National Surety Corporation, a Corporation v. Curators of University of Missouri Ex Rel. Paul Mueller Company, a Corporation

268 F.2d 525, 1959 U.S. App. LEXIS 3529
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 6, 1959
Docket16169
StatusPublished
Cited by14 cases

This text of 268 F.2d 525 (National Surety Corporation, a Corporation v. Curators of University of Missouri Ex Rel. Paul Mueller Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Corporation, a Corporation v. Curators of University of Missouri Ex Rel. Paul Mueller Company, a Corporation, 268 F.2d 525, 1959 U.S. App. LEXIS 3529 (8th Cir. 1959).

Opinion

VAN OOSTERHOUT, Circuit Judge.

This is an appeal by defendant, National Surety Corporation, on the performance bond given to the Curators of The University of Missouri on behalf of. C. Wallace' Plumbing Company, Inc. (Wallace), general contractor for the heating, ventilating, and air conditioning work on a Teaching Hospital building being erected.at the University of Missouri, from judgment rendered against it upon such bond in favor of plaintiff, Paul Mueller Company, for an alleged unpaid balance due On its subcontract with Wallace. Defendant admits that it is obligated by its bond to pay any sum that may be justly due plaintiff on its subcontract. This suit is against the defendant surety only. ‘ Jurisdiction exists by reason of diversity of citizenship and. the requisite jurisdictional amount.

The liability of the defendant is dependent upon the liability of its principal, Wallace, to the plaintiff. The defendant denies that there is any balance due plaintiff on the subcontract. The subcontract here in controversy calls for the payment of $176,101. This sum has been paid plaintiff .except for the $3,277.-36 involved in this action, for which amount judgment has been entered. ■

Defendant’s defense is that the plaintiff by its subcontract, among other things, agreed to “balance the air distribution system” in accordance with paragraph 100(e) and (f) of the plans and specifications; that plaintiff failed to* fully perform such duty; and that upon plaintiff’s refusal to do such work Wallace had the disputed work done by others and back-charged the cost thereof to the plaintiff.. The. reasonable cost of the back-charged work exceeded the amount withheld by Wallace. Thus, as stated by the plaintiff in its brief, the sole issue in this case is whether or not the Mueller Company, in carrying out its subcontract with Wallace, did “balance the air distribution system” as required by the subcontract. If plaintiff by its subcontract obligated itself to perform the disputed work, hereinafter more specifically described, it is not entitled to recover. If plaintiff was not required to do: such work, the judgment must be affirmed.

Wallace held the general contract for heating, ventilating, and air conditioning the hospital. The plans and specifications were made part of its cojitract with the Curators, and Wallace was required to perform all work in the manner required by such plans and specifications. The written subcontract here in controversy signed by Wallace and the Mueller Company, so far as here material, provides :

“Paragraph First: The subcontractor agrees to furnish all material and labor for all work as hereinafter described in accordance with the general conditions, plans and specifications * * * all of which general conditions, drawings and specifications * * * form a part of a contract between the contractor and the owner and hereby becomes a part of this contract. Subcontractor agrees to perform this contract to the entire satisfaction of the Architect and/or Engineer and Contractor.
“Paragraph Twenty-fourth: Both parties to this contract have read and understood this contract, afid all agreements prior to the date hereof are merged herein. The work included in this contract is: To perform the following work in strict accordance with part B of the plans * * *
“A. Furnish and install work described in Paragraphs 72, 73, and 75; furnish and install flashing for duets' through the roof, stainless steel insulation jackets, copper pans *527 for electric filters, and accoustic duct lining.
“B. Install only, that equipment described under Paragraphs 74, 76, 79, 80(b), 81, 82, 83, and 84 and Dampers and Vibration Isolaters.
“C. Balance the Air Distribution System in acccordance with Paragraph 100, Subparagraphs (e) and (f).”

The real controversy in this case relates to the obligation assumed by plaintiff by paragraph Twenty-Fourth C, above quoted. The section of the plans and specifications referred to in Twenty-Fourth C reads as follows:

“100. Testing and Adjustment: * -X- -x-
“(e) Balance the air flow in each air system to produce the quantities shown on the drawings. Adjust all volume dampers and registers in both supply and vent duct work and take anemometer or ‘velometer’, or other approved readings of all supply and vent registers and grilles, with simultaneous static pressure readings at each fan suction and discharge. At least three readings shall be taken at each opening. The total cubic foot delivery of all openings, plus five per cent shall equal the delivery of the respective fan. Instruments used shall have been factory calibrated within the year in which the test is made.
“(f) Provide lists in duplicate with the following:
“1) Air readings at each opening indicating velocity and c.f.m. before balancing and after final balance and c.f.m. required.
“2) Nameplate data — Fans and Motors (Identify).
“3) Voltage readings (Identify).
“4) Current readings — Fans (with belts on and off).
“5) Wet and dry bulb readings of leaving air at coils (readings at both ends of coils) and simultaneous entering air wet and dry bulb temperatures, and freon suction and discharge pressures.

“6) R.P.M. Readings — Fans.”

Other subparagraphs of paragrah 100, not material here, refer to other tests and adjustments to be made of the air conditioning equipment.

Plaintiff concedes that it was required to do the work described in paragraph 100(e) and (f)l. It has performed such work. Plaintiff has not performed the work described in paragraph 100(f)2 to 6, inclusive, and denies that it is obligated to perform such work, plaintiff's contention being that its testing and adjustment duties under its subcontract are limited to those described in paragraph 100(e) and (f) which fall into the category of “balancing the air distribution system,” and that items set out in 100(f) 2 to 6, inclusive, do not fall into such category.

This case was tried to the court. The court found that the plaintiff was not required to do the work listed in paragraph 100(f) 2 to 6, inclusive, and hence plaintiff was entitled to the unpaid balance claimed on the subcontract and judgment was entered therefor.

The court made no findings of fact except such as appear from his reported remarks made at the close of the evidence. We find nothing therein which expressly determines that the subcontract is ambiguous with reference to the disputed work here involved. The court did say, “I am impressed with the thought that about the only issue is to determine what is meant in the trade or profession, or whatever area you use, as the criterion of the words ‘balance the air distribution system.’ ” The court then in effect found from conflicting oral evidence of experts that “balance” is limited to the type of work which sheet metal workers usually claim, and that the work listed in 100(f)2 to 6, inclusive, is not work claimed by sheet metal workers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olah v. Ganley Chevrolet, Inc.
946 N.E.2d 771 (Ohio Court of Appeals, 2010)
Williams v. Spitzer Autoworld Canton, L.L.C.
2009 Ohio 3554 (Ohio Supreme Court, 2009)
Magnetic Copy Services, Inc. v. Seismic Specialists, Inc.
805 P.2d 1161 (Colorado Court of Appeals, 1990)
Taylor v. Richardson
432 A.2d 1307 (Supreme Judicial Court of Maine, 1981)
Ray Slotkin v. Edward W. Willmering
464 F.2d 418 (Eighth Circuit, 1972)
Melton v. Ensley
421 S.W.2d 44 (Missouri Court of Appeals, 1967)
Roan v. Reynolds
364 S.W.2d 763 (Court of Appeals of Texas, 1963)
United States v. Smith
182 F. Supp. 44 (W.D. Missouri, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
268 F.2d 525, 1959 U.S. App. LEXIS 3529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-corporation-a-corporation-v-curators-of-university-of-ca8-1959.