Native Ecosystems Council v. Reese

212 F. Supp. 2d 1227, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20826, 2002 U.S. Dist. LEXIS 19264, 2002 WL 1727409
CourtDistrict Court, D. Montana
DecidedJuly 25, 2002
Docket9:20-mcr-00007
StatusPublished

This text of 212 F. Supp. 2d 1227 (Native Ecosystems Council v. Reese) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Native Ecosystems Council v. Reese, 212 F. Supp. 2d 1227, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20826, 2002 U.S. Dist. LEXIS 19264, 2002 WL 1727409 (D. Mont. 2002).

Opinion

ORDER

MOLLOY, Chief Judge.

I. Introduction

Dale Bosworth, who was then the Regional Forester for the Northern Region of the United States Forest Service, signed the Record of Decision for the Tar-ghee National Forest Revised Forest Plan Final Environmental Impact Statement on April 17, 1997. Sara Johnson then filed an administrative appeal of that decision about the RFP. Her appeal was on behalf of Plaintiff Native Ecosystems Council and was filed on August 28, 1997. Up to this point the administrative process was normal. Then the law and regulations were ignored. The Forest Service first responded to this appeal by denying it on May 6, 2002, having never responded to inquires from Johnson over the years about the status of the appeal. While the Forest Service took nearly five years to respond to the appeal, the law requires a response within 160 days.

In the interim, the Forest Service prepared the East Beaver and Miner’s Creek Timber and Prescribed Burning Project tiered to the RFP. These actions took place before the ruling on Johnson’s RFP appeal. Johnson filed an administrative appeal of the project on behalf of NEC and Plaintiff The Ecology Center on February 17, 2001. The Forest Service denied the appeal on April 6, 2001. The Forest Service agreed to stay any ground-disturbing work on the project until after it issued a ruling on the appeal of the RFP, on which it decided on May 6, 2002.

NEC filed suit in this Court on October 1, 2001. It now seeks summary judgment that the Forest Service failed to respond to the appeal of the RFP within 160 days in violation of 36 C.F.R. § 217.8(f)(1). 1 Further, NEC argues that the Forest Service has exhibited a de facto pattern and practice of not responding to administrative appeals of forest plans as required by law through published regulation, and lists fourteen other forests on which the Forest Service did not respond to forest plan appeals in a timely fashion. NEC asks for a ruling that this defacto policy and practice is arbitrary, capricious, or otherwise not in accordance with the law. It seeks injunc-tive relief to prevent the Forest Service from implementing any ground-disturbing projects tiered to the forest plan in any of these forests under appeal prior to a ruling on the appeal.

*1231 The Forest Service admits that it did not respond to the administrative appeal of the Targhee RFP in a timely fashion. Now the Forest Service argues that this matter is moot, since the illegal activity complained of is no longer at issue. This rationale, if adopted, would eviscerate the public’s role in land use decisions and adopt a relativist public policy that would have broad implications in agency decision-making procedures. The Forest Service also argues that NEC has no standing to challenge most of the other forest plans where the Forest Service delayed ruling on administrative appeals of the plan more than 160 days.

II. Analysis

A. Timeliness

Under the law as set forth in Forest Service regulation 36 C.F.R. § 217.8(f)(1), the Forest Service officer reviewing an appeal of a land and resource management plan revision must render an appeal decision not later than 160 days from the date the notice of appeal was filed. In the event of multiple appeals, the appeal date is calculated from the date of the last appeal. 36 C.F.R. § 217.8(f)(2). The Record of Decision for the Targhee National Forest Revised Forest Plan Final Environmental Impact Statement was signed on April 17, 1997. NEC filed a timely administrative appeal of the RFP on August 28, 1997. See Id. § 217.8(a)(3). When, as here, there are multiple appeals, the reviewing officer may prescribe special procedures to conduct the review and must inform all participants of the procedures and conduct of the appeal. Id. § 217.13(a)(2) & (3).

The Forest Service did not make a decision on the appeal until May 6, 2002. This capacious void creates a perilous procedural conundrum for both the Forest service and public participants in the appeal process. The reviewing officer consolidated seven appeals in her decision.

The Forest Service did not inform any participants of any special procedures in the review. The Forest Service concedes that the decision was untimely and in violation of 36 C.F.R. § 217.8(f)(1). The Forest Service was also in violation of 36 C.F.R. § 217.13(a)(3) and (b)(1): It provided no information about the conduct of the appeal to appellants. Appellants were not informed, for example, that the appeals would be consolidated for the decision. Had the law been followed these initial problems would have been avoided.

B. Standing

In order to satisfy Article Ill’s standing requirements, “a plaintiff must show (1) it has suffered an ‘injury in fact’ that is (a) concrete and particularized and (b) actual or imminent, not conjectural or hypothetical; (2) the injury is fairly traceable to the challenged action of the defendant; and (3) it is likely, as opposed to merely speculative, that the injury will be redressed by a favorable decision”. Friends of the Earth, Inc. v. Laidlaw, 528 U.S. 167, 180-81, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000)(citing Lujan v. Defenders of Wildlife, 504 U.S. 555, 560-561, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992)). “An association has standing to bring suit on behalf of its members when its members would otherwise have standing to sue in their own right, the interests at stake are germane to the organization’s purpose, and neither the claim asserted nor the relief requested requires the participation of individual members in the lawsuit.” Id. (citing Hunt v. Washington State Apple Advertising Commission, 432 U.S. 333, 343, 97 S.Ct. 2434, 53 L.Ed.2d 383 (1977)).

The Forest Service argues that NEC cannot meet the injury-in-fact test. It argues that NEC has not alleged that its members have any interest in any national forest management outside of the *1232 Northern Rockies, therefore NEC has not shown any injury-in-fact. The Forest Service apparently contends that because it has now ruled on NEC’s RFP appeal, NEC no longer has experienced injury-in-fact.

Violation- of procedural regulations by the Forest Service caused NEC procedural harm. NEC suffered an unauthorized- and illegal — delay by the Forest Service before the agency ruled on the RFP appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
212 F. Supp. 2d 1227, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20826, 2002 U.S. Dist. LEXIS 19264, 2002 WL 1727409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/native-ecosystems-council-v-reese-mtd-2002.