Natl Assoc., Reg. Util Commiss v. Department of Energy

CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 19, 2013
Docket11-1066
StatusPublished

This text of Natl Assoc., Reg. Util Commiss v. Department of Energy (Natl Assoc., Reg. Util Commiss v. Department of Energy) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natl Assoc., Reg. Util Commiss v. Department of Energy, (D.C. Cir. 2013).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 25, 2013 Decided November 19, 2013

No. 11-1066

NATIONAL ASSOCIATION OF REGULATORY UTILITY COMMISSIONERS, PETITIONER

v.

UNITED STATES DEPARTMENT OF ENERGY, RESPONDENT

Consolidated with 11-1068

On Petitions for Review of Final Actions or Failures to Act by the United States Department of Energy

Jay E. Silberg argued the cause for petitioner. With him on the briefs were Timothy J.V. Walsh, James Bradford Ramsay, Holly Rachel Smith, and Anne W. Cottingham.

Joseph A. McGlothlin, Cynthia B. Miller, and Richard C. Bellak were on the brief for amici curiae Florida Public Service Commission, et al., in support of petitioners.

Allison Kidd-Miller, Senior Trial Counsel, U.S. Department of Justice, argued the cause for respondent. With her on the brief 2

were Stuart F. Delery, Acting Assistant Attorney General, and Jeanne E. Davidson, Director.

Before: BROWN, Circuit Judge, and SILBERMAN and SENTELLE, Senior Circuit Judges.

Opinion for the Court filed by Senior Circuit Judge SILBERMAN.

SILBERMAN, Senior Circuit Judge: Petitioners, a group of nuclear power plant operators, appear again before us to claim, essentially, that so long as the government has no viable alternative to Yucca Mountain as a depository for nuclear waste they should not be charged an annual fee to cover the cost of that disposal. We agree.

I.

Last year we decided that the Secretary of Energy had not complied with his statutory obligation to determine annually the adequacy of the fee petitioners pay to the government. Nat'l Ass'n of Regulatory Util. Comm'rs v. U.S. Dep't of Energy, 680 F.3d 819 (D.C. Cir. 2012). We rejected the government’s argument that the Secretary was not obliged to determine the fee’s adequacy unless someone (a “deus ex machina”?) brought to the Secretary evidence that the fee was excessive or inadequate. Id. at 824. We held that the Secretary had an affirmative obligation to examine the facts himself and come to a determination as to the adequacy of the fee.

We noted also that the Department of Energy’s opinion had abandoned, without explanation, its previous policy of producing sophisticated analyses of potential costs. It had ignored the enormous amount of interest – $1.3 billion – accruing annually in the fund built up by previous assessments, 3

and it had not excluded costs already paid and costs associated with the disposition of defense-related waste for which the generators are not responsible. And we thought that using Yucca Mountain’s depository cost as a proxy was unreasonable because the government had abandoned that program. But the key defect in the government’s position was its failure to make the statutorily required determination as to whether the fee was adequate. We remanded to the Secretary with instructions to conduct a new fee assessment within six months; the panel retained jurisdiction to expedite any further review.

II.

On remand the Department has again declined to reach the statutorily required determination. Instead, we are presented with an opinion of the Secretary that sets forth an enormous range of possible costs. According to the Secretary, the final balance of the fund to be used to pay the costs of disposal could be somewhere between a $2 trillion deficit and a $4.9 trillion surplus. This range is so large as to be absolutely useless as an analytical technique to be employed to determine – as the Secretary is obligated to do – the adequacy of the annual fees paid by petitioners, which would appear to be its purpose. (This presentation reminds us of the lawyer’s song in the musical, “Chicago,” – “Give them the old razzle dazzle.”) Thus, the Secretary claims that the range is so great he cannot determine whether the fees are inadequate or excessive, which is essentially the same position we rejected only last year as in derogation of his responsibility under the statute. The Secretary may not comply with his statutory obligation by “concluding” that a conclusion is impossible. See Pub. Citizen v. Fed. Motor Carrier Safety, 374 F.3d 1209, 1221 (D.C. Cir. 2004) (“[R]egulation would be at an end if uncertainty alone were an excuse to ignore a congressional command to ‘deal with’ a 4

particular regulatory issue.”); Consolidated Edison Co. of N.Y., v. U.S. Dep’t of Energy, 870 F.2d 694, 698 (D.C. Cir. 1989).

The Secretary’s position – his “non determination” – is purportedly predicated on a Departmental report issued in 2011 termed a “Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste.” Even if that so-called strategy led to a statutorily required determination, it would still be problematic because, as petitioners point out, the strategy is based on assumptions directly contrary to law.

Most glaring is the conflict between the statutory requirement that sites other than Yucca Mountain cannot even be considered as an alternative to Yucca Mountain, 42 U.S.C. § 10172, and the “strategy’s” assumption that whatever site is chosen, it will not be Yucca Mountain. The other conflicts are related to this prime conflict. The “strategy” suggests that a temporary storage facility might be operational by 2025 and that the temporary facility could be constructed without NRC first issuing a license for the construction of a permanent facility. But the statute requires that precondition. The statute is obviously designed to prevent the Department from delaying the construction of Yucca Mountain as the permanent facility while using temporary facilities. 42 U.S.C. § 10168(d)(1). Finally – and this is quite revealing – the strategy assumes that the Department would be required to obtain the consent of the jurisdiction where the permanent depository is to be sited. That is, of course, reflective of the political considerations the Department faces but, unfortunately, it is directly contrary to the statute, which explicitly allows Congress to override a host state’s disapproval. 42 U.S.C. § 10135; accord In re Aiken Cnty., 725 F.3d 255, 260 (D.C. Cir. 2013) (“[A]n agency may not rely on political guesswork about future congressional appropriations as a basis for violating existing legal mandates.”). Finally, the strategy projects completion of a permanent 5

depository (located somewhere) not until 2048, in contrast to the statute, which directed completion by 1998. 42 U.S.C. § 10222(a)(5)(B). That is truly “pie in the sky.”

In response to petitioners’ argument – that a position predicated on a policy that so palpably rejects current law cannot be in accordance with the Secretary’s obligation, even if it does lead to a specific determination – the government responds that some of the Secretary’s previous determinations had also assumed statutory changes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Natl Assoc., Reg. Util Commiss v. Department of Energy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natl-assoc-reg-util-commiss-v-department-of-energy-cadc-2013.