Nave v. McGrane

113 P. 82, 19 Idaho 111, 1910 Ida. LEXIS 103
CourtIdaho Supreme Court
DecidedDecember 30, 1910
StatusPublished
Cited by16 cases

This text of 113 P. 82 (Nave v. McGrane) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nave v. McGrane, 113 P. 82, 19 Idaho 111, 1910 Ida. LEXIS 103 (Idaho 1910).

Opinion

SULLIVAN, C. J".

— This is an action to recover the alleged contract price for certain building plans and specifications, prepared by plaintiff, as an architect, for the defendant. The case was tried by a jury, and from the judgment for plaintiff and from an order overruling a new trial this appeal is taken.

The ease presents for determination questions relating to the duties and responsibilities arising from this class of professional services. A number of errors are assigned in regard to the admission and rejection of evidence and the giving and refusing to give certain instructions. The facts are substantially as follows:

The defendant is the lessee of the Bollinger Hotel in Lewis-ton and the owner of certain adjacent lots, upon which in 1908 he contemplated erecting an addition to the hotel. The plaintiff, an architect, in the same city, learning of the defendant’s intention, went to him and solicited the work of drawing the plans and specifications and supervising the construction. Sketches for the building were prepared and then the defendant temporarily abandoned the project. A little later he decided to erect a somewhat larger building, for which the plaintiff prepared plans and specifications. That construction was likewise abandoned, and defendant pre *115 sented a bill for $240 for his services up to that time. By agreement the claim was reduced to $120, as none of the plans had been used and that amount was paid and accepted in full. In December, 1908, the defendant decided to erect a larger and more substantial building than he had previously contemplated. As an inducement for the defendant to employ plaintiff in connection with the last building, plaintiff offered to let $60 of the amount paid him for his prior work apply on the new contract. The parties finally agreed that plaintiff should prepare the plans and specifications. The plaintiff testified that he was to prepare the plans and specifications for three per cent of the estimated cost, to be determined by the lowest responsible bid, if the building was not constructed, and if the building was constructed and he supervised the construction, then he was to receive five per cent of the cost, less $60. The defendant testified that if the plans were not used, he was not to be charged the full three per cent, but some reasonable sum was to be agreed upon. He also testified that he directed plans and specifications prepared for a building not to exceed a cost of $10,000; that the building was to consist of one story and a basement, so constructed that three additional stories could be built on in the future, making in all four stories and basement; and that the plaintiff “guaranteed” that he would make the plans and specifications and do his work to the satisfaction of the defendant. Plaintiff denied that any limit of cost was placed on the building. He also denied that he was to prepare his plans for a four-story construction. However, in the general specifications prepared and introduced in evidence, the plaintiff states as follows: “All brick used throughout the building must be good, hard-burned, merchantable, .common stock brick, as the character of the stone and concrete provides for four-story construction, ’ ’ etc. Also under the head of plumbing it is stated: “All pipes must be sufficient in size to accommodate the plumbing of four stories.” These specifications themselves would indicate that the plaintiff understood that, they were to be sufficient for a four-story building.

*116 It is claimed by the defendant that there was some delay in preparing the plans and submitting them, but they were finally delivered, but contained no form of contract or bid and no bond for the construction of said building. The defendant, not being an architect, knew nothing about plans and specifications and supposed those delivered to him were complete and skillfully drawn. Notice for bids was published and three bids, all in excess of $10,000, were received and rejected, and it is contended by counsel for defendant that the plans and specifications were defective in regard to the foundation, concrete work, wiring, plumbing, etc.; that they did not contain the date of beginning work; the date of completion; the time or manner of payment; whether work should be continuous or intermittent; the amount and character of indemnity against personal injury or against liens; provision for security for the faithful performance of the contract; for the amount of penalty for delay; or for insuring the building during the construction; some of which provisions should have been contained in a contract. The specifications recite that they are a part of the contract, but no contract or bond was prepared and submitted. At the trial the plaintiff offered to show that a certain blank form of contract was the one he had in mind, but as neither the owner nor the bidders knew of it or had in mind any agreement in reference to it, it was rejected.

It is contended that the defendant was in no position to call for bids at the time they were advertised for; that they were not offers for the performance of a contract submitted, as no contract was submitted; that they were merely an expression on the part of the bidders of a willingness to negotiate further toward arriving at a contract, the terms of which were yet to be agreed upon, and that no bids in the ordinary sense of the word were received. Defendant became doubtful as to the sufficiency of the plans, and testified that he requested the plaintiff to strengthen the building by putting in iron pillars and take the weight off the partitions, and plaintiff became angry and refused to make any changes. Defendant then retained the services of architects from Spo *117 kane and procured entirely new plans and specifications and constructed an entirely differently planned building. He did not use the plaintiff’s plans, and the only copy which he had was a carbon copy of the specifications and a blue-print of the plans, which were not called for by the plaintiff, find which remained in the defendant’s desk until the trial, when they were filed in evidence.

Two expert architects testified that the foundation was not strong enough to support a four-story building, and both testified that they had doubts about its being safe for a three-story building. There was a direct conflict in the evidence on several points, and the verdict of the jury would be conclusive, so fair as those facts are concerned, upon a fair trial. But it is contended by counsel for defendant that he did not have a fair trial, because certain material evidence offered was rejected by the court. Plaintiff introduced his plans and specifications as evidence of the performance of his contract. The burden of showing their inadequacy was upon the defendant. No doubt, without explanation of the plans and specifications, the jury would be in the same hopeless condition as the defendant, who testified that so far as his own knowledge went, he was unable to determine whether the plans were adequate for one or fifteen stories.

It is contended that there is a conflict in the testimony, and that under the well-established rule of this court the verdict of a jury on conflicting evidence will not be reversed. As we view it, there is not a substantial conflict in the evidence in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bott v. Idaho State Building Authority
835 P.2d 1282 (Idaho Supreme Court, 1992)
Greenhaven Corp. v. Hutchcraft & Associates, Inc.
463 N.E.2d 283 (Indiana Court of Appeals, 1984)
Spero v. BOARD OF TRUSTEES OF TOWN OF FEDERAL HGTS.
529 P.2d 327 (Colorado Court of Appeals, 1974)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
Robinson & Wilson, Inc. v. Stone
35 Cal. App. 3d 396 (California Court of Appeal, 1973)
Nevada Bank of Commerce v. Three Seas Corp.
446 P.2d 647 (Nevada Supreme Court, 1968)
Lyon v. Melgard
163 P.2d 1019 (Idaho Supreme Court, 1945)
Bott v. Moser
7 S.E.2d 217 (Supreme Court of Virginia, 1940)
Groesbeck v. Hogan
46 F.2d 67 (Sixth Circuit, 1931)
Plaza Amusement Co. v. Rothenberg
131 So. 350 (Mississippi Supreme Court, 1930)
Heslin v. Lapham
246 P. 150 (California Court of Appeal, 1926)
Davis v. Boscou
237 P. 401 (California Court of Appeal, 1925)
J. E. Johnson Const. Co. v. First Nat. Bank of Brenham
260 S.W. 1091 (Court of Appeals of Texas, 1924)
Bebb v. Jordan
189 P. 553 (Washington Supreme Court, 1920)
Kinzell v. Chicago, Milwaukee & St. Paul Railway Co.
190 P. 255 (Idaho Supreme Court, 1920)
Henon v. Vernon
68 Pa. Super. 608 (Superior Court of Pennsylvania, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
113 P. 82, 19 Idaho 111, 1910 Ida. LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nave-v-mcgrane-idaho-1910.