Nauset Construction Corporation v. Secretary of the Army

CourtCourt of Appeals for the Federal Circuit
DecidedMarch 4, 2024
Docket21-2305
StatusUnpublished

This text of Nauset Construction Corporation v. Secretary of the Army (Nauset Construction Corporation v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nauset Construction Corporation v. Secretary of the Army, (Fed. Cir. 2024).

Opinion

Case: 21-2305 Document: 54 Page: 1 Filed: 03/04/2024

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

NAUSET CONSTRUCTION CORPORATION, Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2021-2305, 2022-1853 ______________________

Appeals from the Armed Services Board of Contract Appeals in Nos. 61673, 61675, Administrative Judge Lis B. Young, Administrative Judge Owen C. Wilson, Adminis- trative Judge Richard Shackleford. ______________________

Decided: March 4, 2024 ______________________

JOHN JOSEPH MCNAMARA, Lane McNamara LLP, Southborough, MA, argued for appellant. Also represented by ELISE M. KUEHN.

WILLIAM JAMES GRIMALDI, Commercial Litigation Branch, Civil Division, United States Department of Jus- tice, Washington, DC, argued for appellee. Also repre- sented by BRIAN M. BOYNTON, PATRICIA M. MCCARTHY, FRANKLIN E. WHITE, JR. Case: 21-2305 Document: 54 Page: 2 Filed: 03/04/2024

______________________

Before REYNA, TARANTO, and STOLL, Circuit Judges. STOLL, Circuit Judge. Nauset Construction Corp. appeals the final decision of the Armed Services Board of Contract Appeals, which dis- missed Nauset’s appeal of a default termination of a gov- ernment contract as untimely under the Contract Disputes Act. In particular, Nauset challenges the Board’s fact find- ings that (1) Nauset was not prejudiced by the appeal no- tice provided in the government’s termination letter; and (2) the government’s behavior following the termination letter did not vitiate the finality of the termination letter. Because the Board’s findings are supported by substantial evidence, we affirm the Board’s dismissal. BACKGROUND On November 1, 2013, the National Guard Bureau awarded a contract to Nauset to build the Guard’s Unit Training Equipment Site Project in Camp Edwards, Mas- sachusetts. On November 17, 2017, the contracting officer terminated Nauset’s contract for default. The termination letter stated: “[T]he Government is completely Terminat- ing Nauset for Default . . . . This notice constitutes such de- cision, and Nauset has the right to appeal under the Disputes clause of the contract.” J.A. 348. The termination letter, however, did not include the specific notice of appeal rights language required by Federal Acquisition Regula- tion (FAR) 33.211(a)(4)(v). Specifically, under that appli- cable FAR provision, the termination notice was required to contain language notifying the contractor that they “may appeal [the] decision to the agency board of contract ap- peals . . . within 90 days” of receipt of the decision or, alter- natively, “bring an action directly in the United States Court of Federal Claims.” FAR 33.211(a)(4)(v). Case: 21-2305 Document: 54 Page: 3 Filed: 03/04/2024

NAUSET CONSTRUCTION CORPORATION v. 3 SECRETARY OF THE ARMY

Within 90 days of receipt of the termination letter, Nauset submitted two letters to the contracting officer. First, on January 17, 2018, Nauset submitted a letter titled “Response to Termination of November 17, 2017 and Cer- tified Termination Claim and Request for Final Decision under the Contract Disputes Act.” J.A. 357. In this letter, Nauset disputed the termination and stated that it in- tended to submit a claim for costs. Nauset also stated that it “takes exception to the government’s decision to termi- nation for default . . . [and that it] will continue to vehe- mently invest every available resource to support [its] Claim, [its] position and reputation.” J.A. 370. The con- tracting officer acknowledged receipt of this letter by email stating “Email received.” J.A. 411. Then, on February 12, 2018, Nauset submitted a “Claim for Extended Time and Unpaid Completed Contract Work – Part 2 and Wrongful Termination.” J.A. 372. In the “Wrongful Termination” section of the letter, Nauset stated that it “intends to de- fend its position and prove that the government’s decision to terminate was based on . . . circumstances . . . beyond [its] control” and that it “submits this wrongful termination claim in accordance with the Contract Disputes Act.” J.A. 374–75. The contracting officer again acknowledged receipt via email stating “Received.” J.A. 413. On June 27, 2018, 222 days after the termination no- tice, Nauset appealed the decision to the Board. J.A. 129. The government filed a motion to dismiss, arguing that Nauset’s appeal of the termination for default was un- timely. Nauset replied that its appeal was not time-barred because, among other things, the government gave inade- quate notice of Nauset’s appeal rights and Nauset reason- ably and detrimentally relied on the lack of notice and was thus prejudiced by the lack of notice. In addition, Nauset asserted that the government’s conduct following the ter- mination vitiated the finality of the termination for default. The Board rejected each of these arguments and ultimately dismissed Nauset’s appeal as untimely. See Nauset Case: 21-2305 Document: 54 Page: 4 Filed: 03/04/2024

Construction Corp., ASBCA Nos. 61673, 61675, 21-1 BCA ¶ 37852, 2021 WL 2029232 (May 5, 2021) (Board Decision). Nauset appeals. We have jurisdiction under 28 U.S.C. § 1295(a)(10). DISCUSSION On appeal, Nauset argues that the Board erred in find- ing that the termination notice did not prejudice Nauset. Alternatively, Nauset asserts that the Board erred in find- ing that the government’s conduct did not vitiate the final- ity of the termination. We address each argument in turn below. Our review of the Board’s decision is limited by statute. Under the Contract Disputes Act, we review the Board’s legal determinations de novo and we may only set aside the Board’s findings of fact if they are “(A) fraudulent, arbi- trary, or capricious; (B) so grossly erroneous as to neces- sarily imply bad faith; or (C) not supported by substantial evidence.” 41 U.S.C. § 7107(b)(2). Whether the termina- tion letter prejudiced Nauset presents a question of fact that we review for substantial evidence. See Bannum, Inc. v. United States, 404 F.3d 1346, 1353 (Fed. Cir. 2005) (“Prejudice is a question of fact.”); see also Godley v. United States, 5 F.3d 1473, 1476 (Fed. Cir. 1993) (stating that whether the appellant suffered prejudice was a factual question). Similarly, whether the government’s actions vi- tiated the finality of the termination letter, or in other words, whether Nauset could reasonably believe that the contracting officer was reconsidering her decision, is a question of fact reviewed for substantial evidence. See Ra- Nav Lab’ys, Inc. v. Widnall, 137 F.3d 1344, 1346, 1348 (Fed. Cir. 1998) (determining that substantial evidence supports the ASBCA’s finding that the government’s con- duct following termination did not vitiate the termination of the contract); Am. Elec. Lab’ys, Inc. v. United States, 774 F.2d 1110, 1116 (Fed. Cir. 1985) (determining whether substantial evidence supports the ASBCA’s finding that a Case: 21-2305 Document: 54 Page: 5 Filed: 03/04/2024

NAUSET CONSTRUCTION CORPORATION v. 5 SECRETARY OF THE ARMY

party’s reliance on the government’s conduct was unrea- sonable). I Substantial evidence supports the Board’s finding that there was no prejudice or detrimental reliance here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Festo Corp. v. Shoketsu Kinzoku Kogyo Kabushiki Co.
535 U.S. 722 (Supreme Court, 2002)
KSR International Co. v. Teleflex Inc.
550 U.S. 398 (Supreme Court, 2007)
Bannum, Inc. v. United States
404 F.3d 1346 (Federal Circuit, 2005)
Octane Fitness, LLC v. Icon Health
134 S. Ct. 1749 (Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Nauset Construction Corporation v. Secretary of the Army, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nauset-construction-corporation-v-secretary-of-the-army-cafc-2024.