Naval Logistics, Inc. v. M/V Petrus

CourtCourt of Appeals for the Eleventh Circuit
DecidedSeptember 12, 2022
Docket21-12934
StatusUnpublished

This text of Naval Logistics, Inc. v. M/V Petrus (Naval Logistics, Inc. v. M/V Petrus) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Naval Logistics, Inc. v. M/V Petrus, (11th Cir. 2022).

Opinion

USCA11 Case: 21-12934 Date Filed: 09/12/2022 Page: 1 of 16

[DO NOT PUBLISH] In the United States Court of Appeals For the Eleventh Circuit

____________________

No. 21-12934 Non-Argument Calendar ____________________

NAVAL LOGISTICS, INC., d.b.a. Middle Point Marina, Plaintiff-Counter Defendant-Appellee, BISCAYNE TOWING & SALVAGE, INC., Intervenor-Appellee, versus M/V PETRUS, in rem, GREG PACK, in persona, CHARTERED YACHTS MIAMI LLC, USCA11 Case: 21-12934 Date Filed: 09/12/2022 Page: 2 of 16

2 Opinion of the Court 21-12934

Defendants-Counter Claimants-Appellants.

Appeal from the United States District Court for the Southern District of Florida D.C. Docket No. 1:21-cv-20556-KMM ____________________

Before JILL PRYOR, LUCK, and LAGOA, Circuit Judges. PER CURIAM: The luxury motor yacht M/V Petrus (the “vessel”) sank twice: first in the Miami River and second at Middle Point Marina’s (“MPM”) shipyard. The vessel, along with its owners, Chartered Yachts Miami, LLC (“CYM”) and CYM’s principal, agent, and ben- eficial owner, Greg Pack (collectively, the “counterclaimants”), ap- peal the district court’s dismissal with prejudice of their amended counterclaim against MPM. In the amended counterclaim, the counterclaimants asserted three claims: breach of contract, breach of the implied warranty of workmanlike performance, 1 and negli- 0F

gence.

1 The amended counterclaim asserted claims for breach of the implied war- ranty of workmanlike performance (Count I) and negligence (Count II). But the district court construed the breach-of-implied-warranty claim as if it were two distinct claims, one for breach of contract and one for breach of the USCA11 Case: 21-12934 Date Filed: 09/12/2022 Page: 3 of 16

21-12934 Opinion of the Court 3

There are four issues on appeal. The counterclaimants, now the appellants, challenge the district court’s dismissal of their (1) breach-of-contract claim, (2) breach-of-implied-warranty claim, and (3) negligence claim and the court’s (4) denial of leave to amend on the ground that amendment would have been futile. Af- ter careful review, we vacate the district court’s order on the fourth issue and remand for the district court to enter a reasoned order on the counterclaimants’ request for leave to amend. I. BACKGROUND 2 MPM operated a shipyard in Miami, Florida. After the vessel sank at its shipyard, MPM filed an action against the vessel and Pack, bringing claims for breach of contract and a maritime lien for necessaries, storage, and salvage services. MPM alleged that, in De- cember 2020, after the vessel had sunk in the Miami River (the “first sinking”), MPM picked up, towed, delivered, and stored the vessel

implied warranty of workmanlike performance. Because the parties do not challenge this construction on appeal, we construe the claim as the district court did. 2 Given our standard of review, we recite the facts in the light most favorable to the counterclaimants. See Edwards v. Prime, Inc., 602 F.3d 1276, 1291 (11th Cir. 2010) (explaining that when reviewing the dismissal of a pleading on a motion to dismiss for failure to state a claim on which relief may be granted, we accept as true the well-pleaded facts in the pleading). USCA11 Case: 21-12934 Date Filed: 09/12/2022 Page: 4 of 16

4 Opinion of the Court 21-12934

at its shipyard according to Pack’s instructions. Two days later,3 the vessel sank again (the “second sinking”). MPM then “salvaged, dewatered, floated, lifted, hauled out[,] and blocked the [vessel] on land in MPM’s yard.” Doc. 1 at 2. 4 MPM further alleged that, after the second sinking, it reached an agreement with Pack regarding storage, payment, and removal of the vessel. Despite the agree- ment, MPM alleged, Pack failed to remove the vessel by the agreed date or pay outstanding fees owed to MPM. As a result, MPM moved for issuance of an arrest warrant for the vessel and for ap- pointment of a substitute custodian. The district court granted the motions and appointed MPM as substitute custodian of the vessel. 5 CYM filed a “Verified Claim of Owner,” thus appearing in the lawsuit as the owner of the vessel. Doc. 36. The counterclaim- ants then filed their answer to MPM’s complaint along with a coun- terclaim against MPM. In the operative counterclaim (the amended counterclaim), the counterclaimants asserted two causes of action

3 MPM’s complaint alleged that the second sinking happened three days later. The amended counterclaim alleged that it happened two days later. For pur- poses of this appeal, we assume that the sinking happened two days later be- cause we accept as true the well-pleaded facts in the amended counterclaim. See Edwards, 602 F.3d at 1291. 4 “Doc.” numbers refer to the district court’s docket entries. 5 Another entity, Biscayne Towing & Salvage, Inc. (“BTS”), intervened as a plaintiff to assert claims against Pack and the vessel for services it performed related to the first sinking. BTS is only nominally a part of this appeal because it was not a party to the amended counterclaim or MPM’s motion to dismiss. USCA11 Case: 21-12934 Date Filed: 09/12/2022 Page: 5 of 16

21-12934 Opinion of the Court 5

against MPM: breach of implied warranty of workmanlike perfor- mance (Count I) and, in the alternative, negligence (Count II). 6 The counterclaimants alleged that, after the first sinking in November 2020, the vessel was recovered and placed in dry stor- age. MPM then offered its shipyard and storage services to the counterclaimants, knowing that the vessel previously had sunk and suffered significant hull damage. In December 2020, the vessel was removed from dry storage, placed in the water, and towed to MPM. It appears that the counterclaimants initially expected MPM to haul the vessel out of the water upon its arrival at MPM. See Doc. 57 at 4 (“Rather than haul out the [v]essel on arrival . . .”). But MPM told them that the vessel needed to be washed and cleaned before the haul-out, which would require it to be left in the water over the weekend. “The parties [orally] agreed that the [v]essel would be in MPM’s care and custody over the weekend, then after MPM finished washing the [v]essel, it would be lifted out of the water and stored in MPM’s dry storage to begin the repair process to fix the damage from the first sinking.” Id. at 5. Two days later, before MPM hauled the vessel out of the water, it sank for the sec- ond time as it sat in the water unattended. The counterclaimants alleged that MPM delayed the haul-out and exposed the vessel to the foreseeable danger of a second sinking.

6 The counterclaimants also alleged that CYM was the registered corporate owner of the vessel and that Pack did not enter into the original shipyard agreement with MPM individually, but rather on behalf of CYM. USCA11 Case: 21-12934 Date Filed: 09/12/2022 Page: 6 of 16

6 Opinion of the Court 21-12934

In Count I of the amended complaint, the counterclaimants alleged that MPM breached the oral agreement between CYM and MPM “when it knowingly allowed the [v]essel to sit in the water unattended at their dock over the weekend . . . and furthermore al- lowed the [v]essel to sink at its facility.” Id. at 6. They also alleged that MPM breached the implied warranty of workmanlike perfor- mance when it failed to “protect the [v]essel from damage while [the vessel] was docked at [MPM’s] own facility. . .” and “exercise reasonable care, safety[,] and skill when it delayed the haul out of the damaged [v]essel [] and left it unattended over the weekend.” Id. at 5–7. In Count II, the counterclaimants alleged, in the alternative, that MPM was negligent because, as a full-service shipyard, it owed them a duty to exercise reasonable care in storing their vessel while it was docked at the shipyard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwards v. Prime, Inc.
602 F.3d 1276 (Eleventh Circuit, 2010)
Vierling v. Celebrity Cruises, Inc.
339 F.3d 1309 (Eleventh Circuit, 2003)
Odessa Dee Hall v. United Insurance Co. of America
367 F.3d 1255 (Eleventh Circuit, 2004)
Sweet Pea Marine, Ltd. v. APJ Marine, Inc.
411 F.3d 1242 (Eleventh Circuit, 2005)
Kirk S. Corsello v. Lincare, Inc.
428 F.3d 1008 (Eleventh Circuit, 2005)
Thomas v. Cooper Lighting, Inc.
506 F.3d 1361 (Eleventh Circuit, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Henry Gerrard Clay v. Equifax, Inc.
762 F.2d 952 (Eleventh Circuit, 1985)
Kelly v. Harris
331 F.3d 817 (Eleventh Circuit, 2003)
Town of Chester v. Laroe Estates, Inc.
581 U.S. 433 (Supreme Court, 2017)
Chaparro v. Carnival Corp.
693 F.3d 1333 (Eleventh Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Naval Logistics, Inc. v. M/V Petrus, Counsel Stack Legal Research, https://law.counselstack.com/opinion/naval-logistics-inc-v-mv-petrus-ca11-2022.