Natural Resources Defense Council, Inc. v. Munro

520 F. Supp. 17, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1981 U.S. Dist. LEXIS 18498
CourtDistrict Court, D. Oregon
DecidedMay 15, 1981
DocketCiv. No. 75-344-RE
StatusPublished
Cited by2 cases

This text of 520 F. Supp. 17 (Natural Resources Defense Council, Inc. v. Munro) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natural Resources Defense Council, Inc. v. Munro, 520 F. Supp. 17, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1981 U.S. Dist. LEXIS 18498 (D. Or. 1981).

Opinion

REDDEN, District Judge:

Defendants move to vacate the judgment and dismiss this case on the grounds that (1) the case is moot, (2) prospective application of the judgment would be inequitable, and (3) the judgment has been satisfied. Plaintiffs oppose the motion.

Nature of the case

Six environmental groups1 brought this action for declaratory and injunctive relief under the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. §§ 4321-47. They claimed that the Bonneville Power Administration (BPA) should not be allowed to take any action with respect to “Phase 2” of the “Hydro-Thermal Power Program” (HTPP) until an environmental impact statement (EIS) was prepared. This [18]*18court held that an EIS was required and issued an injunction prohibiting defendant administrator of BPA and defendant Secretary of the Interior from taking any action to implement Phase 2 or any program equivalent to Phase 2 before an appropriate EIS was filed.2 The court retained jurisdiction of the case pending the filing of an EIS. The Court of Appeals affirmed the ruling.3

On December 5, 1980, Congress enacted the Pacific Northwest Electric Power Planning and Conservation Act (Power and Conservation Act), Pub.L. 96-501, 94 Stat. 2697. Defendants contend that passage of the Power and Conservation Act constitutes a Congressional resolution of the issues raised in this action, and that the injunction entered by this court is no longer necessary or appropriate.4

BPA’s “Phase 2” Program5

In 1968, a “Joint Power Planning Council,” consisting of representatives of a public utilities’ organization (Public Power Council), four private utilities and BPA, devised a ten-year hydro-thermal power program to meet the Northwest’s power needs through 1981. Under the program, the utilities were to build thermal (nuclear and coal-fired) power plants. The addition of thermal energy would provide a mixed base of hydroelectric and thermal power for baseload energy purposes.6 Any new hydroelectric resources were to be used to increase peaking capacity.7 BPA’s role in the HTPP was to provide the necessary peaking capacity, a high voltage transmission grid and reserve electric power in excess of peakload needs. BPA was also to pool the available low-cost hydroelectric and high-cost thermal power for sale to its customers at uniform rates. Public agencies’ share of the costs of the thermal plants’ construction would be financed through net-billing arrangements; i.e., the share of the plant costs would be offset against amounts owed to BPA by the preference customers.

In 1973, it became apparent that the HTPP would have to be modified to meet the Northwest’s energy needs after 1981. The implementation of “Phase I” of the HTPP (up to 1981), was not sufficient because of delays in constructing thermal power plants, because the demand for energy was increasing at a faster rate than forecasted, and because the capacity for net-billing was being exhausted. The Department of Interior therefore instructed BPA to attempt to design an appropriate plan to extend the HTPP or to provide an alternate procedure to provide energy for the Northwest beyond 1981. Following consultations with its customers, BPA drafted a program entitled “Phase 2” of the HTPP. The utilities were to build eight additional thermal plants to provide base-load energy sufficient to meet the Northwest’s energy needs until 1986. The federal government was to construct facilities for additional peaking capacity, and BPA was once again to expand its transmission system. BPA was to continue to provide transmission of power, reserves, load shaping, sale of power surplus to the needs of the participants in the thermal plants and the scheduling of project output on behalf of the participating utilities.

Phase 2 eliminated the use of net-billing as a means of financing the preference customers’ share of the construction costs of [19]*19additional thermal plants. Any low-cost hydroelectric power available under Phase I was to be allocated to preference and industrial customers until 1983. After that, preference customers would have to participate directly or indirectly in the construction of thermal plants generating the high-cost power.

A major change from Phase I to Phase 2 was to be the increasingly important role of direct-service industrial customers (DSIs). The DSIs were to be granted new 20-year contracts with BPA. In return, they would agree to purchase up to 1,000 megawatts of reserve power which would be made available to the utilities if needed. To implement these arrangements, four types of contracts were to be used: (1) twenty-year power contracts with preference customers; (2) trust-agency agreements with participating preference customers; (3) agreements to provide services to thermal plant participants not parties to the trust-agency agreements; and (4) twenty-year power sale contracts with the DSIs.

Phase 2 was made public in December 1973. In April 1975, BPA submitted a draft EIS entitled “BPA Participation in Regional Interutility Cooperation” to the Council on Environmental Quality (CEQ). The Chairman of the CEQ rejected the EIS as inadequate. He criticized the lack of detail with respect to the regional program and BPA’s participation in it. He provided some guidelines for a new EIS by stating:

The most critical components of such an EIS would be a full description of the Program as presently planned, the best possible assessment of the cumulative environmental impacts, and a discussion of reasonable alternatives... ,8

BPA subsequently announced that it was preparing an EIS entitled “The Role of BPA in Pacific Northwest Power Supply System, Including Its Participation in the Hydro-Thermal Power Program.”

On April 17, 1975, plaintiff environmental groups filed this action contending that Phase 2 constituted a major federal action proposal significantly affecting the quality of the human environment, and that an EIS was therefore required under NEPA. They contended that Phase 2 would adversely affect the environment in numerous ways including: Contamination of the air due to the emission of hazardous particulates and gases from coal-fired thermal plants; serious loss of aquatic life in certain Northwest rivers because of the thermal and chemical pollution emitted from nuclear power plants; increased fish mortality; decreased recreational safety and disruption of commerce on the Columbia River due to the increased use of hydro generators; the risk of a catastrophic nuclear accident, as well as the routine emission of hazardous radioactive materials from nuclear power plants; the disruption of wildlife habitat; the loss of thousands of acres of land used for agricultural and recreational purposes, due to the construction of transmission lines; and the loss of thousands of acres of other agricultural land due to the surface mining of coal and uranium.9

Plaintiffs moved for summary judgment on its claim that Phase 2 required the preparation and filing of a “programmatic” EIS. The court held that a programmatic EIS was required.

Scope of Injunction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
520 F. Supp. 17, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1981 U.S. Dist. LEXIS 18498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natural-resources-defense-council-inc-v-munro-ord-1981.