Native Sun v. L & H DEVELOPMENT, INC.

944 P.2d 995, 149 Or. App. 623, 1997 Ore. App. LEXIS 1141
CourtCourt of Appeals of Oregon
DecidedSeptember 10, 1997
Docket94-CV-0014-MS; CA A89980
StatusPublished
Cited by9 cases

This text of 944 P.2d 995 (Native Sun v. L & H DEVELOPMENT, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Native Sun v. L & H DEVELOPMENT, INC., 944 P.2d 995, 149 Or. App. 623, 1997 Ore. App. LEXIS 1141 (Or. Ct. App. 1997).

Opinion

*625 LANDAU, J.

Defendant L&H Development, Inc. (L&H) and intervenor Les Hilgers (Hilgers) appeal a judgment entered pursuant to an arbitration award. They contend that the trial court erroneously rejected their exceptions to the award on the ground that the arbitrator decided issues not submitted to him and that his decision was, in any event, grossly erroneous. We affirm.

Plaintiff Native Sun is a limited partnership engaged in land development. L&H is a general construction contractor. Hilgers is the principal owner of L&H. He also owned a 25-percent interest in Native Sun. His initial capital contribution to the partnership totaled $168,000; he later invested an additional $75,000. L&H and Native Sun entered into a general construction contract under the terms of which L&H agreed to build an apartment complex for Native Sun for approximately $1.3 million. In an addendum to that general construction contract, L&H and Native Sun agreed that, if L&H defaulted, Native Sun was authorized to offset any damages that resulted from that default against Hilgers’s limited partnership interest in Native Sun. Some time after that, Hilgers and Native Sun also negotiated a limited partnership agreement that provided that, in the event of cost overruns in the construction of the apartment complex, Native Sun would offset any damages against Hilgers’s capital account.

L&H failed to complete construction of the apartment complex within the agreed price. As a result, Native Sun incurred additional construction costs totaling $329,426.55. Native Sun initiated this action alleging that it was entitled to offset Hilgers’s $168,000 capital account against the cost overrun and have a judgment for the $161,426.32 difference. L&H answered and alleged by way of affirmative defense that, because Native Sun breached the general construction contract, it was precluded from offsetting Hilgers’s “interest in the partnership.” Meanwhile, Hilgers successfully moved to intervene and, in his complaint in intervention, alleged that Native Sun “wrongfully offset 100% of Les Hilgers’[s] partnership interest in the project” *626 and asked for a declaration “of his rights in the limited partnership.”

All three parties entered into an agreement to submit to arbitration “all issues currently ple[ ]d” by the parties. In its memorandum to the arbitrator, Native Sun contended that any interest in the limited partnership that Hilgers retained after the exhaustion of his capital account should be applied to any losses that Native Sun suffered. Hilgers did not object that the issue was not properly before the arbitrator; he argued instead that the relevant portions of the limited partnership agreement allowed an offset against his capital account alone and that any additional damages would have to be recovered against L&H, not taken out of his remaining interest in the limited partnership. The arbitrator held that L&H had breached the general construction contract, resulting in a cost overrun of $329,426.55. The arbitrator also found that Hilgers had invested $168,000 as an initial capital contribution and an additional $75,000 after that. The arbitrator then concluded that:

“An underlying limited partnership agreement, signed by Hilgers individually, authorized plaintiff, Native Sun, to offset against any overrun of the fixed price the initial capital contribution of the property * * * leaving a balance of overruns in the amount of $86,426.55 owing by L & H Development, Inc. to plaintiff. The application of the allowable offset eliminated any further share in the partnership by Hilgers.”

Hilgers filed exceptions to the arbitrator’s award with the trial court. He argued that, in deciding that the application of the allowable offset entirely eliminated his interest in the limited partnership, the arbitrator had exceeded the scope of the matters submitted. Hilgers also argued that the arbitrator’s decision was “incorrect.” The trial court remanded the case to the arbitrator for clarification as to whether he intended that Hilgers’s entire interest in the partnership be eliminated. The parties argued the matter to the arbitrator, who concluded that

“there was no distinction made between capital account and partnership interest throughout this. * * * There [was] no suggestion to me that once the capital account was brought to zero, that there’s something going to be left over.”

*627 The arbitrator declined to modify his award. The trial court entered judgment in accordance with the arbitrator’s award.

On appeal, L&H and Hilgers first argue that the trial court erred in failing to set aside the award, because the arbitrator exceeded the scope of his authority in concluding that offsetting the cost overruns against ids capital account exhausted Hilgers’s interest in the limited partnership. They contend that the arbitration agreement permitted the arbitration of those issues “currently ple[ ]d” by the parties and that the issue of whether there could be an offset against Hilgers’s partnership interest — in addition to his capital account — was not identified in any pleadings at the time the arbitration agreement was executed. Native Sun argues that Hilgers’s own complaint in intervention asked for a declaration as to his rights in the partnership, and that was sufficient to allow the arbitrator to consider the matters about which L&H and Hilgers object.

The scope of judicial review of arbitration awards is defined by ORS 36.355. Brewer v. Allstate Insurance Co., 248 Or 558, 561, 436 P2d 547 (1968). 1 ORS 36.355(l)(f) provides that an exception to an award may be taken if “[t]he arbitrators awarded upon a matter not submitted to them.” Whether an arbitrator “awarded upon a matter not submitted” depends on the terms of the agreement that confer the authority to arbitrate. We review such agreements as a matter of law, Sloan v. Journal Publishing Co., 213 Or 324, 366, 324 P2d 449 (1958), bearing in mind “Oregon’s policy * * * to construe general arbitration agreements broadly to enhance the arbitrability of disputes.” Budget Rent-A-Car v. Todd Investment Co., 43 Or App 519, 524, 603 P2d 1199 (1979). As this court explained in Snow Mountain Pine, Ltd. v. Tecton Laminates Corp., 126 Or App 523, 529, 869 P2d 369, rev den 319 Or 36 (1994):

“Under that policy, arbitration is required, unless we can say with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute, and we resolve all doubts in favor of coverage.”

*628 In this case, the arbitration agreement submitted to arbitration all matters “currently ple[ ]d” by the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christenson Electric v. McClure and Sons
345 Or. App. 458 (Court of Appeals of Oregon, 2025)
Hayward v. High Performance Homes, Inc.
335 Or. App. 178 (Court of Appeals of Oregon, 2024)
Floor Solutions, LLC v. Johnson
520 P.3d 902 (Court of Appeals of Oregon, 2022)
3000 Investment Corp. v. Teed
494 P.3d 378 (Court of Appeals of Oregon, 2021)
Bisaccio v. Hart
159 P.3d 1179 (Court of Appeals of Oregon, 2007)
In re the Marriage of Woods
142 P.3d 1072 (Court of Appeals of Oregon, 2006)
Russell v. Kerley
978 P.2d 446 (Court of Appeals of Oregon, 1999)
Seller v. Salem Womens Clinic, Inc.
963 P.2d 56 (Court of Appeals of Oregon, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
944 P.2d 995, 149 Or. App. 623, 1997 Ore. App. LEXIS 1141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/native-sun-v-l-h-development-inc-orctapp-1997.