National Wildlife Refuge Association v. Rural Utilities Service

District Court, W.D. Wisconsin·Decided April 26, 2024·No. 3:24-cv-00139·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

NATIONAL WILDLIFE REFUGE ASSOCIATION, DRIFTLESS AREA LAND CONSERVANCY, and WISCONSIN WILDLIFE FEDERATION,

Plaintiffs, OPINION AND ORDER v. 24-139-wmc

RURAL UTITLITIES SERVICE, ANDY BERKE, Administrator, Rural Utilities Service, UNITED STATES FISH AND WILDLIFE SERVICE, WILL MEEKS, Midwest Regional Director, and SABRINA CHANDLER, Manager, Upper Mississippi River National Wildlife and Fish Refuge, UNITED STATES ARMY CORPS OF ENGINEERS, LIEUTENANT GENERAL SCOTT A. SPELLMON, Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, COLONEL JESSE T. CURRY, Commander and District Engineer, Rock Island District, U.S. Army Corps of Engineers, and COLONEL ERIC SWENSON, Commander and District Engineer, St. Paul District, U.S. Army Corps of Engineers,

Defendants,

and

DAIRYLAND POWER COOPERATIVE and ITC MIDWEST LLC,

Intervenor-Defendants.

This lawsuit is a continuation of efforts by several environmental groups to disrupt completion of the 101-mile high-voltage Cardinal-Hickory Creek Transmission Line Project running from Dubuque, Iowa to Madison, Wisconsin, across the Mississippi River, and crucially for purposes of this latest federal lawsuit, through the Upper Mississippi River National Wildlife and Fish Refuge. On March 21, 2024, this court preliminarily enjoined defendants United States Fish and Wildlife Service (“FWS”) and the intervening, utility defendants -- Dairyland Power Cooperative and ITC Midwest LLC -- from closing on a land contract that would result in an exchange of parcels adjacent to the Refuge would proceed, with part of the Refuge, as well as immediate construction of the remaining towers on what is now part of the Refuge.

The court then held a hearing on plaintiffs National Wildlife Refuge Association, Driftless Area Land Conservancy and Wisconsin Wildlife Federation’s pending motion for a preliminary injunction (dkt. #60) on March 22, and on March 25, entered an order granting that motion, at least until the court could review the full administrative record considered by the federal defendants in approving the land exchange agreement. The court’s preliminary injunction order prohibits the federal and utility defendants from

taking any action to close on the land exchange agreement or begin construction on the stretch of the Cardinal-Hickory project running through the Upper Mississippi River National Wildlife and Fish Refuge. (Dkt. #62 and Dkt. #63.) The utility defendants filed an appeal with the Seventh Circuit, followed by a motion in this court under Rule 62(d) of the Federal Rules of Civil Procedure to stay the preliminary injunction order pending resolution of the appeal (dkt. #71), arguing they

should be permitted to consummate a land exchange with FWS and build the final portion of the Cardinal-Hickory transmission line while the parties brief summary judgment and any further appeals. The utility defendants later filed a similar stay motion in the court of appeals, without waiting for a ruling from this court, although the Seventh Circuit issued an order deferring its ruling on the motion to stay until this court could timely address it.

Because the utility defendants have not shown that their likelihood of success on the merits of their appeal outweighs the near certainty of irreparable harm to the Refuge, and because the balance of equities weighs in favor of judicial review (albeit expedited) with a complete administrative record and against staying the preliminary injunction order, the court will deny the utility defendants’ motion to stay pending appeal.

OPINION In deciding whether to stay an injunction pending appeal, the court considers four factors: “(1) the likelihood the applicant will succeed on the merits of the appeal; (2) whether the applicant will be irreparably injured absent a stay; (3) whether issuance of the stay will substantially injure other parties; and (4) the public interest.” Common Cause Indiana v. Lawson, 978 F.3d 1036, 1039 (7th Cir. 2020). “The standard calls for equitable

balancing, much like that required in deciding whether to grant a preliminary injunction” in the first place, but the “first two factors are most critical.” (Id. (quoting Venckiene v. United States, 929 F.3d 843, 853 (7th Cir. 2019)). The utility defendants contend that they are likely to succeed on the merits of their appeal because the court’s March 21 text order and its March 25 preliminary injunction decision do not comply with Rule 65(d)(1)(A)’s requirement to “state the reasons why [the

injunction] issued or Rule 52(a)(2)’s requirement to state the “findings and conclusions” supporting a preliminary injunction. See In re Jimmy John's Overtime Litig., 877 F.3d 756, 770 (7th Cir. 2017) (“Before issuing an injunction, a judge must identify the appropriate legal standard and make the findings of law and fact required by that standard.”) (citations omitted).1 The utility defendants further contend that the court issued the two preliminary injunction orders without providing any justification in law or fact. Neither argument is particularly persuasive. As the Supreme Court has explained, the purpose of a preliminary injunction is “to balance the equities as the litigation moves

forward.” Trump v. Int'l Refugee Assistance Project, 582 U.S. 571, 579 (2017). Thus, “[c]rafting a preliminary injunction is an exercise of discretion and judgment, often dependent as much on the equities of a given case as the substance of the legal issues it presents.” Id. The court’s preliminary injunction rulings in this case to date have each been tailored in time and scope to the specific circumstances before it, balancing the equities between the parties as this litigation proceeds.

Turning first to the March 21 text order, the court’s purpose in issuing that order was to ensure both sides, and defendants in particular, would have the opportunity to present evidence and argument (in writing and at an evidentiary hearing) before the court addressed plaintiffs’ request for emergency injunctive relief. Moreover, in its initial response to plaintiffs’ motion for a TRO, defendants conceded that construction on the transmission line in the Refuge would begin as soon as the land exchange agreement closed.

(Dkt. #15, at 4.) Given the exigent circumstances, the court felt compelled to act to preserve the status quo, even though the court strongly prefers to hear from both sides of

1 The parties spend a significant amount of time arguing whether this court retains jurisdiction to amend its preliminary injunction orders or “cure deficiencies” while an appeal is pending. However, the court does not intend to amend or modify its preliminary injunction order at this time. Regardless, it is entirely appropriate for this court to address the arguments raised by the defendants’ motion to stay, particularly since the Seventh Circuit has directed this court to do so. Accordingly, the court will deny both sides’ request to file additional briefs on this issue. (Dkt. #81 and Dkt. #86.) a dispute before providing any emergency relief. Here, in particular, the court found that there was sufficient time to convert plaintiffs’ TRO motion to a motion for a preliminary injunction so that both sides of the dispute could be heard. (3/11/24 Trans. (dkt. #37) 4.) Thus, the court denied plaintiffs’ motion for a TRO, converted the motion to one for a

Free access — add to your briefcase to read the full text and ask questions with AI

National Wildlife Refuge Association v. Rural Utilities Service, (W.D. Wis. 2024).

National Wildlife Refuge Association v. Rural Utilities Service (National Wildlife Refuge Association v. Rural Utilities Service) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Neringa Venckiene v. United States
929 F.3d 843 (Seventh Circuit, 2019)
Common Cause Indiana v. Connie Lawson
978 F.3d 1036 (Seventh Circuit, 2020)
In re Jimmy John's Overtime Litigation
877 F.3d 756 (Seventh Circuit, 2017)