Naughton v. Stagg

4 Mo. App. 271, 1877 Mo. App. LEXIS 87
Missouri Court of Appeals·Decided June 26, 1877·Published·Cited by 6 cases

Opinion

BaKewell, J.,

delivered the opinion of the court.

This is a suit on a mechanic’s lien. The first countin the [272] petition is for work and material furnished on a building contract for the erection of a dwelling-house, and the second count is for extra work. For work under the contract, and changes made by agreement during the progress of the building, plaintiff demands a balance, said to be due, of $2,319.17 ; and under the second count, for extra work and materials, he asks judgment for $195. The answer admits the contract; denies that the lien was filed in time ; denies that defendant is bound by agreement to pay any thing for the changes.from the original contract; and asks to recoup $1,000 damages for the unworkmanlike manner in which the building was constructed. The answer also puts in issue the averments of the second count, and sets up counter-claims to the amount of $1,105.

The testimony was conflicting on every issue except as to the counter-claims. There was a verdict for plaintiff for $1,586.81. Plaintiff remitted $527, and judgment was rendered for the balance ; and plaintiff appeals.

Several instructions were given at the instance of either side, and some instructions asked by defendant were refused; but as no exceptions were saved, during the trial, to the action of the court in giving and refusing instructions, we shall not consider them. Objections to instructions, taken for the first time on the motion for a new trial, will not be considered here. The record-must show that exceptions were taken at the time the instructions were passed upon, otherwise they are not subject to review by the appellate court. 14 Mo. 367.

It appears that the work sued for was to be done according to plans and specifications furnished by one Bridwell, the architect and superintendent employed by defendant. A sum of something more than $500 is claimed by plaintiff for extra work, caused by changes in the plans. Defendant denies that any changes in the plans were made with his consent. On the trial, plaintiff was introduced as a witness on his own behalf, and in the course of his testimony said: [273] <£I would also say there was a change made in the cut above. On the front I was ordered to cut the stone out; but there was a subsequent plan made out, whereby more sills were to be put in, which threw an immense amount of work upon it. I copied the items and put them in the bill; and when I got the stone up, Mr. Bridwell gave a subsequent plan, which was nine inches wider than the original plan; so I had to make an entire change upon the whole, and not let Mr. Stagg, as he said, know anything about it, and that (sic) if there was any change or any difference about the windows, it would make no difference.”

Defendant’s counsel objected to any evidence of changes in the work, not known to defendant, going to the jury, and asked that it be ruled out; to which the court said that the witness could state whether defendant assented to the change or not. However, no further statement on the subject was asked of, - or made by, the witness at that time. The defendant’s counsel objected to the action of the court in not ruling out this evidence, and the examination proceeded on other points.

We see nothing in this action of the court to warrant a reversal of the judgment. If defendant’s counsel had pressed the matter, and required the witness to state whether or not Stagg knew of these changes, the court would, perhaps, on application of counsel, have ruled out this testimony. As it was, the jury were instructed, at the instance of defendant, that Bridwell had no authority to agree for Stagg to any changes in the work, and that defendant was not bound by any such agreement of Bridwell, if such an agreement was made. And if, 'as defendant’s counsel contends, the amount found includes the $500 for alleged alterations, a remittitur was entered for this amount, and the injustice redressed, in the trial court.

An objection was made to the introduction on the part of the plaintiff of a letter addressed by Bridwell to Naughton, dated March 1, 1873, in which Bridwell requires Naughton [274] to do certain work in bricking-up window-sills, painting, dressing and cleaning stone, and cleaning flues, which he says is necessary for the completion of the job, and as to which he says, “ I find, by close estimate, it will cost $125. When j'-ou do this, I will accept your job as being finished.” The ground of this objection, so far as it professes to be preserved in the record, is perfectly unintelligible. The record reads: “Objected to as a conclusion to anmuch [qu., impeach?] the defendant, and therefore not finding [qu., binding?] on him; and as .incompetent to impeach. Mr. Bridwell, because not called to his attention at the time of-taking his deposition.” The letter was not competent, if introduced to impeach the witness Bridwell; but it does not appear that it was introduced for that purpose. Bridwell’s deposition had not been read when this letter was offered. It does not appear by the record what other ground of objection was called to the attention of the court. The fact that the letter might tend to contradict Bridwell, whose evidence had not been heard, could not appear to the court; and no other reason is stated in such a way that we can determine whether, if specified on the trial, it might not have been obviated at once by the party offering the evidence.

The next objection urged by appellant is that the court admitted in evidence a copy of a paper dated August 1, 1872, when the absence of the original had not been accounted for. This ground of objection is not shown to have been specifically urged on the trial, and it cannot be considered here.

Free access — add to your briefcase to read the full text and ask questions with AI

Naughton v. Stagg, 4 Mo. App. 271, 1877 Mo. App. LEXIS 87 (Mo. Ct. App. 1877).

4 Mo. App. 271 (Naughton v. Stagg) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Nevada Central Railroad
28 Nev. 186 (Nevada Supreme Court, 1905)
State v. Musgrave
28 S.E. 813 (West Virginia Supreme Court, 1897)
Levitt v. Miller
64 Mo. App. 147 (Missouri Court of Appeals, 1895)
Stevens v. City of Minneapolis
43 N.W. 842 (Supreme Court of Minnesota, 1889)
Crum v. Elliston
33 Mo. App. 620 (Missouri Court of Appeals, 1889)
Kelly v. Rowane
33 Mo. App. 440 (Missouri Court of Appeals, 1889)