
obligation imposed by that contract, and (3) resulting damages.180 The parties do
not dispute the Lease Agreement is a valid contract. Section 6(j)(i) established
Navient’s obligations with respect to “Building Systems exclusively serving the
Building.”181 Navient admits the heat pumps fall within the language of Section
177 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 32. 178 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 27. 179 Id. at 28. 180 McCoy v. Cox, 2007 WL 1677536, at *1 (Del. Super. June 11, 2007) (citing VLIW Tech., LLC v. Hewlett-Packard Co., 840 A.2d 606, 612 (Del. 2003)). 181 JX 3 § 6(j)(i). 31 6(j)(i).182 Section 6(j)(i) required Navient, at its “sole cost and expense, to maintain,
repair and replace all Building Systems exclusively serving the Building in good
order and repair.”183
The Court here focuses on the 25 heat pumps that Mr. Levering found to be
non-operational. Of those, Mr. Levering opined the 11 that were within their life
expectancy could be repaired for $28,750.184 Mr. Levering also found 14 of the 25
non-operational heat pumps exceeded their median life expectancy and should be
replaced for $107,100.185 Mr. Levering testified these 14 heat pumps could be
repaired for $42,500, but Mr. Levering stated repairing these 14 heat pumps could
be difficult because the units are “obsolete [and] parts are hard to get.”186
Navient asserts it is not responsible for any repair or replacement costs
because Mr. Alderson testified there was no way to establish whether any of the
repairs were the consequence of issues that arose when Navient was the tenant.187
This argument is not persuasive. Mr. Levering initially reported on the heat pumps
on June 18, 2020,188 approximately three-and-a-half months after the Lease ended.
Mr. Levering’s invoices to BPG indicate he surveyed the heat pumps during
182 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 31-32. 183 JX 3 § 6(j)(i). 184 JX 48; Trial Tr. I at 47 (Levering). 185 JX 48; Trial Tr. I at 19 (Levering). 186 Trial Tr. I at 19-20 (Levering). 187 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 28. 188 JX 39. 32 February and March 2020.189 To the extent Navient argues the need for repairs
occurred after the Lease ended, the evidence shows otherwise. Further, the Lease
Agreement required Navient to “maintain, repair and replace” any heat pumps that
required maintenance,190 and Navient accepted the Blue Wing “in ‘as-is’ condition
and configuration without any representations or warranties by” BPG.191 The Lease
therefore required Navient to “maintain, repair and replace” any heat pumps that
needed maintenance regardless of whether the need arose before the Lease started.
Accordingly, Navient breached the Lease with respect to the non-operational heat
pumps.
BPG therefore is entitled to the cost of repair for the 11 non-operational units
that had not exceeded their median life expectancy. Additionally, with respect to
the 14 non-operational heat pumps that exceeded their life expectancy, BPG is
entitled to the cost to repair those 14 units. BPG did not establish the 14 heat pumps
need to be replaced rather than repaired. To the contrary, nothing in the language of
the Lease Agreement required Navient to replace, rather than repair, systems based
on their median life expectancy. Rather, the Lease referred broadly to Navient’s
obligation to “maintain, repair and replace all Building Systems exclusively serving
189 See JX 40. 190 JX 3 § 6(j)(i). 191 Id. § 4. 33 the Building in good order and repair.”192 This language gave Navient discretion
to determine whether a system should be repaired or replaced, limited only by the
requirement that the systems remain in “good order and repair.” If BPG wanted to
impose a particular industry standard on Navient’s obligation to keep systems “in
good order and repair,” it could have drafted language to that effect. A reasonable
tenant would elect to repair the 14 units for a cost close to one-third (1/3) the
replacement cost.
For the same reason, BPG failed to establish Navient breached the Lease with
respect to the 38 heat pumps that were operational but beyond their median life
expectancy.193 Mr. Levering recommended replacing these 38 heat pumps solely
because they exceeded their median life expectancy.194 The Court does not find this
recommendation persuasive. Mr. Frenck, BPG’s witness, testified that he would not
recommend replacing a heat pump solely because it exceeded its median life
expectancy.195 Mr. Alderson, Navient’s witness, provided similar testimony.196
BPG did not establish heat pumps that exceeded their median life expectancy but
otherwise were operational had to be replaced under either the terms of the Lease
Agreement or the parties’ course of performance.
192 Id. § 6(j)(i) (emphasis added). 193 See JX 48; Trial Tr. I at 50 (Levering). 194 JX 48; Trial Tr. I at 50 (Levering). 195 Trial Tr. I at 113 (Frenck). 196 Trial Tr. II at 252 (Alderson). 34 D. BPG is entitled to recover the repair costs for the rooftop air units.
The Blue Wing had two rooftop air units.197 These units were installed in
2000, and they had an ASHRAE median life expectancy of 15 years.198 The
evidence at trial showed the units were not operational when Navient’s Lease ended
because the controls never were programmed for new controls installed on those
units.199 It appears from the record that the first evaluation of the rooftop air units
occurred on July 15, 2020.200 Mr. Frenck testified the rooftop air units should be
replaced solely because they exceeded their median life expectancy,201 but he also
conceded the units could be repaired instead, as did Mr. Levering and Mr. Nelson.202
Mr. Frenck estimated the total cost to repair both rooftop air units is $8,400.203 The
estimated cost of replacing both units was between $217,200 and $240,000.204
BPG’s claim with respect to the rooftop air units requires the Court to
determine whether Navient breached the Lease Agreement, and, if so, whether BPG
197 See Trial Tr. I at 63 (Nelson). 198 JX 49; Trial Tr. I at 117 (Frenck). 199 Trial Tr. I at 75 (Nelson). 200 See JX 43. 201 Trial Tr. I at 115-16 (Frenck). 202 Id.; Id. at 41 (Levering); Id. at 95 (Nelson). 203 JX 49 at App. B (showing the cost to repair one unit is $2,600, and the cost to repair the other unit is $5,800); see also Trial Tr. I at 41 (Levering) (noting that Appendix B to JX 49 covers the repair costs for, inter alia, the rooftop air units). Mr. Frenck authored the HVAC Building Assessment numbered as JX 49. See Trial Tr. I at 102 (Frenck). 204 JX 43 (noting in Mr. Nelson’s report that the cost to replace the two rooftop air units is $217,200); JX 48 (noting in Messrs. Levering and Nelson’s report that the replacement cost is “$240,000.00 for both units”). 35 suffered damages.205 Navient admits the rooftop air units fall within the language of
Section 6(j)(i),206 which required Navient, at its “sole cost and expense, to maintain,
repair and replace all Building Systems exclusively serving the Building in good
order and repair.”207 Mr. Frenck testified the rooftop units were “in average
condition with some repairs needed” at the time of his inspection.208 Messrs. Nelson
and Levering both testified the rooftop air units did not need to be replaced but
instead could be repaired.209 The Court finds Navient breached the Lease Agreement
by failing to maintain the rooftop air units in compliance with the standards set forth
in Section 6(j)(i). The Court additionally finds BPG did not establish the rooftop air
units need to be replaced; rather, the evidence establishes these rooftop air units
could be repaired. BPG therefore is entitled to the cost of repair set forth in Mr.
Frenck’s expert report, which is $8,400.210
E. BPG is not entitled to any repair or replacement costs relating to the Blue Wing elevators.
The Blue Wing’s elevator systems are comprised of two passenger elevators
and one freight elevator, all of which were installed in 1990.211 Navient employed
205 Cox, 2007 WL 1677536, at *1 (citing VLIW Tech., 840 A.2d at 612). 206 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 31-32. 207 JX 3 § 6(j)(i). 208 Trial Tr. I at 118 (Frenck); JX 49 at 6. 209 Trial Tr. I at 41 (Levering); Id. at 95 (Nelson). 210 JX 49 at App. B. 211 JX 50. 36 ThyssenKrupp to maintain the elevators at the Blue Wing.212 ThyssenKrupp
performed regular preventative maintenance.213 Mr. Wilmington of Navient testified
that the last certificate of compliance for the elevators was issued in June 2019, and
that certificate was valid for one year.214 BPG emphasized at trial that ThyssenKrupp
submitted three work orders to Navient in June 2015 for controller boards, door
edges, and a solid state starter.215 BPG asserts there is no evidence Navient paid
these invoices.216 But that is not BPG’s claim for breach relating to the elevators;
rather, BPG asserts that in September 2020 it had to repair a bracket in one elevator
for $3,345.217
The Lease Agreement required Navient to maintain the elevators at the Blue
Wing. The Court therefore must determine whether BPG proved the bracket needed
repair at the time the Lease ended. BPG has not established any lack of maintenance
by Navient caused the need for the bracket repair. To prevail on its breach of
contract claim, BPG had to prove Navient breached the Lease Agreement and the
“breach caused the loss.”218 Stated differently, BPG did not prove by a
preponderance of the evidence that the need to repair the bracket arose at or before
212 JX 32 at NAV0001665; Trial Tr. II at 59 (Muffler). 213 Trial Tr. II at 101 (Wilmington). 214 Id. at 102-03 (Wilmington). 215 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 57-58. 216 Id. at 58. 217 Id.; JX 46. 218 LaPoint v. AmerisourceBergen Corp., 2007 WL 1309398, at *7 (Del. Ch. May 1, 2007) (quoting Tanner v. Exxon Corp., 1981 WL 191389, at *2 (Del. Super. July 23, 1981)). 37 the time the Lease ended. Indeed, the weight of the evidence is to the contrary.
Navient employed ThyssenKrupp to conduct “regular preventative maintenance, full
coverage of parts and repair and replacement . . . , [and] quality assurance.” 219 Mr.
Wilmington testified Navient paid ThyssenKrupp for its services through the end of
the Lease term.220 And Mr. Wilmington testified Navient received a certificate of
compliance from New Castle County for the Blue Wing elevators in June 2019,
which was valid for one year.221 There is no apparent link between the June 2015
work orders and the September 2020 bracket repair. Further, Mr. DeCocinis’s
testimony does not change the outcome. Mr. DeCocinis, BPG’s expert, testified the
elevators should undergo modernization by March 2024, but that the operating
performance of the elevators was “fair.”222 Nothing in the Lease Agreement required
Navient to modernize or upgrade building systems that were otherwise operational.
BPG therefore has failed to carry its burden to prove it is entitled to $3,345
for the elevator bracket repair.
219 Trial Tr. II at 101 (Wilmington). 220 Id. at 102 (Wilmington). Navient also disputes BPG’s allegation that Navient did not pay the June 2015 invoices. See Pl.’s/Countercl. Def.’s Answering Br. at 21 (directing the Court to JX 62 and stating Navient paid for the control board issue). 221 Trial Tr. II at 102-03 (Wilmington). 222 Id. at 41-43 (DeCocinis); JX 50. 38 F. Navient’s Recoupment Affirmative Defense fails under the Lease Agreement’s plain language. Navient contends that for any portion of BPG’s counterclaim on which BPG
is successful, Navient is entitled to recoupment of BPG’s award under the terms of
the Lease Agreement.223 Based on the Court’s above findings, that means Navient
believes it is entitled to recoupment for the repair costs of the heat pumps and rooftop
air units.224 Navient essentially maintains that even if, as required by the Lease
Agreement, Navient paid to repair the non-operational heat pumps and the two
rooftop air units, Navient would be entitled to have BPG reimburse (as an
Unamortized Reimbursement) Navient for that cost up to $300,000. As Navient puts
it, “[a]ny judgment [for BPG] less than $300,000 would be essentially null.”225
Section 6(j)(i) states in pertinent part:
In the event all or any portion of the Building Systems exclusively serving the Building requires replacement during the Term, [Navient] shall undertake the same at its sole cost and expense, and such replacement shall be accomplished, in a Class-A manner, using materials and equipment consistent with that found in comparable office buildings in the Wilmington, Delaware metropolitan area. However, notwithstanding the foregoing . . . , if (1) the portion of the Building Systems being replaced (the “Replacement Item”) has a useful life extending beyond the Lease Term . . . , and (2) the cost of such Replacement Item would otherwise constitute a capital repair or replacement cost [if] such items were purchased by or on behalf of [BPG], then the cost of such Replacement Item shall be amortized over
223 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 31-32. 224 The Court found BPG is entitled to repair costs on certain heat pumps and the rooftop air units. Navient notes that both the heat pumps and rooftop air units fall within Section 6(j)(i). See Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 31. 225 Id. at 32. 39 the useful life thereof at a rate of eight percent (8%) per annum, and [Navient] shall receive an amount from [BPG] at the expiration or sooner termination of the Lease equal to the then-remaining unamortized cost of such Replacement Item (the “Unamortized Reimbursement”).226 Section 6(j)(ii) caps the “Unamortized Reimbursement” at $300,000 for “Building
Systems” other than the cooling tower.227
Navient raised “setoff and/or recoupment” as its Eighth Affirmative
Defense.228 Navient only argued recoupment in its post-trial briefing.229 “Setoff and
recoupment are related but different defenses.”230 Setoff is a defense “by which the
defendant acknowledges the justice of the plaintiff’s demand, but sets up a defense
of his own against the plaintiff, to counterbalance it either in whole or in part.”231
Recoupment “is a species of defense somewhat analogous to [setoff] . . . but the
defense of recoupment goes to the reduction of the plaintiff’s damages for the reason
that [plaintiff] has not complied with the cross obligations arising under the same
contract.”232
226 JX 3 § 6(j)(i). 227 Id. § 6(j)(ii). 228 Answer to Countercl. at 4. 229 See Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 31-32; Pl.’s/Countercl. Def.’s Post-Trial Sur-Reply Br. at 4-5. 230 Finger Lakes Cap. P’rs, LLC v. Honeoye Lake Acquisition, LLC, 151 A.3d 450, 453 (Del. 2016). 231 Id. (internal quotation marks and citation omitted). 232 Id. (internal quotation marks and citation omitted). 40 The Court finds Navient failed to carry its burden to prove by a preponderance
of the evidence that it is entitled to recoupment. First, the relevant Lease terms refer
only to Navient’s right to be reimbursed for the unamortized cost of a “Replacement
Item.” The Court has not found that Navient was required to replace any Building
System, only that it was required to repair certain systems. Second, even if Section
6(j)(i) applied to repair costs, Navient did not elicit testimony regarding the amount
of unamortized costs to which Navient believes it is entitled for the heat pumps and
the rooftop air units. In its post-trial briefing, Navient points only to Mr. Alderson’s
expert report.233 Mr. Alderson’s report contains his opinions as to what BPG owes
Navient under the Lease Agreement for various costs regarding the heat pumps and
rooftop air units.234 This evidence is probative of Navient’s contention, but it is not
enough. The Court does not find Mr. Alderson’s report sufficient for Navient to
carry its burden regarding the unamortized repair costs. Navient therefore is not
entitled to recoupment costs under Section 6(j) of the Lease Agreement.
G. Navient is entitled to recover its attorneys’ fees as the prevailing party.
Section 28(q) of the Lease Agreement states “[i]n the event of any litigation
between [BPG] and [Navient], the unsuccessful party as determined by a court of
233 Pl.’s/Countercl. Def.’s Post-Trial Sur-Reply Br. at 5 (citing JX 65). Navient provided more record citations for the transformer, but the transformer is not at issue because BPG’s claim on the transformer is barred by the statute of limitations. 234 See, e.g., JX 65 at 11 (opining on water source heat pumps and makeup air units); see also id., Ex. H (displaying Mr. Alderson’s opinions on amortization/depreciation calculations). 41 competent jurisdiction shall reimburse the successful party for all legal fees and
expenses incurred by the successful party in prosecuting or defending any such
action.”235 Navient contends it is the successful party in full on its affirmative claim,
and even if BPG is partially successful on its counterclaim, Navient still prevails on
the majority of the issues.236 BPG contends that unless Navient achieves a net
principal recovery of “1 cent more than 50%” of Navient’s affirmative claim, then
BPG is the prevailing party.237
“Delaware generally follows the American Rule, under which litigants are
responsible for their own attorneys’ fees, regardless of the outcome of the
lawsuit.”238 An exception to the American Rule applies “in contract litigation that
involves a fee shifting provision.”239 In those cases, Delaware courts generally
enforce a contractual agreement to shift fees.240 Absent “qualifying language that
fees are to be awarded claim-by-claim or on some other partial basis, a contractual
provision entitling the prevailing party to fees will usually be applied in an all-or-
235 JX 3 § 28(q). 236 Pl.’s/Countercl. Def.’s Post-Trial Answering Br. at 33. 237 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 60. 238 Bako Pathology LP v. Bakotic, 288 A.3d 252, 280 (Del. 2022) (quoting Alaska Elec. Pension Fund v. Brown, 988 A.2d 412, 417 (Del. 2010)). 239 Mahani v. Edix Media Grp., Inc., 935 A.2d 242, 245 (Del. 2007); see also Bako Pathology LP, 288 A.3d at 280 (citing Mahani). 240 Bako Pathology LP, 288 A.3d at 280 (quoting SIGA Techs., Inc. v. PharmAthene, Inc., 67 A.3d 330, 352 (Del. 2013)). 42 nothing manner.”241 In such an all-or-nothing case, the Court analyzes the
“predominance in the litigation” to determine the prevailing party. 242 “To establish
predominance, the party must prevail on the case’s chief issue[s].” 243
There were two chief issues in this action: (1) Navient’s claim for breach of
the Lease Agreement with respect to the cooling tower reimbursement; and (2)
BPG’s counterclaim for breach of the Lease Agreement with respect to the
transformer, heat pumps, rooftop air units, and elevators. As to the first issue,
Navient indisputably is the prevailing party. BPG conceded shortly before trial that
it owed Navient $503,822.72 for replacement of the cooling tower.244 With respect
to the second issue, the Court also finds Navient is the prevailing party. BPG sought
$817,845 from Navient based on: (a) $434,500 for the heat pumps, (b) $240,000 for
the rooftop air units, (c) $140,000 for the transformer, and (d) $3,345 for the
elevator.245 The Court has determined BPG is entitled to a total of $79,650: $8,400
to repair the rooftop air units and $71,250 to repair the non-operational heat pumps
($28,750 for the 11 non-operational pumps within their life expectancy, and $42,500
241 AFH Hldg. & Advisory, LLC v. Emmaus Life Scis., Inc., 2014 WL 1760935, at *2 (Del. Super. Apr. 16, 2014) (quoting West Willow-Bay Ct., LLC v. Robino-Bay Ct. Plaza, LLC, 2009 WL 458779, at *8 (Del. Ch. Feb. 23, 2009)). 242 Duncan v. STTCPL, LLC, 2020 WL 829374, at *15 (Del. Super. Feb. 19, 2020) (citing Mrs. Fields Brand, Inc. v. Interbake Foods LLC, 2018 WL 300454, at *2 (Del. Ch. Jan. 5, 2018)). 243 Id. (citing 2009 Caiola Fam. Tr. v. PWA, LLC, 2015 WL 6007596, at *33 (Del. Ch. Oct. 14, 2015)); see also id. (noting that there can be more than one chief issue in a case). 244 PTO § 2(z). 245 Defs.’/Countercl. Pls.’ Post-Trial Opening Br. at 61. 43 for the 14 non-operational pumps past their life expectancy). The Court therefore
finds Navient prevailed on BPG’s counterclaim because it successfully defended
more than 90% of the damages BPG sought.
The Court recognizes there are circumstances “where ‘no party may be
regarded as having prevailed.’”246 For example, in Vianix Delaware LLC v. Nuance
Communications, Inc.,247 the Court of Chancery held “there was no prevailing party
and decline[d] both parties’ requests for attorneys’ fees and costs” where each side
won “on several claims and contentions” and one party recovered “what may be
millions of dollars in damages, but far less than it claimed.”248 But that is not the
case here. Instead, Navient recovered more than what this Court has found sufficient
to be the “prevailing party.”249 The Court therefore finds BPG is the “unsuccessful
party” under Section 28(q) of the Lease Agreement, and Navient is the successful
party entitled to “all legal fees and expenses incurred . . . in prosecuting [and]
defending” this action.250
246 Duncan, 2020 WL 829374, at *15 (quoting Vianix Delaware LLC v. Nuance Commc’ns, Inc., 2010 WL 3221898, at *28 (Del. Ch. Aug. 13, 2010)). 247 2010 WL 3221898, at *28 (Del. Ch. Aug. 13, 2010). 248 Id. at *29. 249 See, e.g., AFH Hldg. & Advisory, LLC, 2014 WL 1760935, at *2-3 (finding one party was the prevailing party where that party was successful on the core breach of contract claim, and additionally finding that even though that party voluntarily dismissed fraud claims, it was still the prevailing party under the “all-or-nothing” approach). 250 JX 3 § 28(q). 44 CONCLUSION
For the reasons explained above, Navient is entitled to judgment in the amount
of $503,822.72, plus costs, interest, and attorneys’ fees, less $79,650 for the repair
costs of the 25 non-operational heat pumps and the repair costs of the two rooftop
air units. Navient is entitled to pre-judgment interest on the net principal amount,
with interest accruing as of March 17, 2020. BPG has proved its counterclaim by a
preponderance of the evidence with respect to repairing (not replacing) the 25 non-
operational heat pumps and the two rooftop air units, and the Court therefore enters
judgment in BPG’s favor as to these portions of the counterclaim. BPG has not
proved its counterclaim by a preponderance of the evidence with respect to the
transformer and the elevator, and the Court therefore enters judgment in Navient’s
favor as to these portions of the counterclaim. If there are any open issues not
addressed by this post-trial opinion, the parties shall notify the Court by letter within
five calendar days. Otherwise, Navient shall prepare a conforming form of order
and file it with the Court within ten calendar days. If BPG objects to the form of
order, it shall so advise the Court by letter within two days of filing. The appeal
period for this post-trial opinion shall not begin to run until the final order is entered
as an order of the Court.
Related
Cite This Page — Counsel Stack
Navient Solutions, LLC v. BPG Office Partners XIII Iron Hill LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/navient-solutions-llc-v-bpg-office-partners-xiii-iron-hill-llc-delsuperct-2023.